Resolved

At its meeting of 24th June 2016, Cabinet approved the “in principle” use of compulsory purchase powers to facilitate the assembly of land to deliver the Paddington Village Scheme. Following progress in delivery of the scheme, including the production of, consultation on and approval of a Spatial Regeneration Framework (SRF), approval to make a compulsory purchase order to acquire the outstanding land interests is now sought. This report therefore seeks the Cabinet’s authority to proceed with a Compulsory Purchase Order (“the Order”) under s.226(1)(a) of the Town and Country Planning Act 1990 (“TCPA”) to facilitate the delivery of the Paddington Village scheme.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet 2010/21, 27 pages

Executive summary

At its meeting of 24th June 2016, Cabinet approved the “in principle” use of compulsory purchase powers to facilitate the assembly of land to deliver the Paddington Village Scheme. Following progress in delivery of the scheme, including the production of, consultation on and approval of a Spatial Regeneration Framework (SRF), approval to make a compulsory purchase order to acquire the outstanding land interests is now sought.

This report therefore seeks the Cabinet’s authority to proceed with a Compulsory Purchase Order (“the Order”) under s.226(1)(a) of the Town and Country Planning Act 1990 (“TCPA”) to facilitate the delivery of the Paddington Village scheme.

Appended to this report is a draft Statement of Reasons for the Order (Appendix A), Plan of the Order Land (Appendix B), Masterplan of Paddington Village Central (Appendix C), boundary of land and property to be acquired (Appendix D), flow diagram of CPO process (Appendix E) and financial implications (Appendix F - Exempt), The Mayoral Recommendations in this report are made on the basis that the Cabinet is satisfied that:

 the CPO would contribute to the economic, social and environmental well-being of the area;  there is a compelling case in the public interest and the interference with Human Rights involved is proportionate in the interests of bringing about the improvements that would follow from the carrying out of the re-development;  sufficient funds exist for carrying the resolution into effect;  the whole of the legal estate could not be acquired by agreement or could not be done within a reasonable timescale;  the land sought to be acquired is reasonably required for the purposes of the scheme underpinning the Order;  there are no significant impediments to implementation (other than the need for the CPO) and there is a reasonable prospect of its implementation should the Order be made; and,  the terms of the draft Statement of Reasons are agreed.

Background

Liverpool has a thriving and respected life sciences sector. The city combines academic excellence from its universities with world-leading healthcare facilities and internationally significant industry, largely clustered within a city centre setting known as the Knowledge Quarter. Assets include the University of Liverpool, Liverpool John Moores University, the Royal Liverpool and Broadgreen University Hospitals NHS trust, the Liverpool School of Tropical Medicine and Liverpool Science Park.

Together these facilities make a major contribution to the economy of the city, its city region and the wider economy of the Northern Powerhouse; and as such, the Mayor designated the Knowledge Quarter as a Mayoral Development Zone in 2012. This zone is complemented by national facilities at Sci-Tech Daresbury, the bio-manufacturing park in South Liverpool and global R&D centres on the Wirral.

On Monday 13 June 2016, as part of the launch of the International Festival of Business, the Mayor announced the next major phase of the growth of the city’s Knowledge Quarter, “Paddington Village”, on the former Archbishop Blanch school site. A gateway location to the city centre with a unique position with views to the waterfront; a destination of choice for research and science related business seeking the benefits of agglomeration; capable of creating upwards of 10,000 new jobs.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Approval of use of Compulsory Purchase Powers for Paddington Village (RTC/47)Report 27 pages DownloadRead as text
PDF
RTC47: Appendix AAppendix 31 pages Download
PDF
RTC47: Appendix BAppendix 2 pages Download
PDF
RTC47: Appendix CAppendix 1 pages Download
PDF
RTC47: Appendix DAppendix 1 pages Download
PDF
RTC47: Appendix EAppendix 1 pages Download

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Approval of use of Compulsory Purchase Powers for Paddington Village (RTC/47)This decision
  2. Request for Approval of Mercedes M8 and Renault NX8 Vehicle Types to be Licensed for use as Hackney CarriagesApproved
  3. The Procurement of Bulky Household Waste Collection Services; Approval of Shortlist for Tendering (E/14)Decided
  4. Buildings at Risk programme update and approval of additional external funding for the West Derby Courthouse (GI/17)Noted

More from Liverpool Cabinet 2010/21

All decisions
MeetingDecisionOutcome
5 Jun 2020 Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. Approved Open
5 Jun 2020 Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... Decided Open
5 Jun 2020 Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... Approved Open
5 Jun 2020 Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open
5 Jun 2020 Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies