Liverpool City Council
Mayoral Select Committee 2012/13, Tuesday 12 February 2013

Capital Programme 2013/2014 to 2017/2018

Agreed Committee 1 paper

Mayoral Select Committee 2012/13 agreed this item on Tuesday 12 February 2013. Below is the council's own wording, with the papers it was decided on.

Item25

Resolved

Agreed that the recommendations be approved so far as the Committee is concerned.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Mayoral Select Committee 2012/13, 12 pages

MAYORAL RECOMMENDATION

CITY STATUS – PUBLIC F&R/10

Cabinet Member: Director: Councillor Paul Brant Becky Hellard Cabinet Member - Finance & Director - Finance & Resources Resources

Date of submission: Subject: 22 February 2013 Capital Programme 2013/2014 to 2017/2018

Report No./Background papers: Contact Officer: DFR09/13 Tim Povall, Head of Finance 225 2200

1. Executive Summary 1.1 This purpose of this report is to set the Capital Strategy for the five years 2013-18, based around two over-riding principles:

• It is priority led; and, • That the revenue costs are affordable.

2. Recommendations 2.1 That Members approve –

(i) the revised capital programme of £204.967m in 2013-14 and £258.963m for 2014-15 to 2017-18 as set out at 4.1 and in Annex 1 of the report submitted;

(ii) the policy that reductions in assumed Government capital funding be pass-ported through to services they support, as set out in paragraph 3.2 of the report submitted;

2.2That Members note –

(iii) the significant investments being made to deliver the Mayoral Priorities of New Schools, Building Houses and increasing employment opportunities; and

(iv) that affordable long-term solutions, for major strategic programmes that are currently starved of funding, such as Highways Maintenance, will be developed in 2013 through appropriate financial models 3 Background 3.1 The Capital Programme 2012-13 to 2016-17 was approved by the Council on 7th March 2012. The Council’s Capital Programme is subject to regular review with monitoring reports submitted to Cabinet monthly. The budgets included previously for 2013-14 to 2016-17 were based on the assumptions at the time, and now need to be revised and extended.

3.2Estimates of Capital Allocations were known to be subject to future variations. This report presents to Members the proposed Capital Programme for 2013-14 to 2017-18. This includes the confirmed or indicative capital grant allocations for 2013-14 and future years. Any changes to capital grant allocations will be pass-ported through to services.

3.3The current capital programme for 2013-18, as reported in the Period 8 monitor (Cabinet 25th January 2013) foresees the capital expenditure of £524m over the next five years, as follows:

Table 1: Original Capital Programme 2012-13 to 2016-17 & Period 8 2011-12 2012/13 Programme 2013/14 2014/15 2015/16 2016/17 2017/18 Total £000’s £000’s £000’s £000’s £000’s £000's £000’s 143,827 Original 79,969 48,346 52416 41216 n/a 365,774 139,046 At Period 8 153,183 85,304 91,616 30,772 24,145 524,066

3.4The significant growth in this programme reflects additional grant allocations received during 2012/13 and the approval of the Liverpool Schools Investment Programme.

4 Programme bids 4.1 Table 2 below gives an indicative Capital Programme for 2013-14 onwards based on current information on schemes and funding. The capital programme is subject to continuous change as new resources and projects are identified, and will be updated throughout the year. Table 2 – Indicative 2013-14 to 2017-18 Capital Programme 2013/14 2014/15 2015/16 2016/17 2017/18 Estimate Estimate Estimate Estimate Estimate Total

£,000's £,000's £,000's £,000's £,000's £,000's

Transportation 18,224 18,058 17,739 7,739 6,039 67,799 Regeneration Programmes (SLEGI) 650 0 0 0 0 650 Regeneration Developments (RGF / GPF etc) 52,070 4,407 0 0 0 56,478 Exhibition Hall & Hotel 45,099 12,050 57,149 Adult Social Care 1,764 1,622 0 0 0 3,386 Childrens 548 0 0 0 0 548 Schools & Education 4,902 4,762 4,762 4,762 4,762 23,948 Liverpool Schools Investment Programme (LSIP) 24,090 54,424 53,091 17,119 9,644 158,368 Leisure 1,050 400 0 0 0 1,450 Environment 651 76 0 0 0 727 Housing & Neighbourhood 51,586 15,877 5,877 5,877 5,877 85,094 Corporate 4,333 1,000 1,000 1,000 1,000 8,333

Grand Total Expenditure 204,967 112,676 82,469 36,497 27,322 463,930

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme 2013/2014 to 2017/2018Report 12 pages DownloadRead as text

At this meeting

Whole meeting
24Budget Savings Options Tranche 3On the agenda
25Capital Programme 2013/2014 to 2017/2018This decision
28Minutes of the Last MeetingApproved

On this subject at Liverpool

Search all
  1. Capital Programme 2013/2014 to 2017/2018This decision
  2. Corporate Risk Register Deep Dive - CR2 Capital ProgrammesAgreed
  3. Capital Programme 2019/20 - Final Outturn PositionDecided
  4. Capital Programme Monitor 2019/20 - Month 11 (February 2020)Agreed
  5. Capital Programme Monitor 2019/20 - Month 10 (January 2020)Decided
  6. Capital Programme Monitor 2019/20 - Month 9 (December 2019)Decided

More from Liverpool Mayoral Select Committee 2012/13

All decisions
MeetingDecisionOutcome
21 Mar 2013 Mayoral Commissions UpdateAgreed that – (i) the update be noted and welcomed; and (ii) a standing Agenda Item be included on future meetings of... Agreed Open
21 Mar 2013 Minutes of Last meetingAgreed that the minutes of the meeting held on 28 th February 2013 be approved as a true record. Agreed Open
28 Feb 2013 Mayoral Commissions UpdateAgreed that the update be welcomed and noted. Agreed Open
28 Feb 2013 Motion - Extension of Dog Control Orders area by Councillors Steve Radford, Hazel Williams and Chris LentonAgreed that a report come back to this committee on the matter following a briefing note being prepared, as above, an... Agreed Open
28 Feb 2013 Council Motion - Improved co-operation between Merseyside Authorities by Councillor Pat MoloneyAgreed that the update be noted. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies