Resolved that – (i) the following constructors identified through the tender process – Balfour Beatty, AMEC and Norwest Holst - be confirmed as preferred partners and invited to complete negotiations on contract signature to the construction framework with the City Council as soon as possible; and (ii) the fees prescribed through the construction framework contract in relation to projects allocated to each of the constructors, detailed in Annex B, submitted, be approved and funded, up to the limit of £339,000 estimated, pending satisfaction of the conditions outlined subject to – · the details of the drawdown of funding from DfES and PfS being confirmed before the start of the financial year 2007/8, including confirmation that the funding covers legitimate advance fees incurred as a result of approval of the report submitted; and · appropriate Children’s Services budgets (capital or revenue) meet the cost of any abortive design work on individual schemes, incurred between approval and contract signature, that is not contained within the available Wave 2 Building Schools for the Future funding allocation. CHS/36
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
• outlines the results of a tender exercise to identify three preferred constructor partners to help deliver the BSF Wave 2 schemes; • seeks authority to secure contract signature between the City Council and the preferred constructor partners to a formal construction framework as the delivery vehicle for this • seeks authority to commit to the advanced design fees to be charged by the preferred constructor partners for design services associated with BSF Wave 2 projects allocated to them
subject to a number of conditions outlined below and prescribed in the recommendations section.
Background
The national Building Schools for the Future (BSF) programme aims to transform secondary education through a capital investment programme to re-build or refurbish all secondary schools. Liverpool has a confirmed allocation of £175.18m capital funding for Wave 2 of the programme, to deliver 7 capital projects which will re-build or re-furbish a total of 11 secondary schools. The related report CHS/03/07 provides further background and funding confirmation for this programme.
In Spring of 2006, DfES and Partnership for Schools (PfS) approved Liverpool’s Procurement Business Case to deliver its BSF programme using a combination of existing joint venture partnerships for technical & professional services and ICT services, combined with a construction framework which would provide constructor partners for this major capital investment programme. A key element of work on the BSF programme since then has been the development of this construction framework.
The development process for the framework has been as follows :
July 2006: Outline Business Case for Wave 2 BSF approved by DfES (previously reported in CHS/24/06
July 13 2006: BSF Bidders Day Around 100 potential constructor partners and other associated organisations attended an event involving LA officers, schools and partners like 2020 and LDL, addressed by both the Chief Executive and Executive Member Children’s Services, over the Wave 2 BSF proposals. The event was to market the City Council, schools and partners, and its ambitions for BSF, to the construction industry. Feedback on the event was very positive.
End July 2006: OJEU for Wave 2 BSF released
The OJEU and related Pre Qualification Questionnaire (PQQ) process generated 13 responses from the construction industry to be involved in the tender selection process for constructor partners. This was again a positive response set against other BSF offers nationally.
The long-list of applicants was short-listed to six after consideration of the response to the PQQ – a decision which was considered and approved by Elected Members serving on the BSF Project Board. These six constructors were invited to enter the next stage of the process, in an Invitation to Tender (ITT) document that invited tenders for the design and construction of a sample scheme – West Derby and Ernest Cookson’s new build proposal.
29 October 2006 – tender documentation released
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.