This report requests approval to proceed with the contract procurement for the construction of the new Sefton Park Vitality Trail as part of the agreed phased capital program for Sefton Park. In addition this report seeks approval to reallocate some of previously approved capital funding to deliver necessary improvement works at both Princes Park lake and Calderstones Park lake. These improvements would be an alternative to the previously proposed construction of a further sports and play facility in Sefton Park (phase 3). It is recommended that this element of Phase 3 of the program be withdrawn from the original proposals for Sefton Park in light of the affordability of the scheme and the proximity of the recently constructed Otterspool Skate Park.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
This report requests approval to proceed with the contract procurement for the construction of the new Sefton Park Vitality Trail as part of the agreed phased capital program for Sefton Park. In addition, this report seeks approval to reallocate some of previously approved capital funding to deliver necessary improvement works at both Princes Park lake and Calderstones Park lake.
These improvements would be an alternative to the previously proposed construction of a further sports and play facility in Sefton Park (phase 3). It is recommended that this element of Phase 3 of the program be withdrawn from the original proposals for Sefton Park in light of the affordability of the scheme and the proximity of the recently constructed Otterspool Skate Park.
Background
The Sefton Park Improvement Project is comprised of three phases. Phase 1 £375,000 has the aim of addressing existing infrastructure repair / improvement requirements.
The infrastructure improvement works completed to date have included:
Livingstone Dive car park resurfacing; Resurfacing of various footpaths; Tennis court refurbishment; Bowling club security fencing; Repairs and improvements to Oasis café and lakeside kiosk; Fairy Glen vegetation clearance; Mossley Hill Drive park entrance improvements.
Works remaining to be completed under this Phase include:
Fairy Glen water feature refurbishment Watercourse infrastructure repairs Surface drainage improvements to the Review Field and adjacent to the Oasis Café
The Phase 2 ‘Vitality Trail’ will be constructed along the route of the former Pony Track which runs for 1,500 m inside the western boundary of the park. It will see the construction of a new 1.7m wide macadam path with LED stud feature lighting and fitness stations with static exercise equipment.
Mouchel has been commissioned under the ESPO Framework Agreement to provide professional design and contract management services to facilitate delivery of the Vitality Trail. The design work is complete and tender package ready for issue. Mouchel’s fees to date have been met from the approved Phase 1 budget.
The pre-tender budget estimate for Phase 2 is £302,500
Phase 3 proposed the installation of a new sports and play facility in the park and the development of a mobile device application or ‘App’, to provide information about the city’s parks and upcoming events, with the aim of encouraging greater use of the new vitality trail and other fitness features. Consultation is yet to commence on this phase.
Current Position
Phase 1 is progressing within budget approval
Phase 2: Design work has been completed and tender package prepared. Budget approval is now required to enable the tender process to be actioned and the works delivered in 2017.
Phase 3: The original budget estimate of £480k for the design and installation of the bespoke facility subsequently rose to £800k excluding possible site infrastructure requirements. Furthermore the construction of a new skate park facility at the nearby Otterspool Park in 2015 led to an additional and high quality sports offer in close proximity to Sefton Park.
In light of existing provision and the increased costs of developing a further sports and play facility within Sefton Park it is proposed that the new facility is omitted from the Sefton Park Improvement Project and that the £480k funding allocation be used to finance alternative and much needed capital infrastructure improvements at the nearby Princes Park and Calderstones Park.
Way Forward
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.