Resolved
Agreed that the decision of the Executive Board be noted.
Sustainable Communities Select Committee 2008/09 agreed this item on Wednesday 20 August 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that the decision of the Executive Board be noted.
Attached at Appendix A is the proposed programme for capital expenditure to support the aims and objectives outlined in the Housing Strategy Statement 2005-2008. The programme also assists in achieving the City Council’s Corporate Aims and Priorities as detailed at Appendix B.
Funding Resources
The Specified General Housing Capital Grant allocation of £12.55 million from the Regional Housing Board was received on 2 April 2008. This represented a 26% reduction on the previous allocation. This level of reduction was as a result of a decision taken by the Regional Housing Board to increase the percentage of the overall funding available to meet the regional targets set for the provision of affordable housing. Liverpool schemes received an allocation of £38 million for affordable housing and there will be further possibilities of this being increased through the regular market engagement that the Housing Corporation has initiated to allocate their remaining funding. Specific details of this programme will be subject to a separate report to the Executive Board.
The reduction in the specified grant provided directly to Local Authorities was applied to all Local Authorities within the region. Further discussions on the allocation of resources for 2009/10 and 2010/2011 are ongoing.
The confirmed specific allocation for the Disabled Facilities Grant (DFG) programme for 2008/09 is £1.92 million. This is an increase of 22% on the previous year’s allocation. The grant figure shown of £2.157 million includes a carry forward grant of £237k from 2007/08 for committed schemes that could not be started in the year that will be subject to the approval of the auditor. In addition, following a Government review of the Disabled Facilities Grant programme, the requirement for Local Authorities to provide 40% match funding has been removed. However, due to the level of demand, it is recommended that general resources previously provided by the City Council should be maintained. Furthermore, the Strategic Commissioning Board for the Supporting People Grant has also made a decision to provide £830k to be added to the programme for 2008/09 to undertake physical adaptations to vulnerable residents' properties to enable them to remain in their own homes.
The Capital Receipts shown includes the carry forward of £1.839 million approved using delegated powers in the last financial quarter and taking account of the year end variances amounts to a total of £4.863 million which have been evaluated and reprofiled to ensure programme delivery. In addition to these Capital Receipts brought forward, a further £1.5 million of unallocated HRA Capital Receipts that can be used for regeneration or affordable housing purposes has been identified for inclusion in the Housing Capital Programme.
The remainder of the programme is funded via specific grants or private finance. Reprofiling of £638k specific grant for the completion of the Men’s and Women’s Direct Access Centres is included. However, a separate report on the Men’s and Women’s DACS will be submitted to the Executive Board in due course.
HRA Residual Programme, Total Budget £3.653m
Following the successful final stock transfer on 31 March 2008 of all of the remaining Council housing stock, the City Council is in the process of closing the HRA account. However, there are still projects that the City Council is committed to funding and will need to make provision for from its general resources.
Demolition and Home Loss Programmes
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Housing Capital Programme 2008/09 (SSC/8)Report | 9 pages | DownloadRead as text |
PDF |
SSC8: Housing Capital Programme 2008-09 Appendix AAppendix | 1 pages | Download |
PDF |
SSC8: Housing Capital Programme 2008-09 Appendix BAppendix | 6 pages | Download |
PDF |
SSC8: Housing Capital Programme 2008-09 Appendix CAppendix | 3 pages | Download |
Follow Sustainable Communities Select Committee 2008/09 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Apr 2009 | Minutes of the Last MeetingAgreed that , subject to the deletion of the words “Councillor Barbara Mace” and the insertion of “Councillor Barbara... | Agreed | Open |
| 14 Apr 2009 | Annual Report 2008/09Agreed that the report be noted. | Agreed | Open |
| 14 Apr 2009 | Use of Scheme of DelegationAgreed that the report be noted. | Agreed | Open |
| 14 Apr 2009 | Authority to revise the contract sums for the restoration of Stanley Park (A&D/64)Resolved that – (i) the recommendation be approved; and (ii) the decision be referred to the Sustainable Communities ... | Approved | Open |
| 14 Apr 2009 | Exclusion of Press and PublicAgreed that members of the press and public be excluded from the meeting of the Select Committee during consideration... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.