The purpose of the report is to update Cabinet on the significant progress made on the new Cruise Terminal Liverpool Project and its two Supplemental Projects- Cruise Terminal Hotel and Cruise Passenger Long Stay Multi-Storey Car Park. In relation to the Cruise Terminal, following the Cabinet report on the 9th February 2018, McLaughlin & Harvey have been appointed as the Design & Build Contractor to work with the Council’s Technical Team and to progress the design to firm up construction costs. Outline Planning Permission for the project has been obtained on the 3rd April 2018, and the site investigations works needed for the detailed design of the Cruise Terminal at the Princes Jetty site has been awarded to Fugro Geoservices and they have started the borehole drilling in the River Mersey using jack up barges with a view to complete the works by June 2018. Progress in the design and preparation of the projects has continued, and in order to maintain the momentum including obtaining approvals such as the Harbour Revision Order, Marine Works Licences and also to advance the next key elements of works in the design development of the Cruise Terminal and the two Supplemental Projects, this report seeks approval to continue preparatory works and incur essential expenditure to commission further design and the preparation of all supporting documentation required to enable submission of Planning Applications for the Cruise Liner Hotel and the Multi Storey Car Park. In addition, approval is also required to commence procurement of both a high quality Brand /Franchise and a management company for the Cruise Liner Hotel.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Cabinet Member: Joe Anderson OBE Mayor of Liverpool
Director: Nick Kavanagh Director – Regeneration & Employment Services
Purpose of Report: New Cruise Terminal and Supplementary Projects - Progress update.
Date: Report No: 8th June 2018 EDR/50/18
Decision Type: Cabinet Key Decision
Executive Summary: The purpose of the report is to update Cabinet on the significant progress made on the new Cruise Terminal Liverpool Project and its two Supplemental Projects- Cruise Terminal Hotel and Cruise Passenger Long Stay Multi-Storey Car Park. In relation to the Cruise Terminal, following the Cabinet report on the 9th February 2018, McLaughlin & Harvey have been appointed as the Design & Build Contractor to work with the Council’s Technical Team and to progress the design to firm up construction costs. Outline Planning Permission for the project has been obtained on the 3rd April 2018, and the site investigations works needed for the detailed design of the Cruise Terminal at the Princes Jetty site has been awarded to Fugro Geoservices and they have started the borehole drilling in the River Mersey using jack up barges with a view to complete the works by June 2018.
Progress in the design and preparation of the projects has continued, and in order to maintain the momentum including obtaining approvals such as the Harbour Revision Order, Marine Works Licences and also to advance the next key elements of works in the design development of the Cruise Terminal and the two Supplemental Projects, this report seeks approval to continue preparatory works and incur essential expenditure to commission further design and the preparation of all supporting documentation required to enable submission of Planning Applications for the Cruise Liner Hotel and the Multi Storey Car Park.
In addition, approval is also required to commence procurement of both a high quality Brand /Franchise and a management company for the Cruise Liner Hotel.
Information:
Background / Progress Update The Previous Cabinet report on 9th February 2018 confirmed the appointment of the Stage 1 Contractor for the Cruise Terminal as McLaughlin & Harvey, and since then continued progress has been made in the finalising the design, planning, environmental and pre-construction appraisals required for final confirmation of the Cruise Terminal project.
The progress made since the last report in February 2018 is reported below:-
Outline Planning Approval The outline planning application for the cruise terminal was submitted on the 8th November 2017, with supporting documents including an Environmental Impact Assessment, a Transport Assessment, a Design & Access Statement, a Heritage Impact Assessment, and a statement of public consultation.
No objections were subsequently received and the outline planning application was approved by Planning Committee on the 3rd April 2018, with agreed conditions and reserved matters.
Single Investment Fund (SIF) That Outline Business Case has been appraised by the Combined Authority’s representative consultants, and was approved by the Combined Authority Investment Panel on the 27th November 2017,
The Council submitted the Full Business Case application, containing further detailed appraisals and information on 31st March 2108. The application is now being appraised by the Combined Authority for a final decision.
Site Investigations The site investigation works contract has been awarded to Fugro Geoservices and the investigations on land needed for to the Cruise Terminal commenced on the 8th May and scheduled to be completed on the 26th June 2018.
The Council has also secured the appropriate Marine Licences from the Marine Management Organisation (MMO) for the works associated with investigation works within the River Mersey at the Princes Jetty Site.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.