Repair and Maintenance of Public Buildings

Agreed Committee 1 paper

Resources and Corporate Services Select Committee 2007/08 agreed this item on Wednesday 9 January 2008. Below is the council's own wording, with the papers it was decided on.

Item68

Resolved

Agreed that – a) the contents of the report be noted; and b) a further report be submitted to the committee in April, following a full review of the Repair and Maintenance contract.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Resources and Corporate Services Select Committee 2007/08, 6 pages

Reports to select committees

Liverpool City Council

Report to: Resources and Corporate Services Select Committee

Subject: Repair and Maintenance Public Buildings

Report no: PM / 02 / 2007

Date: 9 January 2008

Reporting officer: Phil Halsall

Contact officer: John Kilbride

Ward: City Wide

1. Purpose and recommendations

1.1To advise the Committee regarding the return of the repair and maintenance contract to City Council control. 1.2 That the contents of the report are noted and following a full review of the Repair and Maintenance Service a further report be submitted to Members in April 2008.

2. Relevant background information

The Partnership for the repair and maintenance of public buildings with Norwest Holst (previously Vinci) commenced 1 September 2000 and was completed on 31 August 2007.

There was a contractual option to extend the contract by up to three years however; the Executive Management Team declined the option in October 2004 when it became apparent that extending the contract would not be in LCCs best interests as it was becoming more difficult to provide the level of income required under the contract conditions.

An Outline Business Case was reported to the Management Team in March 2006 and the decision was to allow the contract to conclude at the end of its original term and allow the operation to come back under direct LCC control within the Premises Management Unit (PMU)

3. Key issues

OUTLINE BUSINESS CASE (OBC)

A detailed OBC was developed which considered a number of possible options at the end of the contract, including splitting the contract by trade or geographical area with preferred contractors but this was not considered practical.

The end of the contract in August 2007 gave LCC the opportunity to implement alternative delivery methods and end unfavourable conditions imposed by the contract which were not in LCC’s favour

1 Holst charge out rates increased for trade operatives by NEDO (industry index – up to 8% annual inflation rise) whereas their employment costs only rose by the LCC inflation rate – approx 3% p.a. 2 Purchasing of materials and engaging contractors could be invoiced at cost price plus a 9% profit on-cost as per the contract In 2006/07 orders to the value of £2.3m were raised with private contractors. 3 Additionally a fixed fee was set for the non-productive staff that also rose at the NEDO rate and was subject to a 9% profit on-cost as per the contract. 4 Although the value of the R&M contract was set at £3m in 2000 – start of the contract – a minimum level of income was specified at £5.3m. There was reliance mainly upon Education Capital to meet the shortfall in budget and maximise income for the partner. 5 Also, as the staff, were TUPE transferred all terms and conditions have in the main, remained the same but as the level of income is guaranteed there has been little incentive to make any operational changes.

The value of the contract was increased to provide the partner with a guaranteed level of income which meant there was little pressure on the partner to radically improve efficiency during the contract period.

Having considered all the various options for the delivery of the repair and maintenance service and compared the options against the strategic objectives set out in the OBC the preferred option once the contract had expired was to return the operation to direct LCC control and TUPE transfer the staff back to the council

The experience gained during the course of the current contract gives a good understanding of the actions required to provide a high performing service. This will be driven by producing a Maintenance Strategy setting out the strategic aims and objectives over a 5 year period and by utilising the available budgets to prevent breakdowns and repairs by focusing on Planned Preventative Maintenance and Cyclical Maintenance

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Repair and Maintenance of Public BuildingsReport 6 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Repair and Maintenance of Public BuildingsThis decision
  2. Repair and Maintenance ContractAgreed
  3. Housing Repair and Maintenance Performance in the 2007/8 Financial Year - Interim Performance ReportAgreed
  4. Housing Repair and Maintenance Annual Report 2006/7Agreed
  5. Housing Repair and Maintenance Annual Position Statement 2005/6Agreed
  6. Annual Position Statement 2004/5 on the Housing Repair Maintenance ServiceAgreed

More from Liverpool Resources and Corporate Services Select Committee 2007/08

All decisions
MeetingDecisionOutcome
9 Apr 2008 Minutes of the Last MeetingsAgreed that the minutes be approved. Agreed Open
9 Apr 2008 Equalities Initiatives - Finance and Legal ServicesAgreed that – a) The contents of the report be noted; b) The Committee be advised whether the anonymity of people who... Agreed Open
9 Apr 2008 Benefits Service Performance ReportAgreed that – a) The contents of the report be noted; and b) Particular attention be given in future reports to the p... Agreed Open
9 Apr 2008 Revenues Service Performance ReportAgreed that – a) The contents of the report be noted; b) A report be submitted to the next meeting on the Collection ... Agreed Open
9 Apr 2008 Medium Term Financial PlanAgreed that the contents of the report be noted. Agreed Open