Resolved that - (i) a new 125 year lease (for the sake of clarity, 125 years and 5 days to allow the necessary reversion to facilitate the 125 year lease to MPTE) be taken from the Mersey Docks and Harbour Company of part of the intended site of the new terminal building as shown marked on the plan submitted for a nil premium and nil rent with each party paying their own legal and surveyors costs; (ii) the rent review due 16 March 2002 in respect of the existing lease of the Mersey Ferries Terminal to the Merseyside Passenger Transport Executive being revised to £20,000 per annum, be approved; (iii) the rent review due 16 March 2007 in respect of the existing lease of the Mersey Ferries Terminal to the Merseyside Passenger Transport Executive being revised to £25,000 per annum, be approved; and (iv) the surrender of the existing lease of the Mersey Ferries Terminal and the grant a new 125 year lease to the Merseyside Passenger Transport Executive at a rent being the higher of 7% of the market rental of the whole property or £30,000 per annum with five yearly rent reviews on the repositioned site identified on the plan submitted be approved. The new lease to include a 12 month rent free period to reflect the expected construction period and capital investment by MPTE and the payment of the Council’s reasonable legal fees up to £1,000 and on other terms as agreed by the Head of Property and Asset Management Services. REG/9
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
This report has been prepared by 2020 Liverpool Ltd. to seek authority to; (i) take a lease from Mersey Dock and Harbour Company (MDHC) of land at the Pier Head; (ii) accept the surrender of a lease to the Merseyside Passenger Transport Executive (MPTE) and (iii) grant MPTE a new lease of the sites comprised within (i) and (ii) above to facilitate the construction and operation of the New Mersey Ferries Terminal.
Background
The MPTE desire to build a new Mersey Ferries Terminal, new visitor attraction and complementary facilities at the Pier Head to replace the existing facility. This is one of several schemes on site or proposed at the Pier Head that will dramatically change and improve the public space and built environment.
At its meeting of the 1st December 2006, the Executive Board considered the detailed proposals required to facilitate the demolition of the existing buildings and construction of the proposed new terminal building. The Board accepted the recommendation to proceed subject to a further report being presented setting out the terms of the proposed disposal to MPTE.
Planning consent for the demolition of the existing terminal building and adjacent restaurant and the construction of the new ferry terminal was approved by the Planning Committee on 13 March 2007. The proposed scheme includes a ferries ticket office with ancillary office and retail areas, an ATM, a restaurant, café, and visitor attraction (exhibition/museum facility). MPTE will also have the right to seek the necessary consents to operate the café on the adjacent pavement.
This transaction has been negotiated by 2020 Liverpool Ltd., who certifies that the proposed acquisition from the Mersey Dock and Harbour Company and lease to the Merseyside Passenger Transport Executive represents the best price reasonably obtainable as at 29 June 2007 and for a period of four months from this date.
Executive Member/Acting Executive Director recommendation (Councillor Keith Turner/ Phil Halsall)
It is recommended that the City Council:
1. take a new 125 year lease (for the sake of clarity, 125 years and 5 days to allow the necessary reversion to facilitate the 125 year lease to MPTE) from the Mersey Docks and Harbour Company of part of the intended site of the new terminal building shown marked on the attached plan for a nil premium and nil rent with each party paying their own legal and surveyors costs;
2. Approve the rent review due 16 March 2002 in respect of the existing lease of the Mersey Ferries Terminal to the Merseyside Passenger Transport Executive being revised to £20,000 p.a. (twenty thousand pounds);
3. Approve the rent review due 16 March 2007 in respect of the existing lease of the Mersey Ferries Terminal to the Merseyside Passenger Transport Executive being revised to £25,000 p.a. (twenty five thousand pounds);
4. Approve the surrender of the existing lease of the Mersey Ferries Terminal and the grant a new 125 year lease to the Merseyside Passenger Transport Executive at a rent being the higher of 7% of the market rental of the whole property or £30,000 p. a (thirty thousand pounds) with five yearly rent reviews on the repositioned site identified on the attached plan. The new lease to include a 12 month rent free period to reflect the expected construction period and capital investment by MPTE and the payment of the Council’s reasonable legal fees up to £1,000 and on other terms as agreed by the Head of Property and Asset Management Services.
Key Decision?
No.
Forward Plan/5 days notice/special urgency:
No
Implementation effective from:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.