Resolved that – (i) the capital funding of £175.18m available for the overall Building Schools for the Future (BSF) Wave 2 programme be incorporated into the Council’s capital programme, and subsequent reports, follow to secure approval to the contract signature of each of the seven individual construction schemes; (ii) the proposed services to be provided for 2o2o’s role in Wave 2 of BSF, as detailed in Annexes A and B submitted, be approved; (iii) the proposed fees in relation to paragraph (ii) above, as detailed in Annex C, submitted be approved and funded, up to the limit of the £3.5M estimated pre-contract fees pending satisfaction of the conditions outlined below; and (iv) the City Council appoint 2o2o as a formal partner for the purposes of the delivery of Wave 2 of BSF through the issue of a Project Order for the services defined by Legal Services subject to the conditions that – · the details of the drawdown of funding from DfES are confirmed, including confirmation that the funding covers legitimate advance fees incurred as a result of approval of this report ; and · appropriate Children’s Services contingency budgets are established within the resources available to the Service, to meet the cost of any abortive design work on individual schemes, incurred between this approval and contract signature, that is not contained within the available Wave 2 BSF funding allocation. CHS/35
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
• Incorporate the overall BSF Wave 2 programme of seven school capital projects into the Council’s capital programme • Accept the proposed services to be offered by 2020 Liverpool in connection with the delivery of BSF Wave 2 • Commit to the advanced design fees to be charged by 2020 Liverpool for those services
subject to a number of conditions outlined in detail below and prescribed in the recommendations section.
Background
BSF Wave 2 Programme
The national Building Schools for the Future (BSF) programme aims to transform secondary education through a capital investment programme to re-build or refurbish all secondary schools. Liverpool now has been a confirmed allocation of £175.18m capital funding for Wave 2 of the programme, to deliver 7 capital projects which will re-build or re- furbish a total of 11 secondary schools (see Appendix 1 at the back of this report for both the funding confirmation letter from DfES and the Wave 2 programme details). The allocation is analysed and profiled across financial years in a little more detail in the Financial Implications section of this report. With funding confirmed and most likely available in 2007/8 financial year, and the programme entering an initial delivery stage, it needs to be incorporated into the Council’s corporate capital programme.
The wider context to the details of this report is that Liverpool has also been included in a future Wave 5 of BSF to complete investment in its remaining secondary school estate, covering around £300m more investment in the other 25 secondary–phase schools. This later wave of investment is subject to a detailed Business Case development over the next year and at the moment separate contractual arrangements with partners, including 2020, for its delivery, but will be shaped significantly by arrangements for Wave 2. 2020 Services
So far, 2020 has been providing technical support and other advisory services in the development of Wave 2 proposals through its existing joint venture partnership with the City Council. These costs have been sourced through existing Children’s Services revenue budgets as a revenue development budget for BSF. However, the City Council is about to contract to a legal construction framework for delivering BSF and 2020 needs to be recognised as the lead provider of professional services and advice in the detailed design and delivery of individual construction schemes funded by DfES/PfS.
In considering 2020’s proposed services for this programme, the related report CHS/04/07 outlining the preferred delivery model for Liverpool’s BSF as a construction framework needs to be noted. Briefly, this proposed framework is to be composed of the City Council, 2020 for professional and technical advice, LDL for the provision of ICT services, and three constructor partners. The seven BSF projects would be shared between constructors on the framework, such that some schemes will be allocated directly to one of the constructors to both design (using their own architectural partners) and build; while others would be allocated first to 2020 to provide architectural services immediately, and subsequently allocated to a constructor to build. 2020 will provide the City with general technical advice and a supervisory role for all the Wave 2 projects.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.