Resolved
Agreed that the report be noted.
Finance and Resources Select Committee 2012/13 agreed this item on Wednesday 13 February 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that the report be noted.
Appendix 1 Revenue Monitor 2012/13 Month 8 (November 2012) LIVERPOOL CITY COUNCIL
Cabinet – 25th January 2013
Date – 20th December 2012
Contact Officers:
Becky Hellard – Director of Finance & Resources – 0151 225 2347 [email protected]
Peter Casterton - Head of Finance - 0151 225 2596 [email protected] SUBJECT: REVENUE MONITOR 2012/13 MONTH 8 (November 2013)
Summary The report sets out the revenue forecast for 2012/13 as at Month 8 and identifies ongoing management actions to ensure that the year-end position will result in a managed budget underspend..
Recommendations Members are asked to: A. Note that in setting the 2012/13 General Fund Budget the City Council faced a budget gap of £50m. This is on top of successfully bridging a budget gap of £91.4m in 2011/12 and a head count reduction of approximately 2,000 in 2 years. It is estimated that the revenue budget gap for the City Council over the 4 year Comprehensive Spending Review period from 2011/12 to 2014/15 is over £200m. This gives context to the current financial forecast for 2012/13.
B. Note at the end of Month 8 (November 2012) the full year forecast projects a potential general fund underspend of £1.025m, as against a full year potential general fund underspend of £0.382m in Month 7. There are 4 months left of the financial year to manage the forecast year end underspend to help mitigate against the financial risks associated with a late 2013/14 Local Government Finance Settlement from National Government. The Dedicated Schools Grant (DSG) funded activities are forecast to break even after the use of earmarked reserves.
C. Note that management actions have been identified to recover the Directorate overspends and these are detailed in Appendix 2.
D. Note that there are a number of risks and uncertainties that may impact adversely on the general fund financial forecasts for the remainder of 2012/13. These are shown in Section 4 of the report and include increased demand pressures for services, impact of the economic downturn, claims made against the City Council and that of the 2012/13 budget savings options still to be delivered £6.253m have been identified as green, and £4.899m identified as amber.
E. Approve the draw down of earmarked reserves of £0.512m as outlined in Section 5.1 of this report relating to specific initiatives. REPORT 1. Background
1.1Revenue budget monitors are produced each month of the financial year with a year end report in June, as set out in the schedule at Appendix 1. The reports track progress against the agreed budget decisions, forecast any anticipated significant variances to the budget, and enables corrective action to be taken.
1.2The main issues that have arisen at Month 8 (November 2013) include:
• As at Month 8 there is an overall forecast year end General Fund underspend of £1.025m, after the draw down of earmarked reserves, made up of the six Directorates potential underspend of £0.250m, and a forecast underspend of £0.775m on capital financing costs.
• Within the Regeneration and Employment Directorate there is a forecast year end overspend of £1.565m, compared to £1.425m in Month 7. This forecast year end overspend is primarily within the Planning, Housing and Development Division (£0.790m) and the Culture and Tourism Division (£0.821m). This forecast year end overspend has fallen significantly since the start of the year (Month 3 forecast a £3.183m year end overspend) as managers have taken action to implement service reviews, generate additional income and fully implement budget options. There are further ongoing management actions to identify additional in year savings from across the Directorates and to review income forecasts to mitigate the remaining potential overspend.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
RM-M8 November 12 Appendix 2Appendix | 2 pages | Download |
PDF |
RP -M8: Appendix 1Appendix | 1 pages | Download |
PDF |
RP -M8: Appendix 3Appendix | 1 pages | Download |
PDF |
RP -M8: Appendix 4Appendix | 1 pages | Download |
PDF |
Revenue Monitor Month 8: November 2012Report | 13 pages | DownloadRead as text |
PDF |
Revenue Monitor Report for Month 8 (November 2012)Report | 3 pages | Download |
Follow Finance and Resources Select Committee 2012/13 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Apr 2013 | Minutes of the Last MeetingAgreed that the minutes of the last meeting of this Select Committee held on 13 February 2013 be approved as a true r... | Agreed | Open |
| 3 Apr 2013 | Making Decisions: Equality Briefing for Elected MembersAgreed that the officers be thanked for their very informative presentation. | Agreed | Open |
| 3 Apr 2013 | ICT Strategy UpdateAgreed that Catherine Garnell be thanked for her presentation. | Agreed | Open |
| 3 Apr 2013 | Medium Term Financial Strategy 2013/2014 to 2016/2017Agreed that the report and updated information be noted. | Agreed | Open |
| 3 Apr 2013 | Capital Programme Monitor Report for Month 10 (January 2013)Agreed that the report be noted. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.