Resolved
Agreed that the report be noted.
Finance and Resources Select Committee 2012/13 agreed this item on Wednesday 3 April 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that the report be noted.
Members are asked to:
A. Agree the Period 10 budget net decrease of £ 8.509m, to the latest 2012/13 capital programme already approved by Cabinet, of £136.706m, as included in Table 1 / Annex 1 (summary), to produce a revised programme of £128.197m.
B. Approve the capital budgets of £128.197m for 2012/13, £181.515m for 2013/14, £99.532m for 2014/15, £64.119m for 2015/16 and £36.497m for 2016/17 as detailed in Tables 2, 3 and 4. These sums update those included in the City Council Capital Strategy document for 2012-17 presented to Cabinet on the 17th February and Budget Council on the 7th March 2012.
C. Note the inclusion of a sum of £1.500m for young peoples infrastructure projects announced at the Council Budget meeting on the 6th March 2013. D. Note spend to date of £80.226m, representing a 62.6% of the revised total capital budget for 2012/13 (Annex 1), with 83.3% of the year having elapsed, and an anticipated projected spend of approximately £ 128.197m.
E. Note that spend is at 100.7% of planned profile so, at this point, it is on target to deliver budget at year end.
F. Note the position regarding the prudential indicators approved as part of the Treasury Strategy Report 2012/13, presented to Council 7th March 2012.
G. Note the total level of Council Borrowing of £367m (£ 317m borrowing and £ 50m Other Long Term Liabilities) as at 1st January 2013.
3.1The capital programme monitors are produced each month of the financial year with an outturn report in June. The Capital Strategy 2012/13 to 2016/17 report was approved by Council 7th March 2012. This included indicative allocations of capital grants for 2012/13 to 2016/17.
3.2The Council’s capital programme is subject to monthly review by a senior group of officers. Under a banner of the Capital Programme Group each new project will be scrutinised under a new “gateway process” to be confirmed as follows:
• Project approvals for financing, delivering corporate outcomes and delivery timetable;
• Financial appraisals for funding and ongoing revenue costs
• Spend profiles against delivery timetable;
• End of project reviews;
• Delivery of Asset Management Plans and overall strategy.
3.3The City Council will continue to identify future funding streams that are available to both itself and private developers to promote ongoing regeneration and investment.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CPM10: Annex 1Appendix | 1 pages | Download |
PDF |
CPM10: Annex 2Appendix | 1 pages | Download |
PDF |
CPM10: Annex 3Appendix | 3 pages | Download |
PDF |
CPM10: Annex 4Appendix | 6 pages | Download |
PDF |
CPM10: Annex 5Appendix | 1 pages | Download |
PDF |
Capital Monitor 2012-2013 Month 10: January 2013Report | 13 pages | DownloadRead as text |
PDF |
Capital Programme Monitor Report for Month 10 (January 2013)Report | 2 pages | Download |
Follow Finance and Resources Select Committee 2012/13 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Apr 2013 | Minutes of the Last MeetingAgreed that the minutes of the last meeting of this Select Committee held on 13 February 2013 be approved as a true r... | Agreed | Open |
| 3 Apr 2013 | Making Decisions: Equality Briefing for Elected MembersAgreed that the officers be thanked for their very informative presentation. | Agreed | Open |
| 3 Apr 2013 | ICT Strategy UpdateAgreed that Catherine Garnell be thanked for her presentation. | Agreed | Open |
| 3 Apr 2013 | Medium Term Financial Strategy 2013/2014 to 2016/2017Agreed that the report and updated information be noted. | Agreed | Open |
| 3 Apr 2013 | Revenue Monitor Report for Month 10 (January 2013)Agreed that the report be noted. ... view the full minutes text for item 79. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.