Capital Programme Monitor Report for Month 8 (November 2013)

Agreed Finance 7 papers

Finance and Resources Select Committee 2013/14 agreed this item on Wednesday 5 February 2014. Below is the council's own wording, with the papers it was decided on.

Item58

Resolved

Agreed that the report be noted.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Finance and Resources Select Committee 2013/14, 12 pages

Recommendations

Members are asked to:

A. Agree the Period 08 budget net increase of £9.524m, to the latest 2013/14 capital programme already approved by Cabinet, as included in Table 1 / Annex 1 (summary), to produce a revised programme of £202.922m.

B. Approve the capital budgets of £202.922m for 2013/14, £192.970m for 2014/15, £68.279m for 2015/16, £44.294m for 2016/17 and £27.110m for 2017/18 as detailed in Tables 2, 3 and 4. These sums update those included in the City Council Capital Strategy document for 2013/14 – 2017/18 (DRFC14/13) presented to Cabinet on the 22nd February and Full Council on the 6th March 2013.

C. Note spend to date of £93.751m, representing a 46.2% of the revised total capital budget for 2013/14 (Annex 1), with 66.7% of the year having elapsed, and an anticipated projected spend of approximately £202.922m.

D. Note that actual spend is showing a 4.8% shortfall against the budgeted profile. This represents a monetary value of £4.689m on a total 2013/14 Programme of £202.922m. This shortfall will need concerted managerial action and close monitoring if the reported forecast is to be maintained.

E. Note the position regarding the prudential indicators approved as part of the Treasury Strategy Report 2013/14, presented to Council 6th March 2013. F. Note the total level of Council Borrowing of £425m (£335m borrowing and £90m Other Long Term Liabilities) as at 30th November 2013. 3. Background

3.1The capital programme monitors are produced each month of the financial year with an outturn report in June. The Capital Strategy 2012/13 to 2016/17 report was approved by Council 7th March 2012. This included indicative allocations of capital grants for 2012/13 to 2016/17. This has been superseded by the Capital Strategy 2013/14 – 2017/18 (DFR14/13) report and the Capital Programme 2013/14 – 2017/18 report (DFR09/13) approved by Cabinet of 22nd February 2013 and Full Council 6th March 2013

3.2The Council’s capital programme is subject to monthly review by a senior group of officers. Under a banner of the Capital Programme Group each new project will be scrutinised under a new “gateway process” to be confirmed as follows:

• Project approvals for financing, delivering corporate outcomes and delivery timetable;

• Financial appraisals for funding and ongoing revenue costs

• Spend profiles against delivery timetable;

• End of project reviews;

• Delivery of Asset Management Plans and overall strategy.

3.3The City Council will continue to identify future funding streams that are available to both itself and private developers to promote ongoing regeneration and investment.

4. Original and latest proposed capital programme for 2013/14

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 1 pages Download
PDF
Appendix 2Appendix 2 1 pages Download
PDF
Appendix 3Appendix 3 2 pages Download
PDF
Appendix 4Appendix 4 2 pages Download
PDF
Appendix 5Appendix 5 1 pages Download
PDF
Capital Programme Monitor 13 14 Pd 8Report 12 pages DownloadRead as text
PDF
Capital Programme Monitor Report for Month 8 (November 2013)Report 2 pages Download

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Capital Programme Monitor Report for Month 8 (November 2013)This decision
  2. Corporate Risk Register Deep Dive - CR2 Capital ProgrammesAgreed
  3. Capital Programme 2019/20 - Final Outturn PositionDecided
  4. Capital Programme Monitor 2019/20 - Month 11 (February 2020)Agreed
  5. Capital Programme Monitor 2019/20 - Month 10 (January 2020)Decided
  6. Capital Programme Monitor 2019/20 - Month 9 (December 2019)Decided

More from Liverpool Finance and Resources Select Committee 2013/14

All decisions
MeetingDecisionOutcome
26 Mar 2014 Minutes of the Last MeetingAgreed that the minutes of the last meeting of this Select Committee held on 5 February 2014 be approved as a true re... Agreed Open
26 Mar 2014 Capital Programme Monitor Report for Month 10 (January 2014)Agreed that the report be noted. Agreed Open
26 Mar 2014 Revenues Service: Performance Review 2013/2014Agreed that the report be noted. Agreed Open
26 Mar 2014 Benefits Service Performance and DevelopmentAgreed that – (a) thanks be expressed to the Benefits Service Team for the work outlined; (b) efforts advised to supp... Agreed Open
26 Mar 2014 Discretionary Housing PaymentsAgreed that the report be noted and the Officers be requested include the amendments and references highlighted to th... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies