Resolved
Resolved that the Budget Report as submitted for 2008/09 to 2010/11 be noted and referred to the Budget meeting of the City Council to be held on 5 March 2008.
Executive Board noted this item on Friday 22 February 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the Budget Report as submitted for 2008/09 to 2010/11 be noted and referred to the Budget meeting of the City Council to be held on 5 March 2008.
Introduction
Government Grant Support
Levies
Quarter 3 Financial Review 2007/08
Efficiencies of Funding Changes
Risks and Uncertainties
Working Balances
Ongoing Revenue Costs
Council Tax Options
Minimum Budget Requirements
Financial Forecasts
Responsibilities of a Local Authority
Budget Strategies
Responsibilities of the Chief Finance Officer
Timescales for Action
Precepts
Abbreviations
Annexe A – LCC Vision, Aims & Priorities Annexe B – Section 11 Report Action Plan Annexe C – Council Tax Options Annexe D – Financial Forecast 2008/09 to 2010/11 Annexe E – Comparison of Costs Annexe F – Performance Indicators Liverpool City Council Budget Report 2008/09 to 2010/11
The key features of this budget report are as follows:
• The report identifies the need to produce a budget for 2008/9 that addresses issues raised within the District Auditor’s s11 report and the Use of Resources assessment.
• The development of a 3-year financial strategy made possible by the government’s longer term funding decisions to local government.
• The maximum budget requirement for 2008/09 for the current level of council tax is £461.140m.
• The forecast entitlement for Dedicated Schools Budget (DSG) of £264.973m is based upon total pupil numbers of 61,225. However, final pupil numbers and DSG may not be confirmed by the government until May 2008.
• The government has indicated that it may consider council tax increases above 5% as “excessive” and is likely to take intervention action requiring any authority that exceeds this level of increase to reduce its budget and council tax requirements.
• The financial forecasts now identify budget gaps for the next 3 financial years as follows:
2008/09 2009/10 2010/11 £m £m £m
Initial Forecast Budget Gaps 62.0 44.7 59.6 as reported 18/01/08 (cumulative)
Additional Total Formula Grant (TFG) -0.5 -0.5 -0.5
Revised forecast of service and -0.3 -1.4 -0.8 specific grants
Identified efficiencies -9.9 -9.6 -9.1
Identified funding changes -11.4 -5.7 -5.6
Improved financial position 2007/08 -2.4 - - ____ ____ ____ Budget Gaps remaining 37.5 27.5 43.6 ==== ==== ==== • The financial forecasts provide for the following level of reserves for the management of risks and progressively increasing level of working balances.
2008/09 2009/10 2010/11 £m £m £m
Reserves for the management of risks 10.0 11.0 12.0 Working balances 10.0 11.0 12.0
These are the minimum levels recommended by and would satisfy the Chief Finance Officer.
• The financial forecasts are before any decisions have been taken in respect of the level of council tax in 2008/09 and future years and any changes in the future level of spending.
Therefore, budget proposals including a council tax strategy need to be considered and determined by the city council at its budget meeting on 5th March 2008. The council should also consider, having regard to its own responsibilities and those of its Chief Finance Officer, approving a Medium Term Financial Plan (MTFP) for the 3 year period up to and including 2010/11.
Both the budget for 2008/09 and the MTFP should be linked to the council’s key strategic objectives and take into account both local improvement priorities and national priorities. Introduction
The purpose of this report is to provide the background and context to the 2008/9 budget. Whilst this report considers issues normally considered at this stage in the budget cycle, there are a number of differences from previous years due to:
• The government providing a 3-year financial settlement for 2008/9 to 2010/11.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
BUDGET REPORT 2008-09: Annexe AAppendix | 2 pages | Download |
PDF |
BUDGET REPORT 2008-09: Annexe BAppendix | 4 pages | Download |
PDF |
BUDGET REPORT 2008-09: Annexe C-FAppendix | 7 pages | Download |
PDF |
Budget Report 2008-09 to 2010-11Report | 18 pages | DownloadRead as text |
Follow Executive Board at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Apr 2010 | Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. | Approved | Open |
| 23 Apr 2010 | New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... | Decided | Open |
| 23 Apr 2010 | 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... | Decided | Open |
| 23 Apr 2010 | Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... | Approved | Open |
| 23 Apr 2010 | Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.