Resolved that- : (i) Liverpool City Council acts as Accountable Body for £500,000 additional Objective One ERDF funding in respect of the LLDC Operating costs project; (ii) on the receipt of an offer letter from the Government Office North West that:- · authority be granted for the Executive Director (Resources) to accept total ERDF grant of up to £2,020,000 towards the cost of delivering the project; and · the Divisional Manager (Regeneration Policy and Programmes) be appointed as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises; and (iii) further reports to be submitted to Members as and when appropriate to update on progress. EDE/4
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
1. Liverpool Land Development Company (LLDC) was established by the City Council, North West Development Agency (NWDA), and English Partnerships (EP) as a vehicle to develop and bring forward key SIA projects. It was modelled on the Speke Garston Development Company with a remit to operate in non-city centre SIAs in Liverpool for the duration of the 2000 – 2006 Objective One Programme.
2. The majority of LLDC’s capital resource is provided by NWDA and EP in the form of grants and land, along with ERDF and LTP monies (through the City Council). Through the LLDC Business Plan the City Council has committed to provide resource to meet LLDC annual operation costs, which in 2003 were circa £1.300,000 and for 2006/07 are estimated at £1.498000.
3. In April 2003 the City Council was awarded £1,520,000 ERDF towards the operating costs of LLDC. The award was over a 3 year period against total costs of £3,688,000 and recognised the central role that LLDC would play in developing SIA projects.
4. Although LLDC has been successful in developing several high profile projects it is clear that some key projects, such as Edge Lane and Liverpool Science Park, are still a long way from completion. We have therefore approached GONW to seek a further ERDF contribution towards LLDC operating costs.
5. Although initially reluctant to provide additional support – they believe that the £1.500,000 already awarded is commensurate with the level of support given to development activity in the other SIAs – GONW have now agreed to provide a further £500,000 over a 2 year period. This in part reflects the performance of LLDC to date in developing projects that involve £62,000,000 public expenditure with financial leverage of £313,000,000.
6. This would be by way of an extension to the existing approval, resulting in revised ERDF approval of £2,020,000 against total cost of £6,284,000.
Executive Member/Director recommendation. Acting Executive Director for Regeneration, Ben Dolan –
That Members agree that:
1. Liverpool City Council acts as Accountable Body for £500,000 additional Objective One ERDF funding in respect of the LLDC Operating costs project.
2 On the receipt of an offer letter from the Government Office North West that:
(a) Authority be given to the Executive Director Resources to accept total ERDF grant of up to £2,020,000 towards the cost of delivering the project.
(b) The Divisional Manager for Regeneration Policy and Programmes is appointed as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises.
3. Further reports to be submitted to Members as and when appropriate to update on progress.
Key Decision: Yes
Forward Plan: Yes
Implementation effective from: date of acceptance of revised offer letter (estimated to be mid May)
Timescale for action: The project extension will support LLDC operational costs until June 2008
Reason(s) for Recommendation:
To secure an additional £500,000 ERDF to support the operational costs of LLDC. Alternative options to be considered:
There was no alternative option to be considered. The City Council is committed to meeting LLDC operational costs and the additional ERDF on offer will help to meet that commitment.
Consultation
The following have been consulted and are content that the additional £500,000 ERDF grant should be accepted.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.