Liverpool City Council
Executive Board, Friday 15 December 2006

12-14 St Domingo Grove (RES/34)

Decided Executive 2 papers

Executive Board decided this item on Friday 15 December 2006. Below is the council's own wording, with the papers it was decided on.

Item136b

Resolved

Resolved that the tender of £160,000, plus £8,000 surveyor’s fees and £6,400 legal costs, submitted by Frank Rogers Building Contractors Ltd for a 999 year lease of 12/14 St Domingo Grove, be accepted. SC&CS/12
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 4 pages

Executive summary

This report has been prepared by 2020 Liverpool Ltd. to seek authority to grant a new lease in respect of 12/14 St Domingo Grove, Liverpool L5 6RR.

Background

The property is located on the south side of St Domingo Grove about 75 m from the junction with Breckfield Road North. The property is situated about ½ mile from the Breck Road Shopping area and about two miles north east from Liverpool city centre.

The property comprises a pair of Victorian semi-detached three storey houses converted by the City Council in the mid 1980’s to 14 flats/ bed-sit units. The property is in poor condition and in need of repair and refurbishment. The property was declared surplus to requirement by the Executive Board on 6 January 2006.

The property lies in the HMRI area Stanley Park zone of intervention.

Current Position

2020 Liverpool invited tenders for a 999 year lease at a peppercorn rent, with a closing date of 11 October 2006.

During the marketing period the property was advertised in the Liverpool Echo on the 6 September 2006 and the 2020 Liverpool webpage.

The highest tender received was submitted by Frank Rogers Building Contractors Ltd, who offered £160,000 plus £8,000 surveyor’s fees and £6,400 legal costs. Frank Rogers Building Contractors Ltd proposes to demolish the existing building and subject to planning, develop the site with 8-10 two bed apartments.

The purchaser is required to refurbish/ redevelop the property within 30 months of the commencement of the lease.

2020 Liverpool Ltd certifies that this tender represents the best price reasonably obtainable for this interest as at 3 November 2006 and for a period of four months from this date.

Executive Member/ Executive Director recommendation (Cllr Keith Turner and Phil Halsall)

That the City Council accepts the tender of £160,000 (one hundred and sixty thousand pounds) plus £8,000 surveyor’s fees and £6,400 legal costs, submitted by Frank Rogers Building Contractors Ltd for a 999 year lease of 12/14 St Domingo Grove, Liverpool 5.

Key Decision?

No.

Forward Plan/5 days notice/special urgency:

No

Implementation effective from:

22 December 2006.

Timescale for action:

The Acting City Solicitor will be instructed to complete documentation at the earliest opportunity.

Reason(s) for Recommendation:

• Will produce a capital receipt. • Will lead to the redevelopment of this property and assist the Councils regeneration aspirations for this area. Alternative options considered:

Not to sell.

Consultation

The HMRI team has been consulted and they confirm that the property lies in the HMRI area and within a zone of intervention. The HMRI Team consulted the preferred residential development partner for the City Centre North area who did not wish to refurbish/ redevelop. They have further advised that support in general is given to the proposals.

The Manager for the North Liverpool Neighbourhood Management Team was consulted and in general supports the proposal.

Consultation with Ward Councillors and outcome:

The ward councillors were consulted by email dated 19 October 2006. Councillor Prendergast and Councillor McIntosh advised that they have no problem with the proposal.

Financial implications

Capital 2006/2007 Premium £160,000

Revenue 2006/2007 Surveyors Fees £8,000 Legal Fees £6,400

The premium contributes to the City Council’s capital receipts forecast and the surveyor’s fees and legal costs contribute to existing revenue budget targets.

Best Value:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
12-14 St Domingo Grove (RES/34)Report 4 pages DownloadRead as text
PDF
RES 34: St Domingo planReport 1 pages Download

At this meeting

Whole meeting

Who was there

14 of 17 attended
WB
Councillor Warren BradleyChair, present
DA
Councillor Dave AntrobusMember, present
PC
Councillor Paul CleinMember, present
FC
Councillor Flo Clucas OBEMember, present
MF
Councillor Marilyn FieldingMember, apologies
RM
Councillor Richard MarbrowMember, present
PM
Councillor Peter MilleaMember, present
MS
Councillor Mike Storey CBEMember, present
BT
Councillor Berni TurnerMember, present
KT
Councillor Keith TurnerMember, present
CH
Colin HiltonOfficer, present
PH
Phil HalsallOfficer, present

All 17 on the meeting page

On this subject at Liverpool

Search all
  1. 12-14 St Domingo Grove (RES/34)This decision
  2. Vacant Plot, 12-14 St Domingo Grove, Liverpool 5 (Everton Ward)Approved
  3. 31 St Domingo Grove, Liverpool 5 (Everton Ward)Approved
  4. Disposal of 17 St Domingo Grove (NH/4)Agreed
  5. Road Humps in the St Domingo Grove Area, Liverpool, 5Agreed

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies