Wavertree Primary School – Extension Refurbishment (E/14)

Decided Executive 1 paper

Cabinet 2010/21 decided this item on Friday 20 March 2020. Below is the council's own wording, with the papers it was decided on.

Item2b

Resolved

Due to issues with water ingress and poor thermal performance in the extension at Wavertree Primary School, Kier have produced a refurbishment design to include replacing existing roofing, replacing the glazed curtain walling with a Steel Framed System (SFS) and replacing the existing heating system in the extension. This Cabinet report seeks authority to award the works up to a projected contract sum of £485,000 to expedite the project for an April 2020 start on site and to ensure completion for September 2020.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet 2010/21, 5 pages

CABINET

WAVERTREE WARD PUBLIC E/14

Cabinet Member: Cabinet Member – Education, Employment & Skills

Director: Director – Regeneration & Economy

Report Title: Wavertree Primary School – Extension Refurbishment

Date: Report No: 20 March 2020 EDR/10/20

Decision Type: Cabinet

Executive Summary: Due to issues with water ingress and poor thermal performance in the extension at Wavertree Primary School, Kier have produced a refurbishment design to include replacing existing roofing, replacing the glazed curtain walling with a Steel Framed System (SFS) and replacing the existing heating system in the extension. This Cabinet report seeks authority to award the works up to a projected contract sum of £485,000 to expedite the project for an April 2020 start on site and to ensure completion for September 2020.

Information: Further to condition survey data and school feedback highlighting ongoing issues with an extension added to the school approximately 20 years ago including; water ingress (poorly performing roof design) and thermal inefficiency (too hot in the summer and too cold in the winter due to fully glazed curtain walling with no adequate ventilation) Kier produced a feasibility study to identify solutions to address these issues.

The works include a replacement roof with an alternative roof finish design to improve performance, replacing the existing glazed curtain walling with an SFS finish to improve thermal efficiency and replace the heating system in the extension with one connected to the main system as currently it is operated from a domestic boiler which is not suitable for use.

Since decanting of the Early Years (Nursery, Reception and year 1) will be required to hand over the extension to the contractor, the school have requested that works commence towards the end of the current term and complete before the new academic year. To relocate Nursery and Reception children in temporary accommodation at the beginning of a new academic year will prove very disruptive. Decanting them once they are already familiar with the school site will prove easier to manage.

This requires a proposed start on site of 20 April 2020 with a proposed completion on the 28 August 2020. For clarity, the provision of temporary accommodation has been procured separately and will be subject to separate reporting arrangements.

One other factor for consideration is the school playground is remote from the school building, separated by an un-adopted highway ‘Rose Villas’, with no land available on the school site for a builder’s compound. Agreement has therefore been reached with the management company of Abbeygate Apartments to use an overflow car park to the rear of the school at a cost of £500 per week and a licence will be required to formalise this occupation.

A pre-procurement business case has been approved for this project and tenders were returned on the 14th February 2020. 4 tenders were received of which 3 were fully compliant. One the basis of the Most Economically Advantageous Tender (MEAT), contract award is recommended to Krol Korlett in the sum of £514,838.00. Financial Standing Checks have been undertaken and passed with low risk, and the price breakdown has been checked and is confirmed to be error-free.

Recommendation: That –

(i) the City Council commits expenditure up to a value of £592,567.00 to be financed from the School Condition Allocation grant funding. The expenditure comprises a contract sum of £514,838.00, design, cost management and Construction, Design and Management fees, compound licence fees and additional survey costs for investigations including asbestos survey;

(ii) in respect of the contract works, the City Council approves the contact award of £512,838.00 under a Joint Contracts Tribunal Standard Works contract; and

(iii) the City Council’s capital programme be amended accordingly and authority granted to commit the expenditure within the approval. Financial Implications:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Wavertree Primary School: Extension Refurbishment (E/14)Report 5 pages DownloadRead as text

More from Liverpool Cabinet 2010/21

All decisions
MeetingDecisionOutcome
5 Jun 2020 Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. Approved Open
5 Jun 2020 Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... Decided Open
5 Jun 2020 Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... Approved Open
5 Jun 2020 Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open
5 Jun 2020 Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies