Resolved that – (i) the lowest tender in the sum of £5,887,009 for the refurbishment of Arnot Primary School and the development of an adjacent Children’s Centre be accepted and the City Council enter into a contract with Kier Northwest Ltd.; (ii) the City Council incur professional fees of £764,306 from 2o:2o Liverpool Limited, plus residual costs of £91,717 and disbursements of £90,000; (iii) the budget for the project be increased by £643,835 to reflect actual costs of the tender compared to original budget estimates to be funded from – · School’s Access Initiative Fund -£ 100,000; · Modernisation Primary Need -£ 476,335; · Arnot Primary DFC -£ 33,750; and · Walton St Mary’s DFC -£ 33,750; and (iv) the Capital Programme be amended accordingly. CHS/8
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
The purpose of the report is to seek approval to accept a tender for the redevelopment and refurbishment of Arnot Primary School, Walton and the construction of a new children’s centre.
Background
Arnot Primary is currently accommodated in a series of late Victorian buildings built since 1885. Originally included within the Liverpool School’s PFI Project, the proposed rebuilding of the school under the PFI Contract was deferred when Grade 2 listed status was conferred on the building in 2003. PFI credits approved for the scheme had amounted to £2.3m. However, its listed status meant that demolition and rebuilding was no longer possible and consequently the estimated cost of refurbishing and remodelling the school increased to nearer £6m and therefore not affordable under the PFI contract.
In 2006 the DfES finally approved an alternative business case for the proposal and agreed to the allocation of a Standards Fund Grant to finance the refurbishment of the school to be procured through a traditional building contract. The listed status protects the frontage of all the buildings facing Arnot street which would have meant under the original proposal, that part of the existing school, constructed when it was catering for much larger pupil numbers, would have had to have been ‘mothballed’. Instead it created the opportunity of converting the former infants’ kitchen and dining hall into a children’s centre for the County Ward using Sure Start Children’s Centre Capital allocated to the Authority for its phase 2 children’s centre programme. No other schools in the ward were considered suitable.
On 17 November 2006 the Executive Board approved the acceptance of a Standards Fund Grant from the DfES of £5,814,197 to finance the substantial remodelling and refurbishment of Arnot Primary School together with the allocation of £885,000 Sure Start Children’s Centre Capital for the construction of a new children’s centre co-located with the school.
The project will comprise the extensive refurbishment and remodelling of the main school building internally whilst retaining the Victorian façade to provide a new 2 form of entry primary school. The existing separate junior block is currently disused and will provide temporary accommodation for the pupils whilst the works are in progress. Towards the end of the main building contract the block will be demolished to create a significantly improved external play and learning environment. The Children’s Centre will provide the following core services:
• 48 centre based day care places for children aged 0-4 • Early Education for nursery age children integrated with day care • Family health and support including ante-natal • A base for a Childminder Network • Support for children with SEN or disabilities and their families • Job Centre Plus • Family Support and Outreach
Current Position
At the moment the first phase of ‘enabling works’, approved by the Executive Board on 5 January 2007, are due to be completed at the end of July. These comprise the re-roofing of the children’s centre and the fit out of the temporary accommodation.
In addition, on 9 May 2007 the School Organisation Committee gave the final approval to the closure of both Arnot Primary and Walton St Mary’s CE (controlled) primary with effect from 31 August 2008 with the a new CE controlled primary to be opened in the refurbished Arnot Primary buildings on 1 September 2008.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.