Parklife Project in Partnership with the Football Association (CTE/3)

Approved Executive 1 paper

Cabinet 2010/21 approved this item on Friday 31 March 2017. Below is the council's own wording, with the papers it was decided on.

Item108

Resolved

Cabinet will recall the previous approval (CTE/6 on 4th March 2016) relative to the FA Investment Strategy ( Parklife ) proposals for Liverpool totalling circa £17m in relation to the development and construction of new third generation (3G) artificial grass pitches and ancillary facilities located strategically across the city. This report is an urgent item because the City Council will need to deliver the project within the agreed funding timescales and has only concluded extensive discussions on VAT and State Aid with Sport England and the funding partners on the 27th March which now allows the Council to expedite the delivery and implementation of the project. Any further delays will put at risk the delivery of the project. In this context, the City Council has already entered into an agreement with Sport England for up to £1.1m of funding.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet 2010/21, 14 pages

MAYORAL RECOMMENDATION All Wards PUBLIC CTE/3

Cabinet Member: Director: Councillor Wendy Simon, Assistant Ron Odunaiya – Mayor / Cabinet Member – Culture, Director for Community Services Tourism and Events

Date of submission: Subject: Parklife Project in partnership with 31 March 2017 the Football Association

Report No. CS/15/17 Contact Officer: Background papers: None Mike Kearney Interim Head of Service Sport and Recreation Service [email protected]

1.0Executive Summary: 1.1 Cabinet will recall the previous approval (CTE/6 on 4th March 2016) relative to the FA Investment Strategy (Parklife) proposals for Liverpool totalling circa £17m in relation to the development and construction of new third generation (3G) artificial grass pitches and ancillary facilities located strategically across the city.

1.2This report is an urgent item because the City Council will need to deliver the project within the agreed funding timescales and has only concluded extensive discussions on VAT and State Aid with Sport England and the funding partners on the 27th March which now allows the Council to expedite the delivery and implementation of the project. Any further delays will put at risk the delivery of the project. In this context, the City Council has already entered into an agreement with Sport England for up to £1.1m of funding. This report now seeks Cabinet approval to commit to the implementation phase of the project including;  acceptance of up to £11.5m of funding from the Football Foundation;  acceptance of up to £115,000 of capital funding from the Rugby Football Union (RFU);  acceptance of up to £127,000 one-off revenue funding from the Rugby Football Union (RFU);  for the City Council to commit to a £4.4 million capital contribution;  to procure and appoint a preferred operator (to manage the facilities);  to enter into a deed of surrender of the existing lease and grant a new 35 year lease to the MYA and then enter into the sub-lease back to the council for the Jeffrey Humble Playing Field site;  to continue to provide short-term revenue support associated with continued operation of the MYA sites estimated at £120k in 2017/18; and,  to appoint a main works contractor to deliver the overall project from the Northwest Construction Hub.

2.0Background Information

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Parklife Project in Partnership with the Football Association (CTE/3)Report 14 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Parklife Project in Partnership with the Football Association (CTE/3)This decision
  2. Parklife Project in partnership with the Football AssociationAgreed

More from Liverpool Cabinet 2010/21

All decisions
MeetingDecisionOutcome
5 Jun 2020 Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. Approved Open
5 Jun 2020 Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... Decided Open
5 Jun 2020 Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... Approved Open
5 Jun 2020 Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open
5 Jun 2020 Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies