Resolved

Resolved that the recommendation be approved. ASC/20
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet 2010/21, 10 pages

Executive summary

Purpose of Report Following the completion of pre-construction activity over the past 4-months, this report seeks authority to award the construction contract for both Palmerston and Abbot’s Lea to Kier Construction under the Liverpool Schools Investment Programme.

Background Information In November 2012, Cabinet of approved a report to progress the delivery of the Liverpool School Investment Programme (LSIP). The report outlined an investment programme to deliver 12 new schools under the Mayoral priority and additional investment to the remaining estate that has not benefitted from either this Mayoral pledge or, previous investment through BSF or PFI or Primary Capital. The programme totals £169m over a 5-year period including investment to the secondary, special school and primary sector.

The investment to Abbot’s Lea and Palmerston was contained within the report and proposes a 6 and 4 classroom extension respectively to accommodate for the increasing demand for places in the special school sector.

Palmerston Palmerston is a special school catering for secondary aged children with Severe Learning Difficulties (SLD). The school has a city wide catchment and currently has around 97 pupils on role. There is however a real shortage of places for such children in the City with growing demands for such specialist provision. The premises are undersized for its current pupil population with a requirement to add a further 48 pupils to take the capacity to approximately 145.

The proposal is to add a 4-classroom extension to the front of the existing premises to provide a post-16 centre.

Abbot’s Lea School Abbot’s Lea is a special school catering for pupils with Autistic Spectrum Disorder (ASD) and MLD (Moderate Learning Difficulties). The school has a city wide catchment and has approximately 157 pupils on role. There are increasing pressures on places for both primary age and secondary age ASD pupils in the City leading the proposals to increase provision at Abbots Lea which has Ofsted Outstanding as a leading school for ASD education.

The proposal is to add a 6-classroom extension to the rear Abbots Lea allowing capacity to increase to approximately 194. The shortage of places within the city, currently 42 pupils (statemented with ASD needs) on the waiting list for September 2013, would mean that should this facility not be made available by September, LCC would have to send these pupils ‘out of area’ costing in excess of £2m per annum. The provision of extra places is therefore essential to avoid LCC incurring these costs.

Procurement Pre-construction orders have been placed with Kier Construction under the Scape Minor Works Framework to adapt the pre-designed ‘Connect’ product for each school and site. ‘Connect’ has been developed as a cost effective and quick new-build option by Scape for expanding schools.

The pre-construction phase is now in its final stages and subject to agreeing a final cost with Kier within the available budgets and obtaining full planning consent, this report seeks authority to award the construction contracts. The report also seeks authority to award an enabling works order to undertake demolition of the stable block at Abbot’s Lea, to site of the new ‘Connect’ extension.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Palmerston and Abbot's Lea Schools: Construction Expenditure (EDCS/20)Report 10 pages DownloadRead as text

At this meeting

Whole meeting

More from Liverpool Cabinet 2010/21

All decisions
MeetingDecisionOutcome
5 Jun 2020 Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. Approved Open
5 Jun 2020 Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... Decided Open
5 Jun 2020 Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... Approved Open
5 Jun 2020 Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open
5 Jun 2020 Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies