Resolved
Agreed that – the report be noted; the Committee welcomes the robust and effective system of risk management; and Officers arrange for the Risk Management Policy to be signed by the Chief Executive and Leader of the Council.
Audit and Accounts Committee 2007/2013 agreed this item on Wednesday 23 March 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that – the report be noted; the Committee welcomes the robust and effective system of risk management; and Officers arrange for the Risk Management Policy to be signed by the Chief Executive and Leader of the Council.
Liverpool City Council
Report to: Audit and Accounts Committee
Subject: Risk Strategy Update
Report no: Audit 47/2011
Date: 23 March 2011
Reporting officer: Susan Curran-Director of Finance and Resources
Contact officer: Peter Taylor – 0151 225 2651
Ward: All
1. Purpose and recommendations
Purpose: The purpose of this report is to provide members with an update on the Council’s Risk Management Strategy and to report progress against the Risk Management Improvement Plan 2010/11. This report updates previous reports to members, the most recent of which was as at 26 January 2011. For ease of review, new and updated information on progress during the year is shown in red in the attached report and appendices.
The principal areas of progress since the last review as at 26 January are as follows-
As at March 2011 good progress has been made in obtaining risk registers for significant partnerships and embedding them into the council’s JCAD system. Risk registers have been obtained from the majority of the council’s strategic partnerships.
Recommendation: That members consider the report.
2. Relevant background information
The Council’s arrangements for managing risk are set out in the Risk Management Strategy 2010/13 (attached as Appendix 2) which was approved by the Executive Board on 26 February 2010. Following successful completion of a risk management improvement plan in 2009/10, the strategy incorporated a risk management improvement plan for 2010/11.
3. Key issues
The 2010/11 Risk Management Improvement Plan is included in the Risk Management Strategy attached as Appendix 2. A schedule showing the progress against all of the planned actions in the plan as at the end of Quarter 3 of 2010/11 is attached as Appendix 1.
Substantial progress has been made against the improvement plan with the majority of planned actions being complete or ongoing.
Developments during 2010/11 to date have included:
• Update and review of all tiers of risk registers (Corporate, AIM, AD and business units). Active risk champions are in place for all Aims; • Completion of development of Risk Management intranet page; • Continuing roll-out of training to staff and members as well as development of risk based training material for inclusion in induction training; • Inclusion of major projects in the council’s risk management database (JCAD) and the ongoing monitoring of those risks via JCAD. • A start on the process of mainstreaming partnership risks into the council’s risk management framework and the establishment of risk registers for significant partnerships. As at March 2011 good progress has been made in obtaining risk registers for significant partnerships and embedding them into the council’s JCAD system. Risk registers have been obtained from the majority of the council’s strategic partnerships. • Review and update of the risk management toolkit for staff on the intranet; • Progress on embedding risk management in schools.
4. Equalities Implications /Equality Impact Assessment
There are no equalities implications arising from this report.
5. Conclusions/ Legal Implications
Significant progress has been made in the 2010/11 Risk Management Improvement Plan and it is anticipated that the plan will be substantially completed as at the year end.
6. Key to any abbreviations used None 7. Documents attached
Appendix 1 Risk Management Improvement Plan 2010/11—Status of Implementation of Planned Actions Appendix 2 Risk Management Strategy 2010/13 Appendix 1
Risk Management Improvement Plan 2010/11
Status of Implementation of Planned Actions
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Risk Strategy UpdateReport | 17 pages | DownloadRead as text |
Follow Audit and Accounts Committee 2007/2013 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Mar 2013 | Minutes of the Last MeetingAgreed that the minutes of the last meeting of this Committee held on 23 January 2013 be approved as a true record. M... | Agreed | Open |
| 20 Mar 2013 | Informing the Audit Risk AssessmentAgreed that the report be noted. | Agreed | Open |
| 20 Mar 2013 | Grant Thornton Audit Plan 2012/13Agreed that – i. The Audit Plan 2012/13 be noted; and ii. The officer response to the Action Plan be noted. | Agreed | Open |
| 20 Mar 2013 | Grant Thornton Accounts and Audit Committee Update March 2013Agreed that – i. the report be noted; and ii. the officer responses to the report referred to in the note appended to... | Agreed | Open |
| 20 Mar 2013 | Monitoring Report - Regulation of Investigatory Powers Act 2000Agreed that the report be noted. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.