Resolved
Agreed that – a) the contents of the report be noted; and b) a further report be submitted to the committee in April, following a full review of the Repair and Maintenance contract.
Resources and Corporate Services Select Committee 2007/08 agreed this item on Wednesday 9 January 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that – a) the contents of the report be noted; and b) a further report be submitted to the committee in April, following a full review of the Repair and Maintenance contract.
Reports to select committees
Liverpool City Council
Report to: Resources and Corporate Services Select Committee
Subject: Repair and Maintenance Public Buildings
Report no: PM / 02 / 2007
Date: 9 January 2008
Reporting officer: Phil Halsall
Contact officer: John Kilbride
Ward: City Wide
1. Purpose and recommendations
1.1To advise the Committee regarding the return of the repair and maintenance contract to City Council control. 1.2 That the contents of the report are noted and following a full review of the Repair and Maintenance Service a further report be submitted to Members in April 2008.
2. Relevant background information
The Partnership for the repair and maintenance of public buildings with Norwest Holst (previously Vinci) commenced 1 September 2000 and was completed on 31 August 2007.
There was a contractual option to extend the contract by up to three years however; the Executive Management Team declined the option in October 2004 when it became apparent that extending the contract would not be in LCCs best interests as it was becoming more difficult to provide the level of income required under the contract conditions.
An Outline Business Case was reported to the Management Team in March 2006 and the decision was to allow the contract to conclude at the end of its original term and allow the operation to come back under direct LCC control within the Premises Management Unit (PMU)
3. Key issues
OUTLINE BUSINESS CASE (OBC)
A detailed OBC was developed which considered a number of possible options at the end of the contract, including splitting the contract by trade or geographical area with preferred contractors but this was not considered practical.
The end of the contract in August 2007 gave LCC the opportunity to implement alternative delivery methods and end unfavourable conditions imposed by the contract which were not in LCC’s favour
1 Holst charge out rates increased for trade operatives by NEDO (industry index – up to 8% annual inflation rise) whereas their employment costs only rose by the LCC inflation rate – approx 3% p.a. 2 Purchasing of materials and engaging contractors could be invoiced at cost price plus a 9% profit on-cost as per the contract In 2006/07 orders to the value of £2.3m were raised with private contractors. 3 Additionally a fixed fee was set for the non-productive staff that also rose at the NEDO rate and was subject to a 9% profit on-cost as per the contract. 4 Although the value of the R&M contract was set at £3m in 2000 – start of the contract – a minimum level of income was specified at £5.3m. There was reliance mainly upon Education Capital to meet the shortfall in budget and maximise income for the partner. 5 Also, as the staff, were TUPE transferred all terms and conditions have in the main, remained the same but as the level of income is guaranteed there has been little incentive to make any operational changes.
The value of the contract was increased to provide the partner with a guaranteed level of income which meant there was little pressure on the partner to radically improve efficiency during the contract period.
Having considered all the various options for the delivery of the repair and maintenance service and compared the options against the strategic objectives set out in the OBC the preferred option once the contract had expired was to return the operation to direct LCC control and TUPE transfer the staff back to the council
The experience gained during the course of the current contract gives a good understanding of the actions required to provide a high performing service. This will be driven by producing a Maintenance Strategy setting out the strategic aims and objectives over a 5 year period and by utilising the available budgets to prevent breakdowns and repairs by focusing on Planned Preventative Maintenance and Cyclical Maintenance
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Repair and Maintenance of Public BuildingsReport | 6 pages | DownloadRead as text |
Follow Resources and Corporate Services Select Committee 2007/08 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Apr 2008 | Minutes of the Last MeetingsAgreed that the minutes be approved. | Agreed | Open |
| 9 Apr 2008 | Equalities Initiatives - Finance and Legal ServicesAgreed that – a) The contents of the report be noted; b) The Committee be advised whether the anonymity of people who... | Agreed | Open |
| 9 Apr 2008 | Benefits Service Performance ReportAgreed that – a) The contents of the report be noted; and b) Particular attention be given in future reports to the p... | Agreed | Open |
| 9 Apr 2008 | Revenues Service Performance ReportAgreed that – a) The contents of the report be noted; b) A report be submitted to the next meeting on the Collection ... | Agreed | Open |
| 9 Apr 2008 | Medium Term Financial PlanAgreed that the contents of the report be noted. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.