Resolved that – (i) the recommendation be approved; and (ii) the best thanks of the Board be extended to the Executive Members and Officers both within the Council and the University involved for all the hard work undertaken in relation to this matter. HSC/4
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
CENTRAL/KENSINGTON AND FAIRFIELD/PICTON WARDS STATUS - PUBLIC (A&D/24) Portfolio: Executive Member/Director: Assets and Development Councillor Peter Millea/John Kelly Finance, Audit and Procurement Councillor Flo Clucas/Phil Halsall
Date of submission: Subject: July 2008 Hall Lane Strategic Gateway Project and Royal Liverpool University Hospital Redevelopment.
Report No. [ ] Contact officer: Background papers Mike Burchnall (233 6749) Glen Penrhyn-Lowe (233 8201) Executive Board Meetings Christine Wray (233 8146) 17th November 2006 (min 121 Bob Dunn (233 8138) refers) Jayne Black (233 8303) 13th April 2007 (min 208f refers) Joint Health and Wellbeing Scrutiny Committee Meeting 2nd July 2007 (min 4 refers) 17th December 2007 (min 20 refers) Planning Committee 18th March 2008 (min. 322 refers)
Introduction
1. This report provides Executive Members with an update on the Hall Lane Strategic Gateway and Royal Liverpool University Hospital (RLUH) projects and seeks agreement to the Construction Programme and advance works for the Hall Lane Scheme
Progress Report on Hall Lane project
Confirmation of CPO and Land Exchange
2. Following the Public Inquiry in 2007, the City Solicitor has written to the Department for Transport requesting that the Hall Lane Compulsory Purchase Order (the CPO) be confirmed. A decision is expected at the end of July / early August. This will enable construction on the road project to be commenced in Autumn 2008.
Early Contractor Involvement
3. A mini-tender selection process has been completed and Birse Civil Engineering has been selected to work with the project designers as part of the Early Contractor Involvement (ECI) process. Their early involvement will provide more detailed information on buildability and risk management.
4. Birse Civil Engineering has also provided advice on the construction programme for the project and delivering the project in the shortest possible timeframe, whilst ensuring that there will be no disruption to routes into the city during 2008.
Construction Programme
5. The current programme for construction is shown below.
Figure 1 Revised Programme Event 2007 2008 2009 2010 S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
Application for full funding approval Detailed Design
Early Contractor Involvement
Land Negotiations
General Vesting Declaration Process Property Demolition
Underground Service Diversions
Road Construction adjacent to existing highway Road Construction on existing highways Road Open to Traffic
6. The contractor’s advice is that construction work could commence in Autumn 2008 on land which lies adjacent to the existing road network, including demolition of properties along Mount Vernon and highway construction in the part of the Royal Liverpool University Hospital overflow car park which is owned by LCC. Officers have been in detailed discussions with the Royal Hospital as to how this can be achieved and for the provision of alternative car parking for the Hospital.
7. The construction work to tie the new road into the existing highway network will then commence in 2009 and continue during that year. These works include forming the new junction at Mount Vernon/West Derby Street and upgrading the junction at Low Hill/Kensington. These works will have an effect on traffic flows into the city, but disruption will be limited as much as practically possible.
8. The contractor has indicated a construction period of 20 months duration, but work is ongoing to integrate and refine the design and construction methodology.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.