Resolved
Resolved that the recommendation be approved.
Cabinet 2010/21 approved this item on Friday 6 February 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the recommendation be approved.
Since opening on 11th October 2014 the new Great Homer Street market on Dryden Street has been an overwhelming success with visitor numbers and trader’s takings significantly up on the old location.
This report seeks authority to increase the original budget for additional works identified during the build period and to allow for some additional funding of up to £0.420m to cover the cost of the extension of the market site and the improvement of the facilities offered in response to the latent demand that has been identified to date and to deal with an overflow for customer car parking requirements.
The City Council and the market traders have a desire to make Greatie Market one of the best markets in the country which the original and additional works will go a long way towards delivering this ambition.
Cabinet of 4th April 2014 resolved that –
(i) authority be granted to develop a new market facility at Dryden Street (as part of the Project Jennifer major regeneration project);
(ii) the City Council Capital Programme is amended to reflect £2.200 m construction costs funded by the use of £0.381m of growth point monies and the balance by unsupported borrowing;
(iii) authority to commit capital expenditure;
(iv) the City Councils revenue budget be amended to reflect the debt charges; and
(v) the Council sign a Memorandum of Agreement (construction contract) with Kier Construction (Liverpool) under the Scape Minor Works Framework up to a maximum of £1.800m (including expenditure committed and spent through pre-construction stage Project Orders). In lieu of a bond, a Parent Company Guarantee is to be provided by the contractor.
The works to construct the new market have since been completed and the market opened on 11th October 2014. It has proved to be very popular with visitor numbers, trader numbers and trader takings all performing very well.
Present position
As the works have progressed it has been identified that the original budget was insufficient to pay for all the work that has been required.
A number of unforeseen events increased the cost of the project including the finding of a well that had to be filled in. It had not shown up on any plans or surveys. In addition once the buildings in Dryden Street were demolished it was found that the ground beneath them required more extensive remediation than had been anticipated.
The approved plans for the project included upgrading the existing zebra crossing opposite the market on Great Homer Street and a package of other measures to deal with traffic circulation and parking on the surrounding highway network. Detailed plans for these weren’t available at the time the original budget was set and now, with the experience of operating the market, are forecast to be more expensive than originally anticipated.
To try and keep within the budget some changes were made to the specification to reduce the cost. These included replacing a ramp from the indoor market hall to the outdoor market with steps and reducing the specification of the surfacing and lighting of the car park.
The latest estimate of costs predicts a final outturn of £2.589m. This is £0.389m above the approved budget and includes the following:
£0.247m of additional construction costs for the contract with Kier
Additional technical support costs from Mouchel to design the scheme and supervise the works of £0.016m £0.050m of additional cost to design and implement the associated highway works including upgrading the crossing, extension of the central reservation, new signage and new road markings.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
New Great Homer Street Market (RTC/19)Report | 7 pages | DownloadRead as text |
Follow Cabinet 2010/21 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Jun 2020 | Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. | Approved | Open |
| 5 Jun 2020 | Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... | Decided | Open |
| 5 Jun 2020 | Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... | Approved | Open |
| 5 Jun 2020 | Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... | Decided | Open |
| 5 Jun 2020 | Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.