Resolved

Resolved that – (i) the Liverpool Direct Limited’s (LDL) response to the ICT managed services specification as representing value for money, be accepted; (ii) LDL be appointed as the ICT consultants for Building Schools for the Future based on their response to the value for money exercise and their acceptance of the standard Partnership for Schools ( PfS ) contract documents. This acceptance be subject to successful completion of negotiation of the particular project specific requirements and their acceptance by PfS ; and (iii) a deed of variation be entered into which introduces a new clause in to the Service Provision Agreement with LDL which provides for the instruction of ICT Services for the BSF contract but subject to PfS compliant terms. SC&CS/9
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 6 pages

Executive summary

Background

In April 2006 Partnerships for Schools (PfS) accepted the City Council’s Procurement Business Case for BSF. This included:

• The procurement of a framework of construction partners

• The employment of our own joint venture partners for the delivery of ICT (LDL) and for technical support (2020). The agreement not to procure ICT in particular relied on LDL demonstrating a value for money solution and agreement to the PfS standard contract documents. 2020 also had to agree to the standard contract and should offer comparable market rates. A further report will deal with the 2020 partnership for BSF delivery.

The BSF Project Board commissioned a value for money exercise which was completed in July 2006. In September 2006 LDL agreed to accept the terms in the standard PfS ICT contract for design services and for the managed service. The detailed project specific contract will require on-going negotiations but the major terms are incorporated in the standard PfS documents.

1.2VfM Exercise

The City Council, PfS and the DfES require Liverpool Direct Limited to successfully complete a Value for Money exercise that demonstrates that the Council’s ICT partner will be able to provide a cost effective ICT Managed Service to schools within the BSF programme.

1.3VfM Process

An ICT managed service specification was drafted by the Council’s external ICT advisor, reviewed by PfS and the Council, and issued to LDL in May 2006. The specification identified the services required by the Council for schools within the BSF programme. LDL’s response to the VfM specification was submitted to the Council on 30 June 2006. LDL presented an overview of their VfM solution to the Council and PfS on 14 July 2006. In addition, a number of post-tender clarification meetings have taken place between LDL and the Council.

1.4Technical Evaluation

LDL have responded to the specification by proposing an area-wide ICT managed service that provides a robust framework for the delivery of an anytime/anywhere solution. Within the proposed architecture, learners, staff and other educational stakeholders will be able to access a learning platform, the core curriculum and management applications and their associated data from school, home or anywhere where access to the Internet is available. The architecture enables users to access the solution from a wide range of computing devices including laptops, desktops and thin-client devices.

LDL’s response to the overall specification has been reviewed and scored. In scoring the requirements, consideration was taken of industrial best-practice.

At the present time few BSF schemes have been costed out so it is not possible to guarantee that their proposed solution offers best value to the Council, however the costs seem reasonable when compared to similar ICT procurement exercises.

The PfS have accepted LDL’s submission as demonstrating value for money and the BSF Project Board of Liverpool City Council have recommended the Acceptance of LDL’s submission.

1.5Services to be provided by LDL

• Refurbishment projects - LDL are to determine what the Schools’ ICT requirements are and provide a complete ICT design. The Contractor will take LDL’s ICT design and construct it within the overall refurbishment. LDL will be required to compliance check the Contractor’s completed ICT works. LDL will have responsibility for any negligent defects in the design. The Contractor will have responsibility for any defects in the workmanship.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Building Schools for the Future: Liverpool Direct Limited Contract (CHS/16)Report 6 pages DownloadRead as text
PDF
CHS.16 bsf ldl contract diag AReport 1 pages Download
PDF
CHS.16 bsf ldl contract diag BReport 1 pages Download

At this meeting

Whole meeting

Who was there

12 of 18 attended
WB
Councillor Warren BradleyChair, present
DA
Councillor Dave AntrobusMember, apologies
PC
Councillor Paul CleinMember, present
FC
Councillor Flo Clucas OBEMember, present
MF
Councillor Marilyn FieldingMember, present
RM
Councillor Richard MarbrowMember, present
PM
Councillor Peter MilleaMember, present
MS
Councillor Mike Storey CBEMember, present
BT
Councillor Berni TurnerMember, present
KT
Councillor Keith TurnerMember, present
CH
Colin HiltonOfficer, apologies
PH
Phil HalsallOfficer, apologies

All 18 on the meeting page

On this subject at Liverpool

Search all
  1. Building Schools for the Future – Liverpool Direct Limited Contract (CHS/16)This decision
  2. Building Schools for the Future (BSF) Wave 6 Site Assembly (A&D/44)Approved
  3. Kingsley and St Silas Primary Schools - capital building works following completion of Phase 2a Primary Review (ESE/34)Approved
  4. Building Schools for the Future (Wave 2): King David Campus Scheme (ESE/40)Approved
  5. Building Schools for the Future (BSF)Agreed
  6. Presentation - Building Schools for the FutureAgreed

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies