Kensington Delivery Plan (R&T/15)

Agreed Executive 5 papers

Executive Board agreed this item on Friday 25 August 2006. Below is the council's own wording, with the papers it was decided on.

Item54f

Resolved

Resolved that – (i) the delivery and spending plan for Kensington NDC as agreed with the Government Office NorthWest for the financial year 2006/2007, be approved; and (ii) on the receipt of an offer letter from Government Office North West - (a) authority to be granted for the Interim Executive Director (Regeneration), to accept new KNDC grants up to £8,077,000 of which £4,550,854 is for revenue and £3,526,146 for capital schemes for financial year 2006/7; (b) the City Council accepts the role of the Accountable Body and ensure the grant is administered appropriately; (c) the capital and revenue budgets of the City Council be amended to reflect expenditure of £8,144,000 financed by NDC grant and other income.; (d) the Divisional Manager (Regeneration Policy and Programmes) be appointed as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises; (e) authority be granted to incur expenditure on this project in accordance with Standing Orders and Financial Regulations; and (f) authority be granted for the Interim Executive Director (Regeneration) to enter into contracts that are in excess of £150,000 for works in accordance with Section 8 Contract Standing Orders.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 8 pages

Executive summary

The report outlines the proposals and activities for the delivery programme for Kensington New Deal for Communities initiative. It sets out the spending plans and targets for the financial year 2006/2007 as agreed with the Government Office NorthWest.

The New Deal for Communities (NDC) is a government initiative to reduce the gaps, in terms of deprivation and inequality, between some of the poorest communities and the rest of the country. Liverpool City Council led the bidding process for Kensington to gain NDC status; Kensington received a lifetime programme funding allocation of £61.9 million for the period 2000-2010. The Council is the Accountable Body for the grant.

Kensington Regeneration, an unincorporated association, was set up to deliver the programme. It became operational in 2000. Kensington Regeneration is a partnership of local residents, agencies and service providers. It manages the programme through a multi sector Board and Committees. The Council as the Accountable Body is represented on the Board by Councillors Marbrow and Doran.

There has been good progress to date, KNDC regularly meet spend and output targets agreed with GONW and partners at the beginning of each financial year through the signing of a Delivery Plan.

Kensington Regeneration for the financial year 2005/06 achieved its total budget of £8,000,000 and a further additional grant of £510,000 thus spending a total budget of £8,510,000. Of which £4,683,189 was revenue and £3,826,811 was capital. This represents a 100% achievement. (This is subject to the annual NDC programme audit).

The additional capital grant was awarded from the 2005/06 National NDC Programme allocation. This grant enabled Kensington Regeneration to make a number of key property acquisitions within the Phase 2 Wavertree demolition area. This will support the HMRI rolling programme in the area. Since the Neighbourhood Renewal Area was declared in December 2004 a framework has been developed, led by the City Council, that will implement a range of physical interventions across the NDC area. The NDC area falls within the Wavertree Zone of Opportunity – one of the New Heartlands (HMRI) investment priorities. Currently the area is undergoing a variety of interventions;

• LCC Improvement Programme in Kensington Fields • Planned acquisitions programme which is progressing in the Edge Hill neighbourhood • Limited statutory interventions both in the Fairfield (Lomond / Grampian development) and Holly Road neighbourhoods

In addition the NDC partnership is supporting the needs of the BRM, refugee and asylum communities who make up over 14% of the NDC area’s population. Advice has been provided via the HEAT (Health Energy and Advice Team) project funded by NDC grant and the support of the Eastern Link and City Council’s Asylum and Refugee Support Teams. Also a housing study is being undertaken to identify the needs of the BRM community in the NDC area which will be published later this year.

Other Physical Improvement Programmes in the area include;

• A rolling programme of repairs to front walls and enveloping schemes worth over £770,000 has taken place in the Kensington Fields neighbourhood • The Tunnel Road housing scheme has received planning permission for 126 units. • Lomond Road in the Fairfield neighbourhood has received planning permission for 79 units and Bellway hope to be on site by end of August 2006 • Street lighting in partnership with Enterprise – Liverpool • Retail enveloping to the retail units in partnership with 2020.

The physical/environmental programme achievements included;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Kensington Delivery Plan (R&T/15)Report 8 pages DownloadRead as text
PDF
R&T.15 Kensington Del PlanReport 66 pages Download
PDF
R&T.15 Kensington appendix 1Appendix 1 pages Download
PDF
R&T.15 Kensington appendix 2Appendix 2 pages Download
PDF
R&T.15 Kensington appendix 3Appendix 6 pages Download

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Kensington Delivery Plan (R&T/15)This decision
  2. Kensington New Deal for Communities Delivery Plan 2009-2010 (SSC/8)Noted
  3. Kensington New Deal for Communities Delivery Plan 2008-09 (A&D/5)Noted
  4. Kensington New Deal for Communities Delivery Plan 2007-08 (REG/12)Noted
  5. Kensington New Deal Delivery Plan Programme 2006-07 Amendments (R&T/51)Noted
  6. The Kensington New Deal for Communities Delivery Plan 2005-06, Programme Amendments (RT/12)Noted

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies