Resolved
Resolved that the estimates be noted.
Audit and Governance Select Committee 2015/16 noted this item on Monday 22 February 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the estimates be noted.
1.1Under Section 25 of the Local Government Act 2003, the Authority’s Chief Financial Officer (Director of Finance and Resources) is required to report on the robustness of the estimates made for the purposes of the City Council’s Budget. The City Council approved a 3 year balanced budget for the period 2014/15 to 2016/17 in March 2014. A budget report was submitted in March 2015 that further updated and validated the robustness of estimates for 2015/16 and 2016/17. This report further validates the robustness of estimates for the financial year 2016/17 due to the final Local Government Settlement on the 8th February 2016, an increase in local funding, corporate adjustments, and an assessment of budget pressures. The size and nature of budget decisions (£156.8m over the 3 year period) has led to significant changes to the budget estimates for all services provided by Liverpool City Council.
1.2Extensive and robust financial planning and challenge has had to be undertaken at a high level to ensure that the budget is financially sustainable as well as at a detailed level to ensure that the budget decisions already taken are being delivered. There have been robust risk assessments undertaken for each budget decision which are reflected in overall terms in the Chief Financial Officers adequacy of reserves assessment which is the subject of a separate report.
1.3There will be robust review and monitoring of the overall financial sustainability of the City Council as well as the delivery of the budget decisions already taken for the financial year 2016/17 as a result of the reduced funding from central government.
2.1Budget estimates are exactly that, estimates of spending and income made at a point in time. This statement about the robustness of estimates cannot give a guaranteed assurance about the budget, but gives Members reasonable assurances that the budget has been based on the best available information and assumptions.
2.2In order to meet the requirement on the robustness of estimates a number of key processes were put into place, including:
Peer review by finance staff and the preparation of risk analysis of budget savings decisions taken in March 2014 for 2016/17. The use of monthly budget monitoring in 2015/16 in order to re- align budgets with current demand for 2016/17. The monthly monitoring of the delivery of budget decisions with detailed reports to management teams. Detailed projections of social care demographic pressures and the impact of increasing the national minimum wage in 2016/17. A comprehensive review of avoidable costs across Directorates validated by management teams, Cabinet Members and the Mayor A review by management teams of savings decisions and their achievability. A star chamber process to challenge achievability, deliverability and priority A review of the levels of unsupported borrowing in the capital programme All budget savings decisions will have an individual risk assessment and these will be placed on the corporate risk recording system (JCAD) Review of the budget by the Mayor. The Chief Financial Officer providing advice throughout the process on robustness, including underlying financial assumptions, inflationary factors, no unallocated savings and reflecting current demand and service standards (unless standards and eligibility are to be changed through a change in policy); and Scrutiny by Select Committee and consultation on budget decisions.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix 1Appendix 1 | 3 pages | Download |
PDF |
Statement of Chief Financial Officer on Robustness of Estimates 2016/17Report | 7 pages | DownloadRead as text |
Follow Audit and Governance Select Committee 2015/16 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Mar 2016 | Minutes of Last MeetingResolved that the minutes of the last meeting of the Select Committee held on 22 nd February 2016 be agreed as a true... | Agreed | Open |
| 9 Mar 2016 | Mayoral Performance UpdateResolved that consideration of this item be deferred to a special meeting of this Committee to be held on Tuesday 22 ... | Deferred | Open |
| 9 Mar 2016 | Have Your Say Half Year Report - April-September 2015Resolved that the report be noted. | Noted | Open |
| 9 Mar 2016 | Risk Management StrategyResolved that the report be approved. | Approved | Open |
| 9 Mar 2016 | Draft Strategic Internal Audit Plan 2016-19Resolved that the Strategic Internal Audit Plan 2016-19 be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.