Children’s Services Capital Programme - update November 2008 (ESE/21)

Approved Executive 3 papers

Executive Board approved this item on Friday 30 January 2009. Below is the council's own wording, with the papers it was decided on.

Item125e

Resolved

Resolved that the recommendation be approved subject to the reference to Annex in paragraph ( i ) above being amended to refer to the revised Annex as submitted. ESE/27
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 18 pages

Executive summary

The purpose of the report is to seek authority for the amendments to the Children’s Services Capital Programme, virements between cost centres and accept additional central government capital allocations.

1. Background Information and Context

The Children’s Services Capital Programme comprises a diverse range of projects aimed at tacking specific asset management priorities at schools relating to condition, suitability and sufficiency, the delivery of national and local strategies such as the implementation of children’s centres and the Building Schools for the Future project, Corporate aims and objectives and those set out in the Corporate Asset Management Plan and Capital Strategy. The programme as detailed in this report was last updated and approved at the Executive Board of 28 March 2008 (CHS/37/08).

The programme underpins the priorities set out in the Children’ and Young Peoples Plan and by investing in the futures of our young people by improving the quality of their learning environments, the programme directly supports the City Council’s aims of developing first rate education and training from early years and those Corporate aims that will:

• Ensure safeguarding and inclusion of the most needy and excluded groups in the city providing equality and real opportunity for improvement and enhanced quality of life; • Confront barriers to employment and training through lack of access, deprivation, discrimination and poor health to ensure provision of a highly skilled workforce

• Challenge crime and antisocial behaviour safeguarding young people from becoming perpetrators or victims

• Provide sustainable communities through access to decent homes and best practice in environment management including, recycling, street cleansing and environmental enforcement against dereliction and environmental detractors. 2. Sources of Funding

The majority of projects are financed by a variety by central government grant and annual supported borrowing allocations and the programme also includes a number of specific one-off initiatives financed by lottery funding, other grant funding and approved general resources.

In addition to individual project contingencies that will vary depending upon the scale of each scheme, a programme contingency is retained in the form of unallocated grant that can be committed as appropriate either to reserve or unforeseen projects or to increase individual scheme budgets as required. A number of such projects are identified in this report.

3. Option Appraisal

The projects contained within the existing approved programme have been identified as priorities and the subject of option appraisals specific to each sub programme. For example planned maintenance schemes are determined following asset management surveys and quarterly updates provided by 2020 Liverpool having regard to potential linkages with other programmes, school organisation proposals and health and safety implications. Technical solutions for each of these proposals will then factor in overall cost and value for money, proportionality and scale in relation to the nature of each project, lifecycle (e.g. initial cost compared to longer term benefits that may accrue in the form of revenue savings) and the potential benefits from delivering a more holistic solution to a project (e.g. dealing in a number of planned maintenance items as part of a larger refurbishment plan).

4. Value for Money

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Children’s Services Capital Programme: update November 2008 (ESE/21)Report 18 pages DownloadRead as text
PDF
ESE.21 annexeAppendix 13 pages Download
PDF
Revised Annexe AAppendix 5 pages Download

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Children’s Services Capital Programme - update November 2008 (ESE/21)This decision
  2. Children's Services Scorecard and Performance HighlightsDecided
  3. Children's Services Cabinet Member UpdateAgreed
  4. Children's Services Cabinet Member UpdateAgreed
  5. Recruitment to post of Director of Children and Young People's ServicesApproved
  6. Arrangements for Transition from Children's Services to Adult ServicesAgreed

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies