Resolved
Resolved that approval be given to the closure of Langham Court, and decant status be awarded to the tenants. R&T/42
Executive Board approved this item on Friday 15 December 2006. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that approval be given to the closure of Langham Court, and decant status be awarded to the tenants. R&T/42
1. Langham Court Sheltered Housing Scheme is situated in Langham Street, Liverpool 4 which, in the Kirkdale Ward. 2. The scheme comprises 41 units of accommodation, 26 bed sits, 14 one bedroomed flats, and a two bedroomed flat for the scheme manager. 3. Currently 15 units are occupied and 26 are vacant 4. The scheme has been identified as not fit for purpose by the Older Persons Accommodation Strategy Report which was agreed by members in October 2001. 5. The scheme does not provide good quality accommodation as the bed sits are provided with a shared living and sleeping room and have shared bathing facilities. Bed-sit accommodation does not meet the tenants existing or future needs. 6. Due to low demand for flats in the scheme, the scheme has had a high percentage of vacancies and as such is included in the Suspended lettings category. Anti social behaviour in the area has resulted in the remaining tenants feeling increasingly vulnerable. Early closure and the re-housing of tenants to suitable alternative accommodation are therefore considered to be the only appropriate option. 7. Current tenants will be decanted to alternative sheltered accommodation, mainstream housing or residential care dependant on their needs and requirements.
Executive Member/Director Recommendation Councillor (Cllr Dave Antrobus/Tony Hunter):
That: approval be given to the closure of Langham Court, Liverpool 4 and decant status be awarded to the tenants.
Key Decision: No
Forward Plan: Not applicable Implementation effective from:
22nd December, 2006
Timescale for action:
On approval of the recommendations, the decant of tenants can begin. The decant process is likely to take approximately 18 months to complete.
Any tenant wishing to remain in sheltered housing will have a choice of local schemes or the option of accepting any alternative sheltered accommodation we have available across the city.
The time scale for action is extended as availability issues for those wishing to remain in the area needs to be taken into consideration.
Reason(s) for Recommendation
The council is about to complete the recommendations of the Older Persons accommodation strategy first commissioned in 2001 which produced a definitive review of the councils sheltered housing stock.
A number of schemes of which Langham Court represents the last, were identified as not fit for purpose and unsuitable for the continued use of older people, with their refurbishment considered not to be cost effective or desirable.
Langham Court consists predominantly of bed-sit type accommodation with shared bathing facilities, there is no provision of a lift for those living on the first floor and the heating system is of an electric underfloor nature which has no heating controls meaning its either on or its off.
The council having embarked upon a major decant, closure and demolition policy for the properties like Langham Court which were deemed unfit, invested heavily in the major refurbishment and improvement of its remaining sheltered stock and the difference in the quality of accommodation between Langham Court and the remaining buildings is stark.
All refurbished buildings consist of self contained one or two bed-roomed flats, some of which are fully adapted for disabled use, all schemes have a passenger lift and all are currently undergoing further Disability Discrimination Act (DDA) improvements.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Closure of Langham Court Sheltered Housing Scheme (SC&CS/12)Report | 4 pages | DownloadRead as text |
Follow Executive Board at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Apr 2010 | Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. | Approved | Open |
| 23 Apr 2010 | New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... | Decided | Open |
| 23 Apr 2010 | 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... | Decided | Open |
| 23 Apr 2010 | Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... | Approved | Open |
| 23 Apr 2010 | Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.