Resolved that - (i) the progress on the delivery and spend of year 6 of the Neighbourhood Fund project be noted; (ii) authority be granted to roll forward if necessary an amount of Neighbourhood Fund project funding into 2007/08, within the limits set by Government of a maximum of 5% of the whole NRF programme, and that the Executive Director (Regeneration) be authorised to determine the amount of roll-forward (in consultation with the Executive Members for Regeneration and Transport, and Resources and Liverpool First); (iii) authority be granted to allocate Neighbourhood Fund for 2007/08 to all Wards across the City as set out in Table 1 submitted; and (iv) further reports to approve new projects and to report on progress made and impacts achieved with the Neighbourhood Fund 2007/08 be presented to the Executive Board in due course.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
To report progress on the delivery of the 2006/07 Neighbourhood Fund project and to agree ward allocations for the Neighbourhood Fund project for 2007/08
Background
Liverpool has been allocated £31,069,066 Neighbourhood Renewal Fund (NRF) for Year 7 (2007/08). In January 2007, Liverpool First and Liverpool City Council approved a number of projects for inclusion in the NRF programme of which approximately £2.7m is being reserved for the Neighbourhood Fund. A sum of £280,000 is required for programme management and neighbourhood delivery capacity allowing £2,487,000 to be available for wards subject to agreement by Neighbourhood Committees.
The Neighbourhood Fund enables a focus on issues at a local level, addressing local priority projects while at the same time developing local decision making and ownership. This project will help to drive the development of local Neighbourhood Agreements which will set out key targets and priorities for investment and provide Neighbourhood Committees and local ward members with new and extra resources to deliver projects which they feel meet the most pressing concerns within their community and/or which might help bring more effective joint working for other partners to deliver the City’s Local Area Agreement.
Progress Year 6 (2006/07)
• At the 30/01/07, £1,647,994 of the £1,700,501 Neighbourhood Fund allocation for 2006/7 had been allocated to projects. Work continues between Committee Chairs and Neighbourhood Managers to agree projects to allocate the remaining resource and a scheme of delegation to the Executive Member and Director has been approved by Executive Board for all but the most innovative/contentious projects.
• Also, reported spend levels at the same stage were low with claims received at that date of £67,567 against the £1,700,501 allocation. A more up to date figure will be reported to Executive Members at the time of considering this report. The situation is being closely monitored by the Regeneration Programmes team right up to the end of the financial year.
• Deliverability issues in the timescales available give rise to a potential under spend on the year 6 programme, not least the differences in time taken by different committees and project management leads to agree the final programme for each ward. Secondly there were some tensions between what can be approved locally and quickly, what needed discussion at a citywide level requiring approval by the Executive Board. Overall, lack of time and capacity were the key impediments to delivering spend. As NRF is an annual grant from Government, funding must be spent by end of March 2007.
• LCC Executive Board and Liverpool First have agreed previously that only capital projects within the NRF programme are eligible to carry forward funding into the following financial year. This has previously been agreed on a case by case basis. However, the Neighbourhood Fund is a revenue based project.
• Due to the exceptional circumstances surrounding the implementation of this new project; the devolved decision making process, the new way of working - delivering neighbourhood projects within the context of the Local Area Agreement (LAA), the timescales involved and the late start to the programme as a consequence of the development of the LAA, it is recommended that LCC Executive Board in consultation with Liverpool First Board agrees to certain elements of the Neighbourhood Fund project carrying over resources into next year.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.