Resolved that – (i) having considered the Council’s possible future financial position and other projects put forward for approval, the priority of the Private Finance Initiative ( PFI ) scheme (a design, build, finance and operate contract) to redevelop Liverpool Central Library and Archive for progression, having regard to the sustainability of the Council’s financial position beyond 2012/13; be confirmed; (ii) the Head of Libraries and Information Services be granted authority to take the Central Library PFI scheme to tender up to the identification of a Preferred Bidder through European Union Procurement procedures when a further report will be submitted to the Executive Board detailing actual projected costs and seeking permission to proceed to contract; (iii) the Board be advised that the annual contribution may vary, but that further reports and updates of the expected affordability gap will be submitted following receipt of tenders and prior to appointment of a Preferred Bidder; and (iv) the Board is further advised that a main purpose of commencing the procurement process is to finalise the total project costs. A future report will seek approval to proceed to contract and will provide final costings and the method by which any additional costs will be met including minor revisions to the scheme following competitive dialogue with bidders, efficiencies made during the closure period of the buildings for development and realising library service assets. ESE/17
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
The recommendations 17 February 2006 (Report LC/004/05) and the 28 July 2006 (Report LC/07/06) were to approve acceptance in principle of the PFI credits, to secure endorsement of the scheme by the government Project Review Group (PRG), to take the scheme through European tender and to establish a City Council Project Board.
The scheme was taken to European tender in October 2006 but in March 2007, the second bidder withdrew (internal company changes) leaving a sole bidder. Discussions with the DCMS and Treasury throughout 2007 did not result in the scheme being allowed to proceed with a sole bidder.
Revised Reference Scheme
The Project Team carried out a review of the project scope to produce a new Reference Scheme that will meet the affordability envelope and to make the scheme more attractive to the PFI market place.
2020 Liverpool were commissioned to work with the Project Team to produce a Revised Reference Scheme. The Revised Reference Scheme was endorsed by the Central Library and Archive Project Board on 8 July 2008.
The project is structured within the existing affordability envelope as the DCMS refused Liverpool City Council’s request in January 2008 for additional PFI credits to recover the original affordability position of the scheme. The four key outputs of the Central Library and Archive Redevelopment are:
• The restoration and renovation of the historic buildings. • A new repository for archives and rare books which meets the requirements of BS5454 (the national standard). • A high quality building with a new entrance on William Brown Street. • Space to deliver the New Service Concept for Library and Archive Services.
a. Summary of the new reference scheme capital works
i. Demolition of the existing 1950’s Brown Library (retaining the historic facade) and 1978 eight storey Extension. ii. Construction of a new four storey library with new entrance on William Brown Street, with a new six storey archive and rare book repository at the rear to replace the demolished buildings. A new rear vehicle entrance to avoid the requirement for access across the adjacent National Museums Liverpool (NML) land. iii. Restoration of the historic Picton, Hornby and Oak buildings. iv. The overall gross floor area would be in the region of 12,500 sq. m., comprising 8,000 sqm new build, 3,300 sq. m. historic areas, and 1,200 sq. m, Clayton Stack building. v. Essential works to Clayton Stack.
b. Soft Market Testing
Potential bidders were contacted to gauge their level of interest in the Revised Reference Scheme and see if they would submit an expression of interest and pre qualification questionnaire if a notice were placed in the Official Journal of the European Union (OJEU).
Four consortia have confirmed that they would bid for the project.
The scheme needs a minimum of two bidders to take it through the competitive dialogue procurement route of PFI, assuming they meet the Council‘s pre qualification criteria relating to financial, commercial and technical capacity. This renewed market interest informed the Project Board's recommendation to take the scheme to tender through OJEU.
c. Government approvals
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.