During the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of the relevant budgetary position and any relevant actions arising. This report summarises matters of relevance for the twelve-month period and provides information on the final outturn for the budget.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
(i) note that the outturn of capital expenditure for 2019/20 is £217.79M. This compares against the approved budget of £272.41M;
(ii) note that the capital programme is financed having regard to the available resources and in accordance with the overarching principles set out in the Capital Strategy Statement approved in March 2019 so that the requirement for borrowing is minimised wherever possible;
(iii) note that during March, the final month of the financial year, £34.04M of expenditure was incurred, which represents 15.6% of the total spend for the year; and
(iv) approve the Capital Programme for 2020/21 to 2024/25 reflecting the carry forward of £41.23M of capital commitments from 2019/20 along with the associated funding.
Background
Capital programme monitors are produced for each month of the financial year with a final outturn report in June setting out the final spend and financing position for the year. This report is the capital programme outturn report for 2019/20.
The Capital Strategy Statement 2019/20 to 2023/24 was approved by City Council on 6th March 2019. This included indicative allocations of capital grants for 2019/20 to 2023/24. Further reports have been approved during the year including the more recent Capital Strategy report presented to Cabinet on the 21st February 2020 and subsequently ratified by Full Council on 4th March 2020.
After accounting for rescheduling, projects carried forward to 2020/21 and approval of additional resources the final 2019/20 programme spend has amounted to £217.79M. 4. Capital Expenditure Outturn for 2019/20
Table 1 below shows the capital expenditure outturn for 2019/20 compared to the approved budget. It should be noted that an underspend variance on schemes can represent rescheduling into a future year rather than a scheme being delivered for less than budget, and the funding available. Where budgets are no longer considered to be required, i.e. on account of changes in the original scheme delivery or due to a change in priorities, then the budget has been removed from the Programme.
Table1:Approved Capital Programme Budget to Outturn
2019/20 Budget Revised 2019/20 Variance Approved Changes 2019/20 Outturn (under) / Budget Approved Capital over post Programme spend Month 11 £M's £M's £M's £M's £M's
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.