Resolved
Resolved that the recommendation, as amended, be approved. REG/10
Executive Board approved this item on Friday 20 July 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the recommendation, as amended, be approved. REG/10
1. Purpose The purpose of this report is to:
• inform Executive Members of the intention to progress an LLDC supported first phase of development at Stonebridge Park to provide new build light industrial space at the newly created Stonebridge Park on the East Lancs Rd. Successful completion of the project will create 5,304 sq mtrs new floorspace (57,100sqft), provide 84 years of construction employment, and accommodate up to 225 jobs.
• seek permission for the City Council to act as accountable body for ERDF funds on behalf of Key Property Developments Ltd / St Modwen Properties plc who will undertake the development. The total cost of the project is £4,565,669 and ERDF of £721,615 is being sought against eligible ERDF costs of £3,333,437. The balance of the funding is being provided by the developer.
Stonebridge Park is a new development opportunity of approximately 29ha situated on the A 580 East Lancs Road, Liverpool, within the A580 Strategic Investment Area. It occupies the former GEC site and the Sugarbrook sites, along with part of the NWDA owned Gilmoss Industrial Estate. Liverpool Land Development Company (LLDC) working in partnership with the NWDA has masterplanned the Stonebridge Park development and, using NWDA and ERDF funding, has provided access and site infrastructure to the site which is now being promoted as a new development opportunity.
LLDC has appointed a preferred developer Key Property Developments Ltd to take forward the development of the Stonebridge Park site. Key Property Developments are a subsidiary of St Modwen Properties PLC who have a strong track record in delivering commercial regeneration schemes. The appointment was a condition of St Modwen agreeing to sell its landholding which formed part of the Stonebridge Park land acquisition, to the NWDA. In addition in 1998 St. Modwen entered into a significant joint venture with Salhia Real Estate Co of Kuwait to establish an investment partnership with a potential £100million involvement.
3. Proposed Development
As a first phase Key Property Developments Ltd propose to commence a new build development as a gateway site, to act as a catalyst for a rolling programme of development over the whole site. It is this first element that is the subject of the ERDF application and involves 5,300m2 (57,100sqft) of industrial space compromising 4 units in two buildings. In line with ERDF regulations these will provide industrial / commercial / warehouse space but will exclude any retail use. The two new buildings will occupy plot 10 of the Stonebridge Park site and will be the first phase of development of the wider scheme. A planning application was submitted in January 2007. Working with LLDC / NWDA Key Property Developments have identified a gap between cost and value of these units of £721,615 and this application for ERDF is to secure gap funding of £721,615 to bridge the gap.
4. Proposed Agreement
It is proposed that the City Council acts as applicant and accountable body for the ERDF funds on behalf of Key Property Developments Ltd. A grant funding agreement , similar to that which the city has used in previous ERDF developments with the private sector, will be put in place between the city council and Key Property Developments Ltd to ensure compliance with ERDF terms and conditions.
Executive Member/Executive Director recommendation: (Councillor Mike Storey CBE/Councillor Keith Turner/Councillor Flo Clucas – Executive Director John Kelly)
That:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Stonebridge Park Development (REG/9)Report | 8 pages | DownloadRead as text |
Follow Executive Board at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Apr 2010 | Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. | Approved | Open |
| 23 Apr 2010 | New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... | Decided | Open |
| 23 Apr 2010 | 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... | Decided | Open |
| 23 Apr 2010 | Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... | Approved | Open |
| 23 Apr 2010 | Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.