Resolved
Agreed that the report be noted.
Regeneration Select Committee 2009/10 agreed this item on Thursday 17 December 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that the report be noted.
Hall Lane is now in receipt of the necessary funding from Department for Transport (DfT) (£17.1m total) and European Regional Development Fund (ERDF) (£1.529m). This has enabled Liverpool City Council to sign a contract with Birse Civils Ltd to carry out the works.
The acquisitions required to provide vacant possession of the site are now completed, mainly by using General Vesting Declaration (GVD) powers as part of the approved CPO. These powers could only be used when funding was confirmed since the City Council is liable to pay 90% of any valuation agreed between the City and the property owners.
All properties are now vacant and the contractor commenced demolition of the remaining properties on 30th November.
The relevant parts of the site have been fenced off. The first works affecting the highway will be diversion works by statutory undertakers to enable the highway to be widened on Mount Vernon and junction improvement work at Low Hill/Kensington/Hall Lane junction. These works should commence in January 2010.
An alternative access to the Royal Liverpool University Hospital (RLUH) car park is currently being constructed and a new pedestrian crossing will be incorporated on West Derby Street early next year. It will be necessary to close West Derby Street to through traffic in April/May next year for a period of 8 months to enable construction of a new junction with Mount Vernon. Arrangements are being made to minimise traffic delays during this period and access to the Hospital car park will be maintained from West Derby Street.
A residents’ parking scheme is being introduced in part of Kensington Fields. This should be in place by the end of 2009. This is being introduced at the request of the Executive Board to alleviate any overspill parking from RLUH as a result of the loss of their overspill car park. RLUH has also made separate internal arrangements to accommodate this loss.
Edge Lane West does not yet have the required funding to enable construction work to commence and to enable some outstanding acquisitions to take place.
A Major Schemes Business Case (MSBC) needs to be approved by DfT before they will be able to approve funding. The MSBC is presently being developed by 2020Liverpool and it is proposed that this will be submitted before the end of this calendar year. DfT aim to turn around a compliant business case within 3 months.
The earliest that we can expect funding approval is therefore April 2010 which would allow construction to commence in May/June 2010.
If there continue to be issues with the MSBC as submitted to DfT and the decision is delayed so that National elections in May/June affect the decision, a delay could be incurred such that funding would not be approved until September 2010. This would obviously delay the commencement of the works, but may also jeopardise the possibility of acquiring ERDF funding which needs to be committed by the end of 2010.
This scheme is linked to the overall development of the area and the Homes and Communities Agency (HCA) has provided additional funding to enable some further acquisitions to proceed along with a limited number of demolitions of the acquired properties. This is due to be carried out in a phased manner.
A contractor has been appointed, following a selection process using OJEU procurement rules, to work with the scheme designers to develop buildability, programming, costs and value for money to feed into the MSBC.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Progress on the Hall Lane Gateway schemeReport | 2 pages | DownloadRead as text |
Follow Regeneration Select Committee 2009/10 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Apr 2010 | Minutes of the last meetingAgreed that minutes of the last meeting of this Committee held on 11 February 2010 be approved as a true record subje... | Agreed | Open |
| 1 Apr 2010 | Notice of Motion - Cycle Purchase SchemeAgreed that the motion be referred to the Executive Member for Assets and Development for a report to be prepared in ... | Agreed | Open |
| 1 Apr 2010 | Response to Motion - Walking Routes to UniversityAgreed that the motion and response be referred to the Executive Member for Assets and Development for a further resp... | Agreed | Open |
| 1 Apr 2010 | Arena and Conference CentreAgreed that (a) a small Group of Members (including the Chair of this Committee) be appointed in the new Municipal Ye... | Agreed | Open |
| 1 Apr 2010 | Annual ReportAgreed that the submission by the Chairman on the work undertaken by this Committee over the last Municipal Year be a... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.