Site Assembly Strategy in the Wavertree Zone of Opportunity (HCS/15)

Approved Executive 1 paper

Cabinet 2010/21 approved this item on Friday 17 February 2012. Below is the council's own wording, with the papers it was decided on.

Item126e

Resolved

Resolved that – (i) Cabinet approves the principles of this site assembly strategy, and The Riverside Group’s contribution of properties to the approved Housing Renewal programme; (ii) the principles of this site assembly strategy are adopted in the other Housing Renewal areas subject to the specific details of all proposed development agreements being reported to Cabinet for approval; and (iii) the Interim City Solicitor in consultation with the Director for Regeneration and Employment be authorised to negotiate, settle and complete all necessary legal documentation to implement the strategy and to complete site assembly with TRG for Edge Hill Phase 3, Picton Phase 3 and Prescot Road. HCS/16
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet 2010/21, 7 pages

KENSINGTON & FAIRFIELD, PICTON WARDS STATUS – PUBLIC HCS/15

Cabinet Member: Director: Ann O’Byrne – Housing and Nick Kavanagh – Regeneration and Community Safety Employment

Councillor Paul Brant – Finance & Peter Timmins – Interim Director of Resources Finance & Resources

Date of submission: Subject: 3rd February 2012 Site Assembly Strategy in the Wavertree Zone of Opportunity

Report No./Background papers: Contact Officer: EDR/6/12 HSC/4 Housing Capital Programme Julie Wickington – Housing Renewal 2011 – 2013 (29th July 2011). Manager 0151 233 2464

Executive summary It is being recommended that the Cabinet accepts the principles set out within this report to facilitate The Riverside Group’s (TRG) contribution of 131 properties to the approved Housing Renewal programme and to facilitate the negotiation of similar arrangements with other Registered Providers in the future subject to approval of such arrangements by the Cabinet. The approach will significantly reduce the amount of resources required by the Council to assemble the sites for re-development. It is noted that as a result of the proposals the Council’s share of future capital receipts on the sale of development sites will be lower than would otherwise be the case.

Purpose of the Report To report on the outcomes of discussions with TRG, the lead Registered Provider (RP) in the Wavertree Zone of Opportunity to facilitate the completion of site assembly in approved clearance and redevelopment areas (Edge Hill, Picton Phase 3 and Prescot Road). To seek approval of the principles discussed with TRG and to adopt these principles in the other Housing Renewal areas with detailed proposals in relation to individual sites / phases being reported to Cabinet for approval when site specific development agreements are entered into. TRG’s board has agreed in their business plan to transfer properties/land to the City Council’s Housing Programme on the basis that the Council will demolish the properties at its own expense. The costs of the demolition works are estimated to be more than the value of the properties / land. Therefore the Council anticipates that subject to Riversides approval the properties / land will be acquired for a nominal consideration of £1.

Background The Council declared Renewal Area’s in 2004 (Kensington) and 2005 (Picton) for a 10 year period to 2014 and 2015 respectively. Annual Housing Renewal Programmes are approved, which detail the resources required to acquire and clear properties to assemble sites for redevelopment. Due to financial constraints affecting the delivery of site assembly, a new approach to complete the assembly of the remaining phases (Edge Hill Phase 3, Picton Phase 3 and Prescot Road) is now being proposed. This approach will significantly reduce the amount of resources required to assemble the sites, but will also reduce the amount of capital receipts ultimately received by the Council. Similar discussions have been taking place with other lead RPs in the other Housing Renewal Areas on the same basis.

To complete the assembly of the priority sites TRG Board agreed on the 9th December 2011 to include the 131 properties they own within the Housing Renewal site assembly programme. If the Council’s Cabinet agree to the principles of this site assembly strategy, this will generate a contribution in kind from TRG being a saving to the Council’s future housing capital programmes for site assembly of c£8.4m.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Site Assembly Strategy in the Wavertree Zone of Opportunity (HCS/15)Report 7 pages DownloadRead as text

More from Liverpool Cabinet 2010/21

All decisions
MeetingDecisionOutcome
5 Jun 2020 Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. Approved Open
5 Jun 2020 Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... Decided Open
5 Jun 2020 Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... Approved Open
5 Jun 2020 Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open
5 Jun 2020 Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies