CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Liverpool City Council
Executive Board, Friday 16 March 2007

Mersey Waterfront Regional Park (R&T/58)

Agreed Executive 1 paper

Executive Board agreed this item on Friday 16 March 2007. Below is the council's own wording, with the papers it was decided on.

Item189c

Resolved

Resolved that – (i) the City Council continues its support and involvement in the Mersey Waterfront Regional Park and that the Acting City Solicitor be authorised to sign the Legal Agreement on behalf of the City Council; (ii) the Divisional Manager for Regeneration Policy and Programmes continues as the lead officer for Liverpool City Council, and; (iii) further reports be submitted to Executive Board in due course regarding any award of grant funding to Liverpool City Council from this programme. R&T/59
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 6 pages

Purpose of report

The purpose of this report is to confirm Liverpool City Council’s continuing support for the Mersey Waterfront Regional Park programme and involvement in it as a full partner. In 2003 Liverpool City Council (together with Sefton MBC and, Halton BC and The Mersey Partnership) signed a legal agreement with Wirral MBC (the Accountable Body for the programme). The new Succession Programme, continuing MWRP from 1st April 2007 to 31st March 2010 requires an extension of the original legal agreement.

Executive summary

Mersey Waterfront Regional Park (MWRP) was one of two “big ideas” which emerged from the Action Plan for the City Region 2002 – 2005, a sub-regional programme setting out key priorities for North West Development Agency (NWDA) investment in Merseyside to 2005. The concept - lead by The Mersey Partnership in collaboration with Merseyside Local Authorities continues to be a sub regional priority and is identified as a priority in both the Regional Economic Strategy and the City Region Development Plan. The current 3-year Inception Programme comes to an end on 31st March 2007

The Vision for Mersey Waterfront is to transform, energise and connect the Mersey waterfront and all its assets to create a unique sense of place that attracts people to live, work and invest in Merseyside. For Liverpool the work on the Mersey Waterfront can directly complement proposals for the Former Garden Festival Site, development on the Speke Garston Coast, the North- shore and Central Docks areas.

A clear rationale for the programme is the value added to be derived from a pan waterfront approach. This has materialised as follows:

• Via the injection of strategic thinking into the programme, where historically projects have been taken forward in a piecemeal fashion across different localities

• Proactively coming forward with ideas that take forward the pan waterfront agenda, as opposed to responding reactively to local partners

• Increasing connectivity across projects, emphasising complementarities across the waterfront and reducing any unhealthy competition where it exists.

• Providing a single, co-ordinated voice in shaping and influencing the spending and investment of wider partners.

• By acting as a pathfinder for other regional parks in the North West and elsewhere in the UK.

Cllr. Barbara Mace represents Liverpool City Council on the Board of MW.

THE MWRP COMMENCEMENT PROGRAMME:

The Commencement Programme formally started in April 2003, and was initially programmed to end in September 2005. It involved the deployment of some £8.54M of NWDA resources, matched with a further £40M of public and private sector expenditure. The Commencement Programme was extended to run for a further 18 months to March 2007 and with an increase in the level of NWDA resources (up by a further £330K) and an allocation of £13 Million of European Objective 1 funding.

SUCCESSES TO DATE:

The programme has so far delivered some 35 projects. A number of these are projects which have benefited Liverpool, those are;

• The Pride in the Promenades pilot. Circa £1.4 Million • Speke Garston Coastal Reserve £250k • Mersey River Festival; circa £500k of support in 2003/4 and 5. • A significant contribution £500K to the development of the Cruise Liner Facility and the marketing of such for the benefit of the sub-region.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Mersey Waterfront Regional Park (R&T/58)Report 6 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Mersey Waterfront Regional Park (R&T/58)This decision
  2. Mersey Waterfront Pride in our Promenades programme: physical improvements along the Leeds Liverpool Canal Corridor (REG/26)Agreed
  3. Mersey Waterfront - Pride in our Promenades (REG/37)Noted

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies