Hall Lane Strategic Gateway Project and Royal Liverpool University Hospital Redevelopment (A&D/24)

Approved Executive 1 paper

Executive Board approved this item on Thursday 31 July 2008. Below is the council's own wording, with the papers it was decided on.

Item31c

Resolved

Resolved that – (i) the recommendation be approved; and (ii) the best thanks of the Board be extended to the Executive Members and Officers both within the Council and the University involved for all the hard work undertaken in relation to this matter. HSC/4
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 12 pages

CENTRAL/KENSINGTON AND FAIRFIELD/PICTON WARDS STATUS - PUBLIC (A&D/24) Portfolio: Executive Member/Director: Assets and Development Councillor Peter Millea/John Kelly Finance, Audit and Procurement Councillor Flo Clucas/Phil Halsall

Date of submission: Subject: July 2008 Hall Lane Strategic Gateway Project and Royal Liverpool University Hospital Redevelopment.

Report No. [ ] Contact officer: Background papers Mike Burchnall (233 6749) Glen Penrhyn-Lowe (233 8201) Executive Board Meetings Christine Wray (233 8146) 17th November 2006 (min 121 Bob Dunn (233 8138) refers) Jayne Black (233 8303) 13th April 2007 (min 208f refers) Joint Health and Wellbeing Scrutiny Committee Meeting 2nd July 2007 (min 4 refers) 17th December 2007 (min 20 refers) Planning Committee 18th March 2008 (min. 322 refers)

Introduction

1. This report provides Executive Members with an update on the Hall Lane Strategic Gateway and Royal Liverpool University Hospital (RLUH) projects and seeks agreement to the Construction Programme and advance works for the Hall Lane Scheme

Progress Report on Hall Lane project

Confirmation of CPO and Land Exchange

2. Following the Public Inquiry in 2007, the City Solicitor has written to the Department for Transport requesting that the Hall Lane Compulsory Purchase Order (the CPO) be confirmed. A decision is expected at the end of July / early August. This will enable construction on the road project to be commenced in Autumn 2008.

Early Contractor Involvement

3. A mini-tender selection process has been completed and Birse Civil Engineering has been selected to work with the project designers as part of the Early Contractor Involvement (ECI) process. Their early involvement will provide more detailed information on buildability and risk management.

4. Birse Civil Engineering has also provided advice on the construction programme for the project and delivering the project in the shortest possible timeframe, whilst ensuring that there will be no disruption to routes into the city during 2008.

Construction Programme

5. The current programme for construction is shown below.

Figure 1 Revised Programme Event 2007 2008 2009 2010 S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M

Application for full funding approval Detailed Design

Early Contractor Involvement

Land Negotiations

General Vesting Declaration Process Property Demolition

Underground Service Diversions

Road Construction adjacent to existing highway Road Construction on existing highways Road Open to Traffic

6. The contractor’s advice is that construction work could commence in Autumn 2008 on land which lies adjacent to the existing road network, including demolition of properties along Mount Vernon and highway construction in the part of the Royal Liverpool University Hospital overflow car park which is owned by LCC. Officers have been in detailed discussions with the Royal Hospital as to how this can be achieved and for the provision of alternative car parking for the Hospital.

7. The construction work to tie the new road into the existing highway network will then commence in 2009 and continue during that year. These works include forming the new junction at Mount Vernon/West Derby Street and upgrading the junction at Low Hill/Kensington. These works will have an effect on traffic flows into the city, but disruption will be limited as much as practically possible.

8. The contractor has indicated a construction period of 20 months duration, but work is ongoing to integrate and refine the design and construction methodology.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Hall Lane Strategic Gateway Project and Royal Liverpool University Hospital Redevelopment (A&D/24)Report 12 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Hall Lane Strategic Gateway Project and Royal Liverpool University Hospital Redevelopment (A&D/24)This decision
  2. Land adjacent to junction Warbreck Moor & Hall Lane, Liverpool 9 (Fazakerley Ward)Approved
  3. Progress on the Hall Lane Gateway schemeAgreed
  4. Hall Lane Strategic Gateway Scheme and Royal Liverpool University Hospital Redevelopment (A&D/6)Approved
  5. Cardinal Heenan & Broughton Hall Schools, Honeys Green Lane & Yew Tree Lane, Liverpool 12 (Knotty Ash/Yew Tree ward)Approved
  6. Land at Corner of Croxteth Hall Lane and Carr Lane East, Liverpool 11 (Croxteth Ward)Approved

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open