Resolved
Resolved that the information be noted.
Audit and Governance Select Committee 2015/16 noted this item on Monday 22 February 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the information be noted.
1.1Under Section 25 of the Local Government Act 2003, the Authority’s Chief Financial Officer (Director of Finance and Resources) is required to report on the robustness of the estimates made for the purposes of the budget calculations and the adequacy of the proposed reserves. This report deals with the adequacy of the proposed reserves, which enables a longer term view of the overall position to be taken, and seeks City Council approval for the recommended level of reserves, based on an assessment of current financial risk.
1.2The City Council approved a 3 year balanced budget for the period 2014/15 to 2016/17 in March 2014 reflecting the significant reduction in controllable government grant funding, being a real terms reduction of 58% over the 6 year period from 2010. The 2015/16 and 2016/17 budgets were further updated in March 2015. The size and nature of these budget reductions have been based upon prudent financial planning assumptions and robust financial challenge as set out in the Chief Financial Officer’s robustness of estimates assessment which is the subject of a separate report elsewhere on this agenda.
1.3The risk associated with major funding reductions from central government and other external funding bodies has never been as high which and has been compounded by significant financial risks associated with major legislative changes and new burdens transferred from central to local government. In broader terms there is significant risk that the current economic situation may continue to put further pressure on central government funding.
1.4There are robust risk assessments for each budget decision which are reflected in the assessment of the level of reserves which has culminated in the proposed reduction in the general fund balance from £24.8m in 2015/16 to £17.6m in 2016/17.
1.5There will be ongoing robust review and monitoring of the risks associated with the delivery of budget savings decisions to ensure the adequacy of reserves for future years.
2.1In setting the budget for 2016/17, estimates were made of the required level of provisions, earmarked reserves and general balances. Provisions relate to known events which have occurred and that have given rise to a liability for the City Council where the exact amount or timing of the payment is not clear.
2.2In addition to known liabilities, the budget also has regard to various risk issues where at the time of setting the budget there is no contractual liability but there is a possibility that payment may be required at some point in the future. In these cases earmarked reserves are created. These reserves are established to cover specific risk issues as highlighted in the Council’s risk register.
2.3Furthermore, it is also considered prudent and best practice to make an allowance for general contingencies to cover the fact that certain budget assumptions may be inaccurate, i.e. demand for a service has proved greater than expected. Such variations are anticipated in the accompanying report on the robustness of the budget estimates and form a key driver for the level of general reserves or working balance the Director of Finance and Resources is mindful to recommend for the 2016/17 budget.
2.4There are two approaches for deciding the optimum level of the general reserves. Either a percentage of expenditure, which at one stage the Audit Commission recommended at 5% of net expenditure, or an approach based on a risk assessment of the budget, in the context of the City Council’s resourcing issues and pressures at the time.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Areas of RiskAppendix 1 | 8 pages | Download |
PDF |
Adequacy of Provisons 2016-17Appendix 2 | 1 pages | Download |
PDF |
Statement of Chief Financial Officer on Adequacy of Provisions & Reserves 2016/17Report | 9 pages | DownloadRead as text |
Follow Audit and Governance Select Committee 2015/16 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Mar 2016 | Minutes of Last MeetingResolved that the minutes of the last meeting of the Select Committee held on 22 nd February 2016 be agreed as a true... | Agreed | Open |
| 9 Mar 2016 | Mayoral Performance UpdateResolved that consideration of this item be deferred to a special meeting of this Committee to be held on Tuesday 22 ... | Deferred | Open |
| 9 Mar 2016 | Have Your Say Half Year Report - April-September 2015Resolved that the report be noted. | Noted | Open |
| 9 Mar 2016 | Risk Management StrategyResolved that the report be approved. | Approved | Open |
| 9 Mar 2016 | Draft Strategic Internal Audit Plan 2016-19Resolved that the Strategic Internal Audit Plan 2016-19 be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.