Resolved that in relation to the Strand project - (i) permission be given to proceed with Stage 1 of the project; (ii) authority be given to the Interim Executive Director (Regeneration) to accept a capital grant from NWDA of £ 1,274,360 and from private sources ( Grosvenor ) up to a figure of £353,073 to facilitate the financing of the Stage 1 scheme. The City Council will thereby accept the role of accountable body for the NWDA grant; (iii) the City Council’s 2006/07 capital programme be adjusted to reflect a revised expenditure profile for Stage 1 of the scheme totalling £1,627,433 financed by - · 2006/07 NWDA funding £ 1,274,360 · 2006/07 Private funding ( Grosvenor ) £353,073 (iv) authority be given to accept the target cost sum of £1,264,048 from Aggregate Industries UK Ltd (trading as Kennedy Asphalt) for the Stage 1 scheme; (v) the City Centre Projects Team Manager be appointed as the nominated Officer for monitoring compliance with the terms and conditions of the NWDA grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises; (vi) members approve the transfer from the revenue budget, of the sum of £353,073 received from Grosvenor as a revenue contribution via a S106 agreement, to finance corresponding capital expenditure; and (vii) in order to facilitate Stage 2 of the scheme, a sum of £330,000 of 2007/08 general capital resources be allocated to the Strand project, thereby being a first call on the resources allocated to the CCMS/ Transportation capital programme within the 2007/08 capital planning round.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
The Masterplan Report that was presented to the Executive Board identified major public realm works with extensive highway remodelling in support of public realm improvements on the Strand corridor. The objectives of the Masterplan are to create high quality public spaces, improve pedestrian linkages between the City Centre and the Waterfront and also to establish a traffic management system which can accommodate the anticipated growth in traffic volumes.
In the presentation to Members, it was identified that not all of the Masterplan proposals could be implemented together along the Strand corridor due to the extent of various works associated with PSDA and the available budget. It was therefore proposed that the first area to be improved would be the length of the Strand between Mersey Queensway Tunnel Exit and the Mann Island/James Street junction.
It has been agreed to implement the scheme in two stages: stage 1 between Mersey Queensway Tunnel exit and Brunswick Street; and stage 2 between Brunswick Street and Mann Island/James Street junction. Stage 1 will be undertaken in 2006/07 and permission is being sought by this report to proceed with this element of the project. It is anticipated, that subject to a complete funding package being identified, stage 2 will be undertaken in 2007/08.
The overall funding cocktail for the scheme comprises City Council general capital resources, NWDA funding and private sector funding.
Transport capital programme funding was approved on 05 August 2005 within the report setting out the overall transportation capital programme for 2005/06 (REG/25 minute 3216 refers). It was planned to commence detailed design work in 2005/06 to enable the construction to commence, subject to approvals, in May 2006. City Council general resources are also anticipated for stage 2 works. On 24 March 2006, approval of the NWDA contribution for Phase 1 works was received in the sum of £1,274,360.
In addition to this, Grosvenor is to make funding contributions to the scheme through S106 and S278 agreements for the PSDA development.
Due to the funding cocktail being proposed and project cost constraints, it is proposed that construction of stage 1 would commence in 2006/07 and that stage 2 is value-engineered to match the funding available. Discussions are currently taking place with Grosvenor over their S278 contribution for stage 2 element, the improvement of James Street junction. These negotiations will be resolved before construction is due to commence in April 2007, however Grosvenor may decide to undertake these works. If this turns out to be the case, the Grosvenor funded elements will not impact on the Council’s capital programme.
The proposals meet the following Masterplan objectives:- • To create an attractive pedestrian environment; • To improve pedestrian access between the city centre and the Waterfront; • To ensure better traffic management by rationalising traffic movements; • To ensure appropriate capacity as part of the Strategic Highway Network; and • To accommodate development proposals and public transport requirements.
Executive Member/Interim Executive Director recommendation: Cllr. Millea, Cllr Turner / Ben Dolan
That, in relation to the Strand project:
1) permission is given to proceed with Stage 1 of the project;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.