Executive Board, Friday 25 August 2006

Lease of Premises (SC&CS/6)

Decided Executive 1 paper

Executive Board decided this item on Friday 25 August 2006. Below is the council's own wording, with the papers it was decided on.

Item54h

Resolved

Resolved that authority be granted for the Head of Property and Asset Management Services to enter into formal negotiations with Merseyside Fire and Rescue Service with regards to heads of terms on leasing part of a new build facility at the Toxteth Fire Station on High Park Street, for the provision of day support services to disabled and older people.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 6 pages

Executive summary

1. Background.

Liverpool City Council has modernised and improved its services over recent years, in particular to help achieve the vision to create a modern, cosmopolitan and confident premier European city, at the heart of a prosperous and confident region.

As part of this commitment, the Council has adopted a broad way forward for day services providing faster and easier access to a wider range of options for users and carers.

A report was submitted to Health and Social Care Select Committee on 16th February 2006 outlining the broad new day services model. The report introduced phase one of the project (North area) and development opportunities in other parts of the city (Central and South), whilst establishing the mechanisms for engagement with users, carers, staff and stakeholders.

2. The new day services model.

The aim of the ‘model’ is to bring about new and improved services which, in particular, seek to expand choice and availability of services within neighbourhood communities to better meet people’s needs.

It has been agreed that officers from within the Supported Living Portfolio will work in depth in one area of the city (North). Officers will utilise a range of facilities, partnerships and resources to apply the model in practice; in close partnership with users, carers, staff and wider stakeholders. This “learn as we go” model is being driven by an implementation group chaired by the Executive Director, Supported Living.

3. Implementation phases.

The day services model involves a major change and improvement programme and is being delivered in three phases. A phased approach will ensure that the programme is delivered in manageable stages, fully involve relevant stakeholders, and captures and rolls out best practice.

The timetable is as follows:

Phase 1: North (March – November 2006) Report findings from evaluation of demonstration project: December 2006

Phase 2: Central (Jan – July 2007)

Phase 3: South (August 2007 – Feb 2008)

The first phase of development involves the North Area due to the presence of existing good quality buildings, strong links with the neighbourhood management areas and the fact that reviews of service users are at an advanced stage.

Whilst the first implementation phase is in the North Area, it is recognised that development opportunities may present themselves in other areas scheduled for later implementation. It is recognised that such opportunities need to be investigated and developed as and when they arise. One such opportunity has arisen within the south central area of the city.

4. Development opportunity in the South Central area.

The Supported Living Portfolio currently has three day service buildings in the South Neighbourhood Management Area, two of which do not provide ideal accommodation. The two facilities in question are Sheila Kay Day Centre, a facility for older people, located on High Park Street; and the L8 Resource Centre on Harrowby Close, in the Granby area, for adults with learning difficulties.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Lease of Premises (SC&CS/6)Report 6 pages DownloadRead as text

At this meeting

Whole meeting

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies