Resolved that authority be granted for Officers to advertise the Council’s intention to dispose of those areas of open space required for the implementation of Project Jennifer as shown coloured blue and green on the plan submitted under the provisions of Section 123 of the Local Government Act, 1972, and to report back on any representations received concerning the proposed disposal. REG/15
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
2.1The City Council entered into a Development Agreement with St. Modwen Properties Ltd. in September 2005. Under this agreement St. Modwen are required to bring forward proposals for the development of a new district centre at Scotland Road/Great Homer Street.
2.2St. Modwen submitted a planning application for their scheme in November 2005. Following detailed discussions with the Council’s planning service a revised scheme was later submitted and this was approved by the Planning Committee of 23rd January 2007. The then Secretary of State for Communities and Local Government notified the Council on 4th May that she would not be calling it in for a public inquiry. The consent can therefore now be issued subject to the signing of a legal agreement.
2.3St Modwen are now preparing to progress negotiations to acquire the property needed to implement the scheme and a report will be submitted later in the year seeking authority to make a Compulsory Purchase Order.
3. The scheme
3.1The planned new district centre is seen as a flagship scheme that will create a new heart for the area. 3.2. The £150m scheme comprises:
§ 115,000 sq ft superstore § 965 space car park § 80,000 sq ft of non-food retail stores § a market hall and 300 relocated outdoor market stalls § 481 new homes § facilities for a Primary Care Trust centre § a new library § leisure facilities § 80,000 sq ft of light industrial space § a public transport interchange § improved public realm
3.3As a condition of planning consent for the scheme the developer will be required to provide new enhanced public realm and to contribute £400,000 to the enhancement of Everton Park
3.4Part of the site for the new development incorporates land that is currently laid out as open space as shown shaded on the attached plan and coloured blue and green.
4. Loss of open space
4.1Before the Council can dispose of the open space proposed for inclusion in the approved scheme it must first advertise the proposed loss of open space in accordance with the provisions of section 123 of the Local Government Act 1973 (as amended) and consider any objections which are received.
4.2Authority to place the necessary advertisements is now sought.
Executive Member (Cllr Mike Storey CBE) / Executive Director (John Kelly) recommendation:
It is recommended that :
Officers be authorised to advertise the Council’s intention to dispose of those areas of open space required for the implementation of Project Jennifer (as shown coloured blue and green on the attached plan) under the provisions of Section 123 of the Local Government Act, 1972, and to report back on any representations received concerning the proposed disposal.
Key Decision?
No Forward Plan/3 days notice/special urgency
No
Implementation effective from:
21 September 2007
Timescale for action:
The notices will be placed as soon as the recommendation is approved and will give objectors 14 days to respond.
Reason(s) for Recommendation:
The advertisement of the proposed loss of open space is an essential step in the process leading to the delivery of this project.
Alternative options to be considered:
The Council could decide not to support the disposal and development of the open space but that would be contrary to the decision of the Planning Committee and would damage the integrity of the scheme as a whole.
Consultation
There has been extensive public consultation on this project to date including exhibitions and newsletters. There are also regular updates on the scheme given to the Project Jennifer Community Forum.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.