Resolved that – (i) the lowest tender in the sum of £249,563 for the construction of a new library and ICT room extension at Woolton Junior School be accepted and the City Council enter into a contract with Gawne and Roberts Ltd; (ii) the City Council incur professional fees of £37,000 from 20:20 Liverpool, plus residual costs of £4,440 and disbursements of £10,850; and (iii) the Capital Programme be amended accordingly. CHS/5
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
The purpose of the report is to seek approval to accept a tender for the construction of a new library and ICT room extension at Woolton Junior School.
Background
As part of the programme of suitability works to schools – a key element of the asset management planning process – a proposal to create a library and extend the ICT suite to accommodate a full class was agreed with the Asset Management Group in 2005. On 17 March 2006 the Executive Board approved the establishment of a budget of £310,000 within the Children’s Services Capital Programme for the project.
In accordance with Standing Orders tenders for the proposed works were invited from 5 firms and returned to the City Council on 4th April 2006. The lowest priced tender received was from Gawne and Roberts Ltd in the sum of £249,563. 20:20 Liverpool have checked the priced schedule submitted by the lowest tenderer and have confirmed that there are no arithmetical errors and the price submitted is competitive and represents value for money.
Interim Executive Director recommendation: Stuart Smith recommends that –
(i) the lowest tender in the sum of £249,563 for the construction of a new library and ICT room extension at Woolton Junior School be accepted and the City Council enter into a contract with Gawne and Roberts Ltd;
(ii) the City Council incur professional fees of £37,000 from 20:20 Liverpool, plus residual costs of £4,440 and disbursements of £10,850; and
(iii) the Capital Programme be amended accordingly
Key Decision: Yes
Forward Plan: Yes Implementation effective from: 7 July 2006
Timescale for action: Subject to Member approval the project could start in July with a contract length of 18 weeks
Reason(s) for Recommendation:
The works outlined in the report relate to priorities of the Children’s Services capital programme reflecting strategic as well as asset management issues.
Alternative options considered: Various alternative design options were looked at for the ICT suite extension and library including internal remodelling of some existing class bases. However, these options were dismissed because of cost and lack of space.
Consultation
The project was considered a priority by the Asset Management Group and has been developed in conjunction with the school and agreed with its governors.
Consultation with Ward Councillors: Ward Councillors have been advised of the proposals and no comments have been received.
Financial implications
At the Executive Board of 7 March 2006 a budget of £310,000 was established for the project. The tender price, fees and disbursements are within the available budget.
The total costs of the project are:
Construction costs - £249,563 20:20 fees and residual charges - £ 41,440 Disbursements - £ 10,850 £301,853
To be funded by the approved budget financed by DfES capital grant.
There are no revenue implications associated with this report. Best Value: The works have been procured by competitive tender in compliance with standing orders and the recommended tenders represent the lowest priced tenders for the projects described.
Equality implications
The project is designed to ensure compliance with the requirements of the Disability Discrimination Act 1995 to provide equality of access to appropriate areas of the curriculum.
Corporate strategy:
The Education Capital Programme is intended to assist in the delivery of the aim of raising educational standards through the provision of improved learning environments in turn supporting the delivery of the outcomes set out in the Every Child Matters agenda.
Budget and Policy Framework: The programme is within the Portfolio’s budget and policy framework.
Community safety implications: None associated with this report
Neighbourhood Management Implications: None associated with this report
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.