Resolved
Agreed that – a) The contents of the report be noted; and b) A further report be submitted in six months time including, if possible, an estimate of the savings since the contract was brought in house.
Resources and Corporate Services Select Committee 2007/08 agreed this item on Wednesday 9 April 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that – a) The contents of the report be noted; and b) A further report be submitted in six months time including, if possible, an estimate of the savings since the contract was brought in house.
Reports to select committees
Liverpool City Council
Report to: Resources and Corporate Services Select Committee
Subject: Repair and Maintenance Public Buildings
Report no: PM / 1 / 08
Date: 9 April 2008
Reporting officer: Phil Halsall
Contact officer: John Kilbride
Ward: City Wide
1. Purpose and recommendations
To advise the committee of the review of the Repair and Maintenance service following its return to LCC
That the report is noted
2. Relevant background information
In January 2008 the Committee considered a report regarding the return of the Repair and Maintenance Service to City Council control. The report was noted and it was agreed that a further report would be submitted to members following a review of the Repair and Maintenance Service.
The end of the contract in August 2007 gave LCC the opportunity to consider alternative methods of delivery and end conditions imposed by the contract which were not in LCC s favour.
In 2000, the value of the contract was increased by including capital works to the value of £2.3 million which provided the partner with a guaranteed level of income which meant that there was little pressure to improve efficiency during the contract period.
The main areas within the Repair and Maintenance operation that have been identified as requiring immediate review/change are –
- The use of Private Contractors
- Improved use of the internal workforce
- Efficient process for dealing with work requests
The main aim since the return to LCC control has been to reduce the level of work passed to private contractors and make more cost effective use of the internal workforce which will allow more jobs to be completed with the available budget.
Contract conditions allowed the partner to include a 9% on-cost when using private contractors. In 2006/07 order to the value of £2.3 million were raised with private contractors.
While there will always be a need to engage private contractors for specialist works e.g. lift maintenance, the introduction of e-forms to request repairs allows a full audit of all work requests and tighter controls have been introduced to ensure that were possible the internal workforce is utilised rather than passing work straight to private contractors.
It is essential that the LCC workforce has the ability to respond to varying client needs and the flexibility to meet changes in workload.
The need to provide adequate training is an obvious requirement for a workforce involved in such diverse operations. A workforce training plan is being introduced that will ensure that the workforce have the skills necessary to meet our statutory requirements but also allows for a more flexible use of the workforce.
An example of this approach is the glaziers who have been trained to undertake glass surveys to ensure compliance with the Glass Regulations. This can be undertaken between glazing repairs and has ensured that they are fully occupied and we are not paying fees to specialists to carry out glass inspections.
The introduction of e-forms to allow premises managers to request repairs also allows an audit trail to be established rather than making a phone call and hoping the correct response will be made.
The e-form links to the corporate premises and asset database (Tribal) which is being introduced across LCC and will allow all building managers to access any data relating to their building ranging from repair and maintenance, digital drawings, condition surveys, asbestos surveys etc.
The Government Procurement Card (GPC) was introduced for a trial period from September 2007. The trial has been very successful and GPC has now been introduced. The system uses a credit card which enables operatives to purchase most of their materials immediately form local suppliers with the added bonus that the suppliers are paid within 2/4 days.
Further Actions
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Repair and Maintenance ContractReport | 5 pages | DownloadRead as text |
Follow Resources and Corporate Services Select Committee 2007/08 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Apr 2008 | Minutes of the Last MeetingsAgreed that the minutes be approved. | Agreed | Open |
| 9 Apr 2008 | Equalities Initiatives - Finance and Legal ServicesAgreed that – a) The contents of the report be noted; b) The Committee be advised whether the anonymity of people who... | Agreed | Open |
| 9 Apr 2008 | Benefits Service Performance ReportAgreed that – a) The contents of the report be noted; and b) Particular attention be given in future reports to the p... | Agreed | Open |
| 9 Apr 2008 | Revenues Service Performance ReportAgreed that – a) The contents of the report be noted; b) A report be submitted to the next meeting on the Collection ... | Agreed | Open |
| 9 Apr 2008 | Medium Term Financial PlanAgreed that the contents of the report be noted. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.