Resolved that – (i) a demolition contract for Long Lane Depot be awarded to JP Tisdale up to a maximum of £312,150 (tender price of £284,150 plus £28,000 contingency if required); (ii) total expenditure can be incurred up to a maximum of £342,000 (including tender price, contingency, fees and surveys) in 2010/11 and 2011/12, as outlined in the report submitted, to be financed through unsupported borrowing from a previously approved capital budget of £2.7m ; (iii) the Capital Programme be updated accordingly including the removal of the remaining former borrowing approval against Long Lane and vire these remaining resources back to the previously established generic BSF funding allocation; (iv) authority be granted to spend resources; (v) a further report be considered by Members in the event further below-ground remediation works are required should the site be recommended for educational use or other development; and (vi) in the event that Members conclude that the Long Lane Depot site is not required for educational use in the long-term, the site be marketed for disposal. N/8
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
The Council-owned Long Lane Depot will be fully vacated in February 2011 following a decant process that commenced in early-2010 subsequent to the proposal to rebuild Archbishop Beck on the site as part of BSF Wave 6.
Following the cancellation of Liverpool’s BSF programme by the coalition government in July 2010, this report seeks approval to award a demolition contract (from a previously approved budget) to clear the site down to slab level in order to: • Mitigate against potential health and safety risks to the Council (by leaving a relatively isolated and large site with some semi-dilapidated structures). • Prevent the Council paying ongoing revenue costs by retaining a large empty site with significant business rates. • Take advantage of very competitive market prices as a result of the recession in the construction industry and, the high price of scrap metal at present.
Background
Archbishop Beck Secondary School was a ‘sample scheme’ as part of the BSF Wave 6 proposals. Following a detailed site option appraisal, it was proposed that the school move to the larger and more visible Long Lane Depot site under BSF as a new build scheme. Outline planning consent was obtained in July 2009.
Following the vacation of the main occupier Enterprise-liverpool in 2007, the majority of the site has remained empty with only a handful of small LCC teams in occupation on a large site incurring business rates, utility charges and maintenance costs. Following the approval of the BSF Wave 6 Outline Business Case in February 2010, these remaining teams started to vacate the site with the final relocation programmed for February 2011. A Cabinet report in early-2010 (26 March 2010) approved expenditure of up to £2.7m to undertake a complete clearance and remediation of the site prior to the Council handing the site over to the proposed BSF Wave 6 contractor programmed for mid-2011.
Now the BSF Wave 6 project has been cancelled and premises vacated, the Council is left with the burden of the Long Lane Depot site with health and safety risks, potential anti-social behaviour and ongoing running costs.
Although there are ongoing strategies (led by a BSF Taskforce) to reconstruct a ‘BSF Rescue Plan’, it could be some time before a definitive programme is established. Given the lack of clarity at this point in time, it is now proposed to undertake a ‘basic’ site clearance scheme to remove the financial and safety liabilities at the site at lowest capital cost to the Council.
Procurement:
The original tender documentation was developed as a complete demolition and remediation scheme in order to hand a fully clean site over to the BSF Wave 6 contractor without any residual risk retained with the Council. As a proposed PFI scheme, an overly cautious approach was taken with the proposed works to reduce the risk of future compensation events by the PFI special purpose vehicle.
As a result of the BSF cancellation however, the tender documentation was amended to allow for full building clearance including foundations and utilities with some isolated remediation of identified contamination hotspots rather than complete remediation of the site.
Tenders have recently been sought (subject to contract) against this specification. Following a technical tender appraisal by 2020 Liverpool and financial check by LCC Finance, the most economically advantageous compliant tender is from JP Tisdale at £459,150 which, also happens to be the lowest tender..
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.