Project design and development for potential Heat Network along the Liverpool Waterfront and Docklands (STA/12)

Decided Executive 1 paper

Cabinet 2010/21 decided this item on Friday 22 March 2019. Below is the council's own wording, with the papers it was decided on.

Item110f

Resolved

Project design and development for potential Heat Network along the Liverpool Waterfront and Docklands.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet 2010/21, 9 pages

CABINET

CITY PUBLIC STA/12

Cabinet Member: Councillor James Noakes Cabinet Member – Street Scene, Highways & Transport and Air Quality

Director: Ron Odunaiya Director – Community Services

Purpose of Report: Project design and development for potential Heat Network along the Liverpool Waterfront and Docklands.

Date: Report No: 22 March 2019 CS/07/19

Decision Type: Cabinet Key Decision

Executive Summary: Following a positive feasibility study this report seeks Cabinet approval for: (i) Acceptance of a grant offer of £100,500 as 67% towards the completion of detailed design and development work on a Water Front Heat Network. (ii) Acceptance of offers of a minimum £20,000 match funding payments from external organisations to support the work. (iii) Approval for the payment of up to £29,500 from Liverpool City Council to provide match funding

Information:

Background In October 2017, Cabinet gave approval for the City Council to apply for funding from the Government Department of Business Energy and Industrial Strategy (BEIS) Heat Network Delivery Unit (HNDU), to assess the feasibility of a commercially viable heat network along the Liverpool waterfront. The City Council secured the HNDU grant of £64,000 towards the costs of the feasibility study with additional match funding of £40,000 from the Liverpool Waterfront Business Partnership; Peel Water Services; the Canals and Rivers Trust (C&RT), and Liverpool City Council.

The feasibility study is now being finalised. Appendix One shows the study area. Within this area expert consultants have liaised with building managers and with the District Network Operator, and modelled different technical solutions to see if there is potential for a new network of heat pipes along the waterfront that could supply heat to key buildings at a lower cost than the owners are currently paying.

UK Heat networks are mostly powered from gas engines but in Liverpool’s case the work has looked in particular at whether low carbon renewable heat can be extracted from the Docks or the River Mersey using heat pumps and converted to supply heat to local buildings.

Heat network are common across Europe and growing within the UK. To put heat network development work in context Government BEIS HNDU are investing up to £320m over the next 5 years to support the development of heat networks across England and Wales and projects are developing in most of the Core cities. Liverpool City Council is already developing a heat network to support the Paddington Village development and Peel Energy are currently on site with preliminary works to build a heat network coming down from the North Docks and servicing Liverpool Waters and Princes Parade.

The link below gives an example of a water sourced heat project in Scotland https://www.edie.net/news/8/Scotland-receives-green-light-on-large-scale- water-source-heat-pump-project/

The Liverpool Waterfront feasibility study shows that there are clusters of buildings along the waterfront from the 3 graces to the M&S Arena where there are both interested and willing owners and technically viable solutions that would support a commercially viable project. In particular a central cluster based around the 3 Graces and a southern cluster based around the M&S Arena. Across all the different building cluster scenarios and across multiple phasing options, there are viable options with capital investment requirements varying from between £11million to £30 million. The different options give widely varying Rates of Return on Investment (IRR) between 1% a year over 25 years to 9%.a year over 25 years.

There are also parts of the area closest to the North Docks where there may be options to develop accelerated proposals in partnership with the adjacent private sector-led networks that warrant further consideration.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Project design and development for potential Heat Network along the Liverpool Waterfront and Docklands (STA/12)Report 9 pages DownloadRead as text

More from Liverpool Cabinet 2010/21

All decisions
MeetingDecisionOutcome
5 Jun 2020 Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. Approved Open
5 Jun 2020 Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... Decided Open
5 Jun 2020 Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... Approved Open
5 Jun 2020 Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open
5 Jun 2020 Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies