Amendment to Capital Programme and Acceptance of Tenders - Walton Hall Park and Mab Lane Play Provisions (SSC/17)

Decided Executive 1 paper

Executive Board decided this item on Friday 12 September 2008. Below is the council's own wording, with the papers it was decided on.

Item50m

Resolved

Resolved that in connection with Walton Hall Park and Mab Lane Play Provision - (i) the capital programme be amended by £100,000; (ii) the Bramall Construction tender of £179,858.63 for building, fencing and landscaping of Walton Hall Park be accepted; (iii) the Play Quest tender of £75,000 for the Construction and build of the Adventure Play Ground at Walton hall Park be accepted; (iv) 2o2o Fees for Walton Hall Park of £75, 867 be accepted; (v) the J Yearsley & Sons tender of £155,876.53 for Refurbishment, fencing and Landscaping at Mab Lane Youth Centre be accepted; (vi) the Play Quest tender of £65,000 for the Construction and build of the Adventure Play Ground at Mab Lane Youth Centre be accepted; and (vii) 2o2o Fees of £71,893 for Mab Lane be accepted.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 4 pages

Executive summary

As part of the Big Lottery project portfolio previously agreed by Executive Board (CHS/57/06), it was agreed to create an adventure playground at Walton Hall park and Mab Lane Youth Centre.

Walton Park – there is currently no provision for adventure play; the scheme will create an adventure playground and small office. In accordance with Standing Orders procedures, tenders were invited by the Corporate Procurement Unit; and returned from 5 companies with the chosen scheme being from Bramall Construction. The company will construct office, landscape and fence the site. A second tender for the construction of the adventure playground was advertised and returned by 3 companies, with the chosen scheme being from Play Quest. Walton Park scheme has full planning permission subject to the elevations for play equipment submission.

Mab Lane – the scheme is to refurbish the existing Youth Centre and create an adventure playground. In accordance with Standing Orders tenders were invited by the Corporate Procurement Unit and returned from 6 companies with the chosen schemes being from J Yearsley & Sons. The company will refurbish building, landscape and fence the site. A second tender for the construction of the adventure playground was advertised and returned by 3 companies, with the chosen scheme being from Play Quest. Mab Lane scheme has full planning permission subject to the elevations for play equipment submission.

The capital budget awarded by the Big Lottery is £531,713. The scheme tenders and fees have been received at £631,738. A successful application has been made to the PCT for funding to support the anti obesity strategy through the provision of the play rather than reduce the quality of the provision for children and young people. Executive Member/Director recommendation:

The Executive Director, Stuart Smith, recommends that:

1. The capital programme be amended by £100k

2. The Bramall Construction £179,858.63 tender for building, fencing and landscaping of Walton Hall Park be accepted

3. The Play Quest tender of £75,000 for the Construction and build of the Adventure Play Ground at Walton hall Park be accepted

4. 2020 Fees for Walton Hall Park of £75, 867 be accepted

5. The J Yearsley & Sons £155,876.53 tender for Refurbishment, fencing and Landscaping at Mab Lane Youth Centre be accepted

6. The Play Quest tender of £65,000 for the Construction and build of the Adventure Play Ground at Mab Lane Youth Centre be accepted

7. 2020 Fees of £71,893 for Mab Lane be accepted

Key Decision: The decision is a key decision at it requires an amendment to the capital programme

Forward Plan:

Notice had already been given of the capital programmes through the previous Executive Board reports which approved the Play Strategy and Big Lottery projects.

Implementation effective from: 19 September 2008

Timescale for action: Contracts will be issued on approval of the Executive Board

Reason(s) for Recommendation:

The increase in budget is due to tenders being higher than estimates provided for the projects. The additional funding is essential if the range and quality of provision agreed with the young people and Big Lottery is to be met. Alternative options considered:

The alternative option is to reduce the quality of the build and range of provision. This was would have a significant impact on the relatively small projects. The projects support the anti obesity strategy and reductions in anti- social behaviour by providing opportunities for safe, supervised physical activity

Consultation

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Amendment to Capital Programme and Acceptance of Tenders: Walton Hall Park and Mab Lane Play Provisions (SSC/17)Report 4 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Amendment to Capital Programme and Acceptance of Tenders - Walton Hall Park and Mab Lane Play Provisions (SSC/17)This decision
  2. Called In Item - Amendments to the Approved Housing Capital Programme 2009/10 at the end of the Third Quarter (SSC/38)Approved
  3. Amendments to the Approved Housing Capital Programme 2009/10 at the end of the Third Quarter (SSC/38)Decided
  4. Amendments to the Approved Housing Capital Programme 2008/09 (SSC/37)Decided
  5. Amendments to the approved Housing Capital Programme 2007/08 (NH/9)Decided
  6. Capital Programme 2006/07 Amendments (R&T/59)Decided

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies