Resolved that – (i) the lowest tender in the sum of £426,708 for enabling works at Arnot Primary School be accepted and the City Council enter into a contract with Mansell Construction Services Ltd.; (ii) the City Council incur professional fees of £55,472 from 2o2o Liverpool, plus residual costs of £6,657 and disbursements of £1,000; and (iii) the capital programme be amended accordingly. CHS/28
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
On 17th November 2006 the Executive Board approved the establishment of a budget of £6,699,197 comprising DfES grant and Sure Start capital in connection with the refurbishment of the school and the development of a children’s centre on the site.
Prior to the start of the main building contract which is programmed for July 2007 it is necessary to carry out some enabling works at the school, principally to facilitate the decanting of staff and pupils into temporary accommodation. These works will comprise the refurbishment of the former 2 storey junior block adjacent to the main school building together with roofing works to the proposed children’s centre and existing foundation stage area.
In accordance with Standing Orders tenders for the proposed works were invited from 5 firms and returned to the City Council on 22nd November 2006. The lowest priced tender received was from Mansell Construction Services Ltd in the sum of £420,279. A list of technical queries was raised with Mansells and a response received on 29th November. The removal of loose furniture and the installation of CCTV had been omitted in error from the priced schedule and the tender was adjusted to £426,706 still 10% lower than the next lowest tender. 20:20 Liverpool has therefore confirmed that the price submitted is competitive and represents value for money.
Executive Director recommendation: Stuart Smith recommends that –
1. the lowest tender in the sum of £426,708 for enabling works at Arnot Primary School be accepted and the City Council enter into a contract with Mansell Construction Services Ltd.;
2. the City Council incur professional fees of £55,472 from 20:20 Liverpool, plus residual costs of £6,657 and disbursements of £1,000; and
3. the capital programme be amended accordingly. . Key Decision: Yes
Forward Plan: Yes
Implementation effective from: 12 January 2007
Timescale for action: Subject to Member approval the enabling works are due to start towards the end of January 2007. The contract period is to be 16 calendar weeks
Reason(s) for Recommendation: The works are required in advance of the main contract of works to ensure that the temporary accommodation that the school will decant into is ready for occupation by May 2007.
Alternative options considered: The decant into the empty junior block is considered to be the least disruptive and most cost effective option for the school. The DfES has also set fairly tight timescales for the commitment and phasing of the capital grant to the project requiring works to commence prior to the end of the financial year.
Consultation: Currently Arnot and Walton St Mary’s staff, parents and governors are being consulted regarding the proposed closure of both schools and the creation of a new Church of England Controlled Primary school in the Arnot building. This has been the subject of separate Board approval. The development of plans in connection with the refurbishment of the building will be carried out in discussion with both schools pending the outcome of the consultation on the re-organisation proposal.
Consultation with Ward Councillors:
County Ward councillors have been consulted about the proposals for the school and are supportive of them.
Financial implications
At the Executive Board of 17th November 2006 a budget of £6,699,197 was established for the refurbishment of the school and the development of the children’s centre comprising £5,814,197 Standards Fund Grant and £885,000 Sure Start Children’s Centre capital. The cost of the enabling works will be met from the budget for the scheme
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.