Acceptance of Highways Capital Funding for Liverpool Loop Line (RH/8)

Decided Executive 2 papers

Cabinet 2010/21 decided this item on Friday 7 February 2020. Below is the council's own wording, with the papers it was decided on.

Item242a

Resolved

This report is seeking permission to accept funding from European Regional Development Fund (£249,963) and Transforming Cities Fund (£249,963) through Liverpool City Region Combined Authority for a Green Cycling and Walking scheme on the Liverpool Loop Line.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet 2010/21, 6 pages

CABINET

CITY PUBLIC RH/8

Cabinet Member: Cabinet Member – Regeneration & Highways

Director: Director – Finance & Resources

Report Title: Acceptance of Highways Capital Funding for Liverpool Loop Line.

Date: Report No: 7th February 2020 EDR/85/19

Decision Type: Cabinet Key Decision

Executive Summary: This report is seeking permission to accept funding from European Regional Development Fund (£249,963) and Transforming Cities Fund (£249,963) through Liverpool City Region Combined Authority for a Green Cycling and Walking scheme on the Liverpool Loop Line.

Information:

Background The Strategic Green and Open Spaces Review Final Report 2016 identified the need for investment in a ‘Green Web’ network across Liverpool identifying four specific corridors overlaid into key highway priorities. Investment has already been secured via Horizon 2020 funding, for the area between Baltic Triangle and the waterfront. The Sustainable Urban Development (SUD) programme presents the opportunity to further this investment in Liverpool.

The final version of the LCR Sustainable Urban Development (SUD) Strategy was approved by Government in November 2016 and the SUD call was launched by the Department for Communities and Local Government (DCLG) on 30 June 2017. The LCR Combined Authority (LCRCA) agreed to act as the region’s Intermediary Body or Designated Urban Authority for the SUD. DCLG

V1.1/060919 – 170919 onwards has been responsible for assessing bids through a two stage process with the Combined Authority’s outline SUD applications being submitted on 15 September 2017.

The LCR SUD Strategy is split into 3 strands to be delivered over a three year period:  Strand 1 Creating green walking and cycling corridors  Strand 2 Innovative measures to promote sustainable travel  Strand 3 Encouragement of alternatively fuelled Local Authority vehicles.

Under Strand 1 & 2 the LCRCA was invited by the Ministry of Housing, Communities and Local Government (MHCLG, formally DCLG) to proceed to Full Application and a bid 2 for £16.8m was submitted on 15 February 2018, of which £8.3m is matched funding. The application has now been assessed and confirmation has been received that the proposal has been approved along with a Grant Funding Agreement (GFA).

ERDF projects require match funding, therefore £4.8m of the £8.3m match funding has been approved by the Combined Authority from the Transforming Cities Fund (TCF). On the 27 July 2018, the Combined Authority approved the Commissioning approach for the Transforming Cities Fund. This included the invitation for the ‘Match Funding in respect of the priority ERDF Sustainable Urban Development (SUD) programme of green travel for cyclists’. The additional £3.5m contribution is from Local Authorities, Sustainable Transport Enhancements Package funding, S106 and Integrated Transport Block.

PROPOSALS – Strand 1 & 2 A consortium of partners has been assembled including Merseytravel (lead partner for the bid), Halton Borough Council, Knowsley Borough Council, Liverpool City Council, Sefton Borough Council, St Helens Borough Council, Wirral Borough Council and Liverpool John Moores University.

Each partner will be responsible for delivering their element of the project with Merseytravel acting as programme co-ordinator. As per the standard process for ERDF projects, partners will submit quarterly claims to the LCR European Structural and Investment Fund (ESIF) Compliance Team to draw down on the European Regional Development Fund (ERDF) funding secured.

The SUD Programme was developed by the LCR Transport Partnership Officers who sought to identify routes which were aligned to the SUD Strategy, these schemes form the first phase of the Local Cycling and Walking Infrastructure Network which is currently being developed.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Acceptance of Highways Capital Funding for Liverpool Loop Line (RH/8)Report 6 pages DownloadRead as text
PDF
Appendix 1Appendix 1 5 pages Download

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Acceptance of Highways Capital Funding for Liverpool Loop Line (RH/8)This decision
  2. Acceptance of Highways Growth & Maintenance Funding (R/25)Approved

More from Liverpool Cabinet 2010/21

All decisions
MeetingDecisionOutcome
5 Jun 2020 Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. Approved Open
5 Jun 2020 Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... Decided Open
5 Jun 2020 Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... Approved Open
5 Jun 2020 Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open
5 Jun 2020 Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies