Children’s Services Capital Programme - update October 2006 (CHS/20)

Decided Executive 1 paper

Executive Board decided this item on Friday 17 November 2006. Below is the council's own wording, with the papers it was decided on.

Item115g

Resolved

Resolved that – (i) authority be granted to increase the authorised expenditure on the contract for the rebuilding of the boundary wall at Alsop High School (BEERM45) to £420,730 and to increase the budget by £40,000 to be financed from the balance of Modernisation (Secondary) 2006/07. £8,500 of the budget to be phased into the 2007/08 financial year; (ii) authority be granted to increase the budget for the 2005/06 programme of electrical works on schools (BEERJ32) by £104,000 to be financed by £79,000 New Pupil Places funding 2006/07 and £25,000 Schools Devolved Formula Capital; (iii) authority be granted to increase the budget for the programme of playground re-surfacing in schools for 2005/06 (BEERP29) by £17,000 to be financed from the balance of New Pupil Places funding 2006/07; (iv) authority be granted to increase the budget for the single siting of Gateacre Comprehensive (BEEKN81) in connection with the settlement of the final account by £7,310 to be financed from the balance of Modernisation (secondary) 2006/07; (v) authority be granted to increase the budget for the programme of mechanical (heating and ventilation) works on schools for 2006/07 (BEESB74) by £262,000 to be financed by £232,000 Planned Maintenance Fund 2006/07 and £30,000 Schools’ Devolved Formula Capital; (vi) authority granted to re-phase £150,000 from the budget for the construction of a new kitchen and multi-purpose hall extension at Booker Avenue Infants and Junior School (BEESC15) into the 2007/08 financial year; (vii) authority be granted to increase the budget for the programme of mechanical (heating and ventilation) works on schools for 2004/05 (BEERD25) by £5,000 to be financed from the balance of the Planned Maintenance Fund 2006/07. (viii) authority be granted to increase the budget for the remedial works at Pinehurst Primary school (BEESE36) by £185,000 and to increase the authorised expenditure on the main contract with Allenbuild to £297,154 to be financed from – · £142,000 from the balance of the Devolved Formula Capital Surplus; and · £43,000 from the School’s Devolved Formula Capital (ix) authority be granted to increase the budget for Fountains Road Children’s Centre (BEERL67) by £6,200 to reflect the Early Services Grant; (x) authority be granted to re-phase the Devolved Formula Capital allocations as per the table included in the Executive Summary of this report; (xi) a budget of £1,100,000 be established to fund the cost of electrical works at 10 schools to be financed from – · £600,000 from the balance of New Pupil Places 2006/07; · £431,000 from the balance of Planned maintenance 2006/07; and · £39,000 Schools Devolved Formula Capital £400,000 of the budget to be phased into the 2007/08 financial year. (xii) a DfES Standards Fund Grant of £5,814,197 be accepted to finance the cost of the remodelling and refurbishment of Arnot Primary School to be phased as follows – · £1,000,000 – 2006/07; and · £4,814,197 – 2007/08 An allocation of £885,000 be set aside from the City’s Sure Start Capital Grant to fund the cost of a new Children’s Centre as part of the development and be added to the total ... view the full minutes text for item 115g CHS/21
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 9 pages

Executive summary

The purpose of the report is to seek authority to amendments to the Children’s Services Capital Programme set out in the report below, approval to capital allocations for the 2006/07 programme and the establishment of budgets for a number of projects to commence in 2006/07.

Project variances

The following project variations together with reasons are identified below:

1. Alsop High School, Boundary Wall – BEERM45

Increase in budget of £40,000 to reflect additional costs of adaptations to the pavement outside of the school gates including visirails, new paving and kerbing and increased costs in connection with the eradication of Japanese Knotweed. To be financed from the balance of Modernisation (Secondary) 2006/07. £8,500 of the total budget to be phased into the 2007/08 financial year to reflect the retention on the contract.

2. Electrical Works 2005/6 – BEERJ32

Increase in budget of £104,000 to reflect additional costs spread over electrical re- wire projects on 10 primary schools as a result of increases in the scope of works, and unforeseen expenditure. To be financed as follows:

• £79,000 - New Pupil Places 2006/07 • £25,000 - Schools Devolved Formula Capital

3. Playground Re-surfacing Programme 2005/06 – BEERP29

Increase in budget of £17,000 to reflect additional costs spread over projects on 8 schools following the settlement of final accounts. Costs reflect problems occurring on site such as additional excavation work over and above contingency allowances. To be financed from the balance of New Pupil Places funding 2006/07 4. Gateacre Comprehensive – single siting –BEEKN81

Additional accommodation was constructed at Gateacre Comprehensive following the closure of Lee Manor High School in July 2000. Whilst practical completion of all associated works was given several years ago the final account was only settled in August 2006 leaving a shortfall on the budget of £7,310. It is therefore recommended that the budget be increased by this amount to be financed from the balance of Modernisation (secondary) 2006/07.

5. Mechanical Programme 2006/07 – BEESB74

Increase in the budget of £262,000 to reflect increase in the tendered sums for works compared to the budget estimates used to establish the original budget of £500,000 approved at the Executive Board of 17 March 2006, together with the inclusion of two additional projects in the programme for this year. To be financed as follows: • £232,000 - Planned Maintenance Fund 2006/07 • £30,000 - Schools Devolved Formula Capital

6. Booker Avenue Infants and Junior school – new kitchen and multi-purpose hall extension – BEESC15

The budget for the project to be re-phased to reflect delays in a start on site due to slow progress from the utility company in the carrying out and completion of enabling works involving the laying of a new mains cable from the road.

It is therefore recommended that £150,000 of the current budget be phased into 2007/08.

7. Mechanical programme 2004/05 – BEERD25

The budget for the 2004/05 programme be increased by £5,000 to reflect additional costs over and above the contingencies allowed for on the programme upon settlement of final accounts. To be financed from the balance of the Planned Maintenance Programme 2006/07

8. Pinehurst Primary – remedial works – BEESE36

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Children’s Services Capital Programme: update October 2006 (CHS/20)Report 9 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 17 attended
WB
Councillor Warren BradleyChair, present
DA
Councillor Dave AntrobusMember, present
PC
Councillor Paul CleinMember, present
FC
Councillor Flo Clucas OBEMember, present
MF
Councillor Marilyn FieldingMember, present
RM
Councillor Richard MarbrowMember, present
PM
Councillor Peter MilleaMember, present
MS
Councillor Mike Storey CBEMember, present
BT
Councillor Berni TurnerMember, present
KT
Councillor Keith TurnerMember, apologies
CH
Colin HiltonOfficer, present
PH
Phil HalsallOfficer, present

All 17 on the meeting page

On this subject at Liverpool

Search all
  1. Children’s Services Capital Programme - update October 2006 (CHS/20)This decision
  2. Children's Services Scorecard and Performance HighlightsDecided
  3. Children's Services Cabinet Member UpdateAgreed
  4. Children's Services Cabinet Member UpdateAgreed
  5. Recruitment to post of Director of Children and Young People's ServicesApproved
  6. Arrangements for Transition from Children's Services to Adult ServicesAgreed

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies