Resolved that – (i) the Service specification for the ICT Managed Service that will be provided to schools in Wave 2 of the City Council’s Building Schools for the Future ( BSF ) programme by its preferred partner, Liverpool Direct Ltd ( LDL ), at Annex A of the report submitted be approved; (ii) the pricing structure at Annex B of the report submitted be agreed as the maximum amount to be paid by schools for the Services specified, with the Local Choice Fund remaining as at least 50% of the funding available; (iii) any costs for pension arrangements associated with TUPE transfer be met from Children’s Services portfolio budgets; (iv) any running costs for the Learning Platform between 2010 and 2015 be met from Children’s Services portfolio budgets; and (v) the Executive Directors (Children’s Services) and (Finance and Legal Services) in consultation with the Acting City Solicitor be authorised to reach a final contract agreement subsequently with LDL on the ICT Managed Service. CHS/44
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
This report seeks approval to the proposed Final Business Case (FBC) submission to Partnerships for Schools (PfS) on the ICT Managed Service that will be provided to schools in Wave 2 of the City Council’s BSF programme by its preferred partner, Liverpool Direct Ltd (LDL).
The FBC, which needs to include the Board’s approval to its key details when submitted to PfS, will set out: • the case for the City Council’s proposed delivery of ICT services to schools in its BSF programme • the specification of the services to Wave 2 schools and their consequences to schools and the City Council • the cost of the service to central Government (via direct grant), Liverpool schools and potentially the City Council • any risks that may fall to the City Council during implementation of, or as a result of the delivery of, the Service to BSF schools.
Commercial negotiations on the detailed operation of the ICT Managed Service are nearing completion, led by AEDs from Resources and Childrens’ Services. This report also seeks approval for delegated powers to conclude the negotiations and reach contract signature with LDL on the Service.
Background
Delivering a Council-procured, provider-managed ICT service for all BSF schools is part of the central government prescription for BSF. In April 2006, PfS accepted the City Council’s proposal to procure the ICT Managed Service from LDL (see Report CHS/59/06 attached as Annex C) as representing value for money and based on LDL’s acceptance of the standard PfS contract documents involved. This was dependent upon successful completion of negotiations over the project-specific requirements between LCC and LDL and their acceptance by PfS. The FBC will recite this background in detail.
Current Status of Proposals
Negotiations with LDL over the delivery of the ICT Managed Service have reached agreement on the following position: (a) Service specification
Annex A contains the proposed specification for all Wave 2 schools in BSF. This remains in line with the scope of service envisaged by the processes described in the 2006 report CHS/59/06. The specification has been developed with the involvement of all Wave 2 schools, and the supervision of an ICT Programme Board managed by Children’s Services AED Tim Warren, to ensure that LCC Childrens’ Services and the wider City Council’s needs are properly met.
(b) Broad Service costs
Annex B details the proposed costs of the service for Wave 2 schools. It illustrates how the service is prescribed by Government but also pump-primed by it. As part of the significant overall funding for Wave 2 BSF that the City will receive, around £11m is intended for the delivery of the ICT Managed Service.
However, since 2006, the scope of the Wave 2 schools programme has changed and two school schemes have been deferred, while one school – Lower Lee Special School – has been accelerated into Wave 2. As a result the overall cost of the ICT service delivery, particularly central operating costs, have had to change. They remain, however, within the scope of the costs reported in the 2006 report. Indeed, two key elements of the proposed elemental costs are best performing nationally in PfS benchmarking. These are:
• the cost per pupil for the service charged to schools – nationally this is £130 - £200 per pupil per year. For Liverpool Wave 2 schools this will be fixed at £109 per pupil • the size of the Local Choice Fund (amount for schools to buy ICT kit) – nationally this is 37% of the overall ICT funding available. For Liverpool Wave 2 schools this will be fixed at 50%.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.