Executive Board, Friday 30 June 2006

Revised Waste Management Arrangements (EH/3)

Approved Executive 1 paper

Executive Board approved this item on Friday 30 June 2006. Below is the council's own wording, with the papers it was decided on.

Item21a

Resolved

Resolved that – (i) a negotiated exit from the existing recycling contract be effected; (ii) approval be given to officers to negotiate and enter into a two year extension to the Council’s existing refuse collection contract with Veolia (Onyx); (iii) approval be granted to officers to negotiate a contract variation for the transfer of the Council’s fortnightly kerbside recycling services to Veolia (Onyx) and enter into a contract for 2 years; (iv) subject to the approval of leasing arrangements via recommendation to the Executive Board, the procurement of 100,000 green wheeled bins be commenced, the distribution of such bins to each garden property in the City currently serviced by the Councils green waste collection service and the commencement of the new collection arrangements on the completion of such roll out; (v) subject to the approval of leasing arrangements via recommendation to the Executive Board, the procurement of 100,000 blue wheeled bins for the collection of multi-materials (to replace the current bag and box containers, in those properties with sufficient space to accommodate a second or third wheeled bin) be commenced; (vi) approval be granted to officers to negotiate a two year extension to the existing Bulky Bob’s contract subject to the agreement of satisfactory terms and conditions; (vii) approval be granted to commence the procurement of an integrated waste service provider to begin in late 2008/2009 and the issue of an OJEU notice; (viii) negotiations commence with MWDA to ensure that any new Materials Recycling Facility (MRF plant) is commissioned in a suitable location for the Council in time for its appointment of a new long term waste management services partner; (ix) reductions in the MWDA levy resulting from future changes to the payment of recycling credits are vired to finance the recycling service should there be any shortfall in Regeneration Portfolio resources as a result of the reduction in recycling credits; and (x) the report be referred to the Waste Management Scrutiny Panel of the Green Environment and Heritage Select Committee for scrutiny. NH/8
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 15 pages

Executive summary

Major Step Forward The Council has made major improvements in recycling performance since the £500,000 investment made by the Authority to the introduction of kerbside recycling in 2003/2004. This has seen a five fold increase in recycling performance for the Council, coming a long way in a short time from 1.9% in 2002/2003 to 10.7% 2005/2006. This represents a significant step forward demonstrating the Authority’s commitment to the waste minimisation agenda.

This recent improvement in recycling performance provides an excellent platform to enable the Authority to build upon in the achievement of the very challenging increases in national recycling targets announced in May 2006 from 15% to 20% in 2007/2008 and further increases contained within the JMWMS to 33% in 2010, 38% in 2015 and 44% in 2020.

Enhanced Recycling Arrangements To achieve these very challenging targets will require the range of materials for recycling to be increased and changes to containment methods and revised collection arrangements to enable the service to respond successfully to the increased capacity. In order to fully maximise the potential recycling opportunities and engage every household across the City, the revised arrangements proposed will include for a variety of alternative storage and collection methods determined by local need and type of property.

The report attached recommends a number of variations to the existing contracts which, if approved, will allow the Council to improve the methods of containment and collection and increase the range of materials recycled to better respond to customer need and property type. A common factor within the collection methods of the best performing Authorities is a same day collection service for all waste and recycling. The proposed changes to the kerbside recycling service will involve some revisions to the day of collection for green waste, paper, cans and glass collection services but with the recycling collection frequency remaining on a fortnightly basis and the removal of domestic non-recyclable waste remaining on a weekly basis. The enhancements proposed for the fortnightly kerbside recycling service will provide a further opportunity for the social enterprises operating a recycling collection service within the city to be explored. The implementation of further changes to containment and collection methodologies will be done in consultation with social enterprises operating within the City to ensure all residents receive a consistent service irrespective of provider.

Governance The governance arrangements have also been reviewed as part of the variations to the existing contracts to strengthen the client arrangements with the development of a robust contract and performance management framework and the introduction of a Strategic Advisory Group to perform an enhanced scrutiny role.

The revised contract and performance management arrangements also facilitate change and review during the contract extension allowing the Authority to road test improved working practices and initiatives in neighbourhoods in advance of their inclusion within the new fully integrated waste management service to be procured in 2008.

The proposed new integrated waste management contract will draw together all collection activity within a single package, however the delivery will not be a one size fits all service. The service to residents will be configured to reflect customer need, locality and housing type, which in turn will be used to determine containment and recycling collection frequencies best suited to engage residents in recycling and waste minimisation.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Revised Waste Management Arrangements (EH/3)Report 15 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 20 attended
WB
Councillor Warren BradleyChair, present
DA
Councillor Dave AntrobusMember, apologies
PC
Councillor Paul CleinMember, present
FC
Councillor Flo Clucas OBEMember, present
MF
Councillor Marilyn FieldingMember, present
RM
Councillor Richard MarbrowMember, apologies
PM
Councillor Peter MilleaMember, present
MS
Councillor Mike Storey CBEMember, present
BT
Councillor Berni TurnerMember, present
KT
Councillor Keith TurnerMember, present
CH
Colin HiltonOfficer, present
PH
Phil HalsallOfficer, present

All 20 on the meeting page

On this subject at Liverpool

Search all
  1. Revised Waste Management Arrangements (EH/3)This decision
  2. Presentation - Waste Management Agenda - Interim revised ArrangementsAgreed
  3. Called In Item - Revised Waste Management Arrangements (EH/3)Approved

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies