CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Liverpool City Council
Executive Board, Friday 22 February 2008

Quarter 3 Financial Review 2007/08 and Medium Term Financial Plan Update

Noted Executive 2 papers

Executive Board noted this item on Friday 22 February 2008. Below is the council's own wording, with the papers it was decided on.

Item165

Resolved

Resolved that subject to the above amendments – (i) the report be noted; and (ii) the Liverpool Culture Company be instructed not to enter into any further financial contractual commitments in relation to the programme until such time as the anticipated income, sponsorship and grant monies of approximately £1.6m has been secured.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 17 pages

Executive summary

General Fund – Revenue Expenditure 2007/08

Medium Term Financial Plan Update

Collection Fund - 2007/08

General Fund – Grants 2007/08

Housing Revenue Account – 2007/08

Capital Programme Expenditure 2007/08

Capital Programme Financing 2007/08

Prudential Indicators

Annual Efficiency Statements

Cost Effectiveness Indicators

Number of Employees

Contingent Liabilities

Major Contractual Arrangements

List of Annexes

List of Background Papers

Abbreviations Liverpool City Council

This review is the latest assessment of the financial position of the council.

• The half year Financial Review reported an adverse financial forecast of £3.4m. This report now forecasts that the adverse variance remaining is now likely to be £1.5m.

• General fund working balances for 2007/08 were budgeted at £9m but are now forecast after allowing for the forecast overspending to be £7.5m at the year end unless further remedial action is taken.

• There are general fund reserves forecast of £39.9m set aside primarily for legally restricted spending, the management of risks or to meet future Private Finance Initiative (PFI) contributions.

• The Medium Term Financial Plan (MTFP) identifies two principle options for funding the 2008 capital of culture programme.

• The current trend of social care costs will require the council to determine how, in 2008/09 and beyond, offsetting and continuing cost reductions in other service areas can be achieved to offset these cost pressures.

• The Collection Fund has a forecast year end deficit of £12.9m arising primarily from 2006/07. Although efforts continue to further increase collection, the council has set aside available resources to offset the impact on future council tax payers.

• The Housing Revenue Account (HRA) expenditure remains within allocated and available resources and forecasts year end working balances of £7.4m.

• There are HRA reserves of £2.3m set aside for future repairs.

• Capital spending planned for the year is forecast at £281.6m.

• The planned capital spending is forecast to be financed as follows:

§ Government & other external sources £215.0m (76%) § Local sources (capital receipts & revenue) £27.4m (10%) § Unsupported Borrowing £39.2m (14%)

• The forecast of capital spending therefore assumes that £24.2m of capital expenditure in 2007/08 will be financed by capital receipts. There were useable capital receipts brought forward from 2006/07 of £15.3m and it is anticipated that the council will generate useable capital receipts of £15.2m during the year, of which £9m will be useable for capital financing. General Fund - Revenue Expenditure 2007/08

The financial review identifies a number of material variations which unless addressed will result in a significant call upon working balances in the current financial year and, as a consequence, adversely affect the council’s financial strategy and position in respect of 2008/09.

The Half Year Financial Review reported an adverse financial forecast of £3.4m. This report now forecasts that the adverse variance remaining is likely to be £1.5m, an improvement of £1.6m. The following is a commentary on the key variances.

Children’s Services

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Q3 FINANCIAL REVIEW 2007-08: Annexes A-EAppendix 7 pages Download
PDF
Quarter 3 Financial Review 2007/08 and Medium Term Financial Plan UpdateReport 17 pages DownloadRead as text

At this meeting

Whole meeting
163Treasury Management StrategyNoted 164Budget Report 2008-09 to 2010-11Noted
165Quarter 3 Financial Review 2007/08 and Medium Term Financial Plan UpdateThis decision
166aBus Layover in the City Centre (REG/46)Deferred

On this subject at Liverpool

Search all
  1. Quarter 3 Financial Review 2007/08 and Medium Term Financial Plan UpdateThis decision
  2. Revenue and Capital Financial Monitoring Report 2025/26 (Quarter 4)Noted
  3. Quarter 3 Financial Review 2010/11Agreed
  4. Quarter 3 financial review 2009-10Approved
  5. Quarter 3 Financial Review 2009-10Agreed
  6. Work Programme Issue - Quarter 1 Financial Review 2009/10 and Medium Term Financial Plan UpdateNoted

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies