Liverpool City Central Business Improvement District (REG/54)

Approved Executive 1 paper

Executive Board approved this item on Friday 11 April 2008. Below is the council's own wording, with the papers it was decided on.

Item207i

Resolved

Resolved that - (i) the ballot date of 16 October 2008 be approved for the new 5 year City Central Business Improvement District (BID); (ii) the proposal for a 5 year BID which will run from 1 November 2008 to 31 October 2013, be approved; (iii) the continuing contribution in the Liverpool City Council City Centre Management Team budget for revenue expenditure of £321,000 for 2008/2009 and a contribution for the following years of the proposed BIDS duration which reflects any agreed salary increases and inflation costs, be approved; and (iv) the extension of the existing boundary for the BID to include Bold Street subject to appropriate level of support from Bold Street businesses be approved. NH/21
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 9 pages

Executive summary

1. At its meeting on 21 January 2005, the Executive Board approved; the Baseline Service Agreement and the three year Business Plan for the Liverpool City Central BID with a BID levy set at 1.2% of the rateable value of properties in the BID area, bringing in £584,000 per annum of additional investment into the city centre.

It also agreed the continuing contribution by Liverpool City Council General Fund budget for the revenue expenditure of £305,000 for 2005/2006 to fund the BID team, and a contribution for following years of the BIDS duration which reflects any agreed salary increases and inflation costs, £311,600 for 2006/2007 and £312,700 for 2007/2008.

The Liverpool BID Company seek council approval for a continuing contribution in the Liverpool General Fund budget for revenue expenditure of £321,000 for 2008/2009, and a contribution for the following years of the proposed BIDS duration which reflects any agreed salary increases and inflation costs. The BID Chief Executive reports to the Executive Director of Regeneration.

2. The City Central BID which comes to an end on 31 October 2008 represents the influence of 500 businesses in the main retail area of the city centre and since it commenced on 1 November 2005 it has provided additional services, paid for through the BID levy, over and above those provided by the city council, with a key objective of increasing footfall into the city centre and therefore into the retail outlets – key to the future sustainability and potential inward investors in the city centre. These services have established high standards of cleansing, marketing and safety in the city centre. Some of the key successes delivered by the BID to date are;

- Additional street cleansing 7 days a week with 5 additional ‘BID’ branded street sweepers - Hot spot washing to remove graffiti and other grot spots around the city centre retail area - High profile events at key retail times throughout the year; Easter, Grand National, Summer and Christmas - Launch of permanent late night shopping on Thursdays - High profile PR, press and radio campaigns - 2 dedicated crime wardens patrolling the BID area every day - Paid for Radio Alert Scheme membership for retailers / businesses - Additional CCTV monitoring in the BID area - Deterring beggars, street drinkers and moving on rough sleepers - Agreement and enforcement of city centre ‘byelaws’ e.g. leaflet distribution etc - Introduction of a ‘voluntary code of practice’ for street entertainers

3. On 19 September 2007 the City Central BID operating board agreed a ballot date of the 16 October 2008 for a 5 year BID to run from 1 November 2008 to 31 October 2013.

4. The Liverpool BID Company Ltd is seeking Executive Board approval to hold a new ballot for a 5 year City Central BID on 16 October as required under the BID Regulations 2004 under the Local Government Act.

5. The BID is seeking Executive Board approval to extend its current boundary to include Bold Street in the new BID proposal subject to the appropriate level of support from businesses in Bold Street.

6. In order to obtain a successful vote in the BID ballot no less than 50% of the businesses that vote have to vote in favour of the BID by number and no less than 50% of the aggregate rateable value of those that vote have to vote in favour. In October 2005 56% of the businesses voted in the ballot (12% above the average turnout). 62% of the businesses voted in favour and 51% of the aggregate rateable value voted in favour.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Liverpool City Central Business Improvement District (REG/54)Report 9 pages DownloadRead as text

At this meeting

Whole meeting
205Minutes of the Last MeetingApproved 206Annual Audit Letter - March 2008Noted 207aLand at Wavertree Boulevard (RES/53)Agreed 207bPassageway rear of 21/23 Williamson Square (RES/54)Decided 207cSites at Stonedale Crescent (RES/55)Agreed 207dHighwayman Public House, Shrewton Road (RES/56)Agreed 207e50 St Mary's Road (RES/57)Approved 207f1 Southbrook Way (RES/58)Agreed 207g63/65 Jamaica Street and 44/46 Greenland Street (RES/59)Agreed 207h39/41 Stanley Road (RES/60)Agreed
207iLiverpool City Central Business Improvement District (REG/54)This decision
207jGranby Renewal Area 2-24 and 1-27 Hatherley Street (NH/21)Approved 207kEstablishing a Partnership Framework Between Liverpool City Council & Liverpool Primary Care Trust (HASC/12)Noted 207lEnhancement of Integrated Work Between Liverpool City Council & Liverpool Primary Care Trust (HASC/13)Approved 207mSefton and Liverpool Enterprise Growth Initiative Commissioning Report 4 (EDE/24)Decided 207nFinal Business Case: BSF ICT Managed Service (Wave 2 schools) (CHS/43)Approved 207oAdmissions to Primary & Secondary Schools:Academic Year 2009/10 (CHS/44)Approved 207pCorporate Improvement Programme (CPS/6)Approved 208Local Development Framework - Anfield, Tuebrook and Stoneycroft and Old Swan Neighbourhood Committee - 13 March 2008Agreed 209Newhall Baths - Walton Neighbourhood Committee - 19th March, 2008Agreed 210Fazakerley Special Needs - Walton Neighbourhood Committee - 19th March, 2008Decided 211Voluntary Transfer of Housing Stock - Liverpool City Council to Liverpool Mutual Homes LimitedOn the agenda 212Traffic and Highways Representation Committee - 17 March 2008Noted

Who was there

15 of 17 attended
WB
Councillor Warren BradleyChair, present
DA
Councillor Dave AntrobusMember, present
FC
Councillor Flo Clucas OBEMember, present
CE
Councillor Colin EldridgeMember, present
MF
Councillor Marilyn FieldingMember, present
EK
Councillor Erica Kemp, CBEMember, present
PM
Councillor Peter MilleaMember, present
MS
Councillor Mike Storey CBEMember, present
BT
Councillor Berni TurnerMember, present
KT
Councillor Keith TurnerMember, present
CH
Colin HiltonOfficer, present
TH
Tony HunterOfficer, present

All 17 on the meeting page

On this subject at Liverpool

Search all
  1. Liverpool City Central Business Improvement District (REG/54)This decision
  2. Liverpool City Region and Cheshire Children's Regional Care CooperativeApproved
  3. Liverpool City Region Overnight Visitor Levy (OVL) Progress UpdateAgreed
  4. Liverpool City Council Disability Action PlanNoted
  5. Liverpool City Council - Crisis and Resilience Fund Policy 2026/2027Approved
  6. Grant Funding from the Liverpool City Region Combined Authority for a Music Industry Recovery Fund (CTE/12)Approved

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open